OFFICIAL COPY FEB 2 o 1991.

Docket Nos. 50-280, 50-281

  • Li~ense Nos. DPR-32, DPR~37 Vi rgi ni a Electric and Power Company.
  • ATTN:

Mr. W.

  • L. Stewart Senior Vice P~esident - Nuclear
  • ~000 Domi.nion.Boulevard Glen Allen~ VA 23060 Gentlemen:

SUBJECT:

MANAGEMENT MEETING

SUMMARY

This letter refers to the Management Meetings held on February 6, 1991, at your

. Innsbrook Technical Center in Glen Allen, VA.

.The two meetings concerned activities.authorized for your Surry facility and involved discussions related to long~term corrective action to service water macrofouling problems and the scheduling and content for the April 1991 Unit.2 refueling outage~

A list of.

  • attendees, meeting summaries, and a copy of your handouts are enclosed.

Based on the ongoing and planned servite water cor~e~tive actioni discussed in the

.presentation, the NRC c,oncurs in the continued operation of Surry l anq 2 *...

We request that you keep us informed of the results of i~spection and testing conducted during the Unit 2 outage..

In accordance with Section 2.790 of the NRC 1s 11Rules of Practice, 11 Part 2, Title 10, Code of Federal Regulations, a copy of. this letter and its enclosures will be placed in the NRC Public Document Room.

~ Should yo~ have any questions conc~rnirig this matter, please cont~ct us.

Enclosures:

1.

List of Attendees

2.

Meeting Summary.- Service Water

3. Meeting Summary - Outage
4.

Handout - Service Water

5.

Handout - Outage cc w/encls:

(See -page 2) 9,1030502& 910220

!?DR ADOCK 05000280 p

PDR Sincerely,..

Original Signed by

.Luis A. Reyes Luis A. Reyes, Director

. Division of Reactor Projects

Virginia Electric and Power Company

2.

cc w/encl s :-

E*. W. Harrell Vice Pre~ident - Nuclear Operatibris

  • Virginia Electric & Power Company 5000 Dominion Bo~levard Glen Allen, VA* 23060 J. P. 0 1Hanlon Vice President - Nuclear Services Virginia Electric & Power Company 5000 Dominion Boulevard Glen Allen, VA 23060 M. R. Kansler Station Manager Surry Power Sta ti o*n P. 0. Box 315

. Surry, VA 23883 M. L. Bowling-, Jr., Manager Nuclear Licensing

. Virginia Electric & Power Co.

5000 Dominion Boulevard Glen Allen,* VA 23060

  • Sherlock Holmes, Chairman Board of Supervisors of Surry County Surry County Courthouse Surry, VA 23683 W. T. Lough Virginia Corporation Commission*

Division of Energy-Regulation P. 0. Box -1197.

Richmond, VA 23209 Michaei W. Maupin Hunton and William~

P. 0. Box 1535 Richmond; VA 23212 C. M. G. Buttery, M.D., M.P.H.

Department of Health 109 Governor Street Richmond, VA 23219 Attorney General Supreme Court Building 101 North 8th Street Richmond, VA 23219 Commonwealth of Virginia bee w/encls:

(See page 3)

FES 2.o 1991.

Virginia Electric and Power.Company 3

~c w/encl s:

\\.-*1)ocument Control Desk

  • P. Fredrickson, RI1 B~ Buckley, NRR.

NRC_ Resident Inspector U.S. Nuclear Regulatory Commission Route 1, Box 166

.*

  • Surry, VA. 23883. __

NRC Resident Inspector U.S. Nuclear Regulatory Commission R6ute.2, Box 78~A:

Miner~l, VA 23117 RII:~.

