ML18155A392
| ML18155A392 | |
| Person / Time | |
|---|---|
| Site: | 05200046 |
| Issue date: | 06/04/2018 |
| From: | Kim H Korea Hydro & Nuclear Power Co, Ltd |
| To: | William Ward Document Control Desk, Office of New Reactors |
| Shared Package | |
| ML18155A391 | List: |
| References | |
| MKD/NW-18-0083L | |
| Download: ML18155A392 (2) | |
Text
70-1312-gil, Yuseong-daero, Yuseong-gu, Daejeon, 34101, KOREA Tel: +82-42-870-5400 / Fax: +82-42-870-5449 http://www.khnp.co.kr June 4, 2018 Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attention: Mr. William Ward Docket No.52-046 Division of New Reactor Licensing MKD/NW-18-0083L
Subject:
Revised Response to RAI 297-8309 for Question 19.03-2 (Rev.1)
References:
- 1) NRC Request for Additional Information 297-8309, dated November 9, 2015
- 2) KHNP Letter MKD/NW-16-0559L, Response to RAI 297-8309 for Question 19.03-2, dated May 30, 2016 KHNP is hereby submitting the revised response to RAI 297-8309, dated November 9, 2015. The revised response addresses Question 19.03-2 relating to change from mobile GTG to mobile generator. The enclosure provides the revised response to RAI 297-8309 for Question 19.03-2 (Rev.1) (Non-Proprietary).
If additional information or clarification is required, please contact Daegeun Ahn, Director of KHNP Washington DC Center at ahn.daegeun@khnp.co.kr or 703-388-0592.
Sincerely, Han-gon Kim Project Manager Advanced Reactors Development Laboratory Korea Hydro & Nuclear Power Co., Ltd.
Enclosure:
Revised Response to RAI 297-8309 for Question 19.03-2 (Rev.1) (Non-Proprietary)
Enclosure Revised Response to RAI 297-8309 for Question 19.03-2 (Rev.1)
(Non-Proprietary)
June 4, 2018