Pfrel;ii~kso:FC:er 021.,.l91 RII :DRP

. WJ5 MSrnkule 02J_/) /91 FEB 2 0 1991

ENCLOSURE 1 LIST OF ATTENDEES Virginia Electric and Power Company (Virginia Power)

W. Harrell, Vice President, Nuclear Operations K. Moore, Vice President~ Nuclear Engineering Services R. Saunders,.Assistant Vice President, Nuclear Operations M. Kansler, Station Manager, Surry J. Price, Assistant Station Manager, Surry M. Bowling, Manager, Nuclear Licensing and Programs E. Grecheck, Manager, Nuclear Engineering D. Sommers, Supervisor, Surry Licensing R. Cherry, Licensing Engineer R. Prideaux, Licensing Engineer W. Benthall, Licensing Engineer, Surry

  • W. Corbin, Supervisor, Project Engineering V. West, Nuclear Specialist Nuclear Regulatory Commission, Region II L. Reyes, Director, Division of Reactor Projects (DRP), Regiori II (RII)
  • A. Gibson, Director, Division of Reactor Safety, RII M. Sinkule, Chief, Reactor Projects Branch 2, DRP, RII P. Fredrickson, Chief, Reactor Projects Section 2A, DRP, RII W. Holland, Surry Senior Resident Inspector, DRP, RII

.Nuclear Regulatory Co11111i ssi on, Headquarters H. Berkow, Director, Project Directorate II-2, Office of Nuclear Reactor Regulation (NRR)

J. Wechselberger, Regional Coordinator, Office of the Executive Director of Operations

8. Buckley, Surry Project Manager, NRR L. Engle, North Anna Project Manager, NRR
  • N. Wagner, Plant Systems Branch, Division of Systems Technology, NRR
  • S. Jones, Plant Systems Branch, Division of Systems Technology, NRR

ENCLOSURE 2 SERVICE WATER MANAGEMENT MEETING

SUMMARY

A meeting was conducted at the Virginia Power Innsbrook Techni~al Center in Glen Allen, Virginia on February 6, 1991, in order to _discuss long-tenn.correc-tive action for the Surry service water macrofoul ing_ problem.

The Vice President, Nuclear Operations opened the meeting by stating that the service water macrofouling problem had been thoroughly analyzed by Virginia Power.

The Supervisor, Project Engineering then conducted the presentation using the handout in Enclosure 4.

In addition, drawings not provided in the handout were referenced during the presentation.

Discussion ensued on the macrofouling mechanisms, specifically as they r~lated to the pipe coating effort and the.

inspection activity on the discharge piping.

Additional discussion took place on the effect of fish and other marine life on heat exchanger fouling.

Service

  • water biological control measures and the alternate operation of the 48 11 service water lines was also discussed in detail. With respect to the service water testing of Unit 2 during the April 1991 outage, the NRC recommended selecting the 11worst case" header for testing.

Virginia Power stated-they would consider that approach.

The 1 ong-tenn service water study w~s al so discussed.

The study will include all piping that flows service water.

A subset discussion ensued on* the inspecting that* ensured that the emergency service water pumps were not macrofouled.

The conclu~ion of the meeting was a presentation by the Manager, Nuclear Licensing and Programs on the basis for continued operation, using the same handout.

The NRC concurred that the Virginia Power testing and inspection was sufficient to warrant continued operation of both units.

The meeting was concluded with the NRC stating that Virginia Power had made a reasonable approach to resolving the problem, but that further testing and inspection was necessary to determine the exact cause and effect of the problem and implement a long-tenn corrective action plan.

ENCLOSURE 3 OUTAGE MANAGEMENT MEETING

SUMMARY

A meeting was conducted at the Virginia Power Innsbrook Technical Center in Glen Allen, Virginia on February 6, 1991, in order to discuss the April 1991 Unit 2 refueling outage.

The meeting was opened by the Vice President, Nuclear

  • Operations, who stated that the goal of Virginia Power is to conduct a safe, well-managed outage.

In addition, he stated that Virginia Power was in process of developing a five-year planning schedule.

The schedole would be impacted on a yearly basis by the availability of people and money.

The Surry Station Manager then conducted the Unit 2 outage presentation using the handout in.

At present, the outage is scheduled to commence on April 5, but may start one or two weeks earlier. Discussions were conducted on the planned improvements and also on the rescheduled and reassessed improvements.

Specific cormnitment schedule changes were then discussed.

Virginia Power closed the meeting by stating that lessons learned from the 1990 Unit 1 outage are being integrated into the Unit 2 outage, and that very serious discussion took place prior to rescheduling work out of the Unit 2 outage.

ENCLOSURE 4 VIRGINIA POWER SURRY POWER STATION MANAGEMENT MEETING -

FEBRUARY 6, 1_991.

SERVICE WATER TO RECIRCULATION SPRAY HEAT EXCHANGERS

I.

AGENDA INTRODUCTION ~ E. W. HARRELL MACROFOULING MECHANISMS AND SOLUTIONS - W. D. CORBIN BASIS FOR CONTINUED OPERATION-M. L. BOWLING

MACROFOULING MECHANISMS AND SOLUTIONS W. D. CORBIN SUPERVISOR - PROJECT ENGINEERING

  • I RECIRC SPRAY HEAT EXCHANGER FOULING MECHANISM~ AND SOLUTIONS MACROFOULING MECHANISMS.

FLAKES OTHER MATERIALS HYDROIDS HYDROID BIOLOGY BIOLOGICAL CONTROL MONITORING & SAMPLING INSPECTIONS & TESTS LONG TERM STUDY FOR BIOLOGICAL CONTROL INSTRUMENTATION STUDY 1-

MACROFOULING MECHANISMS.

FLAKES FLAKES CONSISTED OF. COAL TAR COATING AND ADHERENT SCALE FLAKES CAME FROM THE PIPE JUST UPSTREAM OF THE HEAT EXCHANGERS PRIOR TO RSHX REPLACEMENT THIS PIPE WAS OFTEN IN AN UNCONTROLLED WElTED CONDITION SPECIFIC CONTROLS ARE NOW IN PLACE TO ENSURE.VERTICAL

  • RISERS AND HEAT EXCHANGERS ARE DRAINED

.. I I

MACROFOULING MECHAN_ISMS FLAKES (continued)

  • INLET SW PIPING WAS INSPECTED IN UNIT 1 AND UNIT* 2
  • AREAS OF SCALE DEPOSITS WERE HYDROLASED AND/OR SAND BLASTED
  • A WET LAYUP BOUNDARY HAS aEEN ESTABLISHED FOR A PORTION OF THE SW PIPE TO-REDUCE INRUSH VELOCITIES
  • THE WET LAYUP BOUNDARY IS BEING CHEMICALL V.

CONTROLLED TO REDUCE THE CORROSION RATE AND PROVIDE BIOLOGICAL CONTROL FUTURE OUTAGES WILL 1CONTINUE THE PROGRAM OF INSPECTION, CLEANING, BLASTING, COATING AND PIPE REPLACEMENT FOR AFFECTED SECTIONS AS REQUIRED

MACROFOULING MECHANISMS OTHER MATERIALS PRESENCE OF SILT IS NOT A SIGNIFICANT TUBE BLOCKING -

MECHANISM

  • _ SOME SMALL SHELL, EEL AND CRAB PARTS WERE DISCOVERED

- - EELS ARE "BOTIOM DWELLERS" THAT ARE NOT LIKEL V TO. -

GET UP INTO THE SW HEADERS INSPECTIONS OF THE CONTINUOUS SERVICE COMPONENT COOLING HEAT EXCHANGERS INDICATE THAT SHELLS, EELS AND CRABS ARE NOT A SIGNIFICANT LONG TERM TUBE BLOCKING MECHANISM

-- - - - - - ~ ~ ~ ~ ~

MACROFOULING MECHANISMS HVDROIDS HYDROIDS WERE FOUND IN THE 48" SW HEADERS, THE 96" CW

. PIPE AND THE INTAKE STRUCTURE

  • INSPECTIONS REVEALED THAT THE HVDROID SOURCE FOR RSHX BLOCKAGE WAS PREDOMINANTL V THE 48" SW HEADERS DUE TO INITIAL FLOW INRUSH VELOCITIES

HVDROID BIOLOGY BIOLOGICAL PARAMETERS

-, VIRGINIA INSTITUTE OF MARINE SCIENCES (VIMS) HAS IDENTIFIED SEVERAL SPECIES. DOMINANT SPECIES IS A.HYDROID - GARVEIA FRANCISCAN A OTHER SPECIES OF HYDROIDS AND BRYOZOANS ARE ALSO PRESENT ALL SPECIES ARE OF THE LOW SALINITY TYPE

HYDROID BIOLOGY (CONTINUED)

THEY FEED ON ZOOPLANKTON, PROTOZOANS, AND OTHER ONE CELLED ORGANISMS OPTIMAL GROWTH OCCURS WHEN WATER TEMPERATURE IS ABOVE -57°F, OXYGEN IS PRESENT, SALINITY IS BETWEEN 1-15 PPT (5-10 PPT OPTIMUM) AND A HARD SUBSTRATE.IS PRESENT FOR ATTACHMENT PLANULA PHASE (FREE SWIMMING) IS SHORTER THAN GROWTH PERIOD BUT VARIES BY GEOGRAPHICAL LOCATION

BIOLOGICAL CONTROL

  • ALTERNATE STAGNATION OF 48" SW SUPPLY HEADERS IS CURRENTLY IN PROGRESS FOR UNIT.1. WEEKLY STAGNATION.

LIMITS BOTH FOOD AND OXYGEN'-SUPPLIES VIMS CONCLUDES THIS IS A SUFFICIENT ACTION TO CONTROL I

HYDROID GROWTH

  • AS ADDED PROTECTION, CHEMICAL TREATMENT TO CONTROL HYDROID GROWTH WILL BE INITIATED.PRIOR TO THE START OF AND CONTINUED THROUGHOUT THE HYDROID OPTIMUM GROWING SEASON

- 2 PPM RESIDUAL CHLORINE WILL BE MAINTAINED ON STAGNANT LINES I

. i

MONITORING AND SAMPLING MONITORING AND SAMPLING PROGRAMS WILL BE INITIATED PRIOR TO UNIT 2 REFUELING OUTAGE TO CORRELATE SAMPLING DATA WITH VISUAL INSPECTION RESULTS

- VISUAL OBSERVATIONS IN KEV SW PIPING BY BOROSCOPE AND SIDE STREAM SAMPLING WILL BE PERFORMED

- "HVDROLAB" SURVEYOR ON INTA*KE AND DISCHARGE CANALS WILL CONSTANTLY MONITOR FOR TEMPERATURE, SALINITY, AND DISSOLVED OXYGEN

- GRAB SAMPLES AT THE INTAKE AND DISCHARGE CANALS WILL BE*

TAKEN PERIODICALL V. PERIOD IS DEPENDENT ON ACTIVITY SEEN

-* CHLORINE AND AMMONIA WILL BE MONITORED TO ASSURE 2 PPM CHLORINE RESIDUAL AND *TO CORRELATE AMMONIA PRESENCE TO SAMPLES

TEST AND INSPECTIONS A FLOW TEST WILL BE PERFORMED ON ONE RECIRCULATION SPRAY SW SUBSYSTEM DURING THE UNIT2 REFUELING.OUTAGE TO ASSESS THE EFFECTIVENESS OF THEMACROFOULING CONTROL TECHNIQUES AN 'AS-FOUND' INSPECTION WILL BE PERFORMED ON THE OTHER SW SUBSYSTEM THE FLOW TESTED SW SUBSYSTEM WILL BE INSPECTED AFTER THE FLOW TEST A COMPARISON OF THE INSPECTION RESULTS WILL BE PERFORMED I

VIMS TO PARTICIPATE IN THESE INSPECTIONS I

LONG-TERM STUDY FOR BIOLOGICAL CONTROL VIMS RETAINED FOR STUDY OF THE ECOSYSTEM DR.. D. CALDER OF THE ROYAL ONTARIO MUSEUM HAS BEEN RETAINED BY VIMS. HE.IS A WORLD RENOWNED AUTHORITY ON HYDROID ECOSYSTEMS CALGON HAS BEEN RETAINED TO PROVIDE CHEMICAL CONTROL

. EXPERTISE

LONG-TERM STUDY FOR BIOLOGICAL CONTROL (continued)

SCOPE OF STUDY INCLUDES ENTIRE SW ECOSYSTEM DOCUMENTATION SEARCH AND DESCRIPTION OF ANY SPECIES TEMPERATURE AND SALINITY PROFILES FOR GROWTH FLOW TESTING COUPON TESTING CHLORINE TOLERANCE TESTING RESULTS FROM ON-LINE SAMPLE PROGRAM

LONG-TERM STUDY FOR BIOLOGICAL CONTROL (continued)

  • POSSIBLE MODIFICATIONS TRAVELLING SCREENS STRAINERS IN THE SW SUPPLY LINES CHEMICAL OR OTHER CONTROL

INSTRUMENTATI.ON STUDY RECIRC SPRAY SW INLET AND OUTLET FLOW INSTRUMENTS DID NOT PERFORM WELL DURING THE *RECENT TESTS.

THE INSTRUMENTATION WAS SUBJECT TO AIR BINDING AND.

FOULING ALTERNATIVES ARE BEING REVIEWED TO RESOLVE THESE PROBLEMS SCHEDULE - ENGINEERING STUDY IN PROGRESS WILL.

COMPLETE IN SEPTEMBER 1991

BASIS FOR*

CONTINUED OPERATION M. L. BOWLING

. I MANAGER - NUCLEAR LICENSING & PROGRAMS

BASIS FOR CONTINUED OPERATION HVDROID GROWTH.IN AND DETACHMENT FROM THE SW PIPING IS THE ONL V SIGNIFICANT POTENTIAL BLOCKAGE MECHANISM FOR THE RSHX

//

OPERATIONAL ACTIVITIES INITIATED IN NOVEMBER 1990 WILL MINIMIZE HVDROID GROWTH AND ANY ADVERSE EFFECTS

  • REMOVAL OF HVDROIDS AND OTHER MACROFOULING SOURCES FROM THE SW PIPING TO.RSHXs.

f ALTERNATING SW HEADER FLOW TO CONTROL GROWTH FILLING SW TO RSHX PIPING TO REDUCE THE INRUSH VELOCITIES AND CORROSION ACCORDING TO VIMS, HYDROID GROWTH*SHOULD BE REDUCED SINCE THE OCTOBER 1990 CLEANING DUE TO COLDER TEMPERATURES

BASIS FOR CONTINUED OPERATION (continued)

CONTINUOUS CHEMICAL TREATMENT TO CONTROL HVDROID GROWTH WILL BE INITIATED PRIOR TO START OF THE OPTIMAL HVDROID GROWTH SEASON MONITORING AND SAMPLING PROGRAMS WILL BE INITIATED TO DETECT MACROFOULING FROM ALL SOURCES VISUAL OBSERVATIONS IN KEV SW PIPING SAMPLING IN KEV LOCATIONS I

BASIS FOR CONTINUED OPERATION (continued)

UNIT 2 AND UNIT 1 SW SUBSYSTEMS WILL BE FLOW TESTED AND

  • INSPECTED DURING THE APRIL 1991 AND APRIL 1992 REFUELING

. OUTAGES RESPECTIVELY TO VERIFY EFFECTIVENESS OF PREVIOUS ACTIVITIESAND TO VALIDATE ASSUMPTIONS ON HYDROID GROWTH PERIODIC INSPECTION AND CLEANING OFSW HEADERS WILL BE CONTINUED THE PROGRAM TO INSPECT AND UPGRADE SW PIPE COATINGS WILL BE CONTINUED I

I 1

ENCLOSURE 5 VIRGINIA POWER I

1991 UNIT 2 REFUELING OUTAGE SCOPE MEETING

  • FEBRUARY 6, 1991

---* ~------

OPENING REMARKS

  • E.W. HARRELL J

VICE PRESIDENT - NUCLEAR OPERATIONS

. UNIT 2 OUTAGE SCOPE M. R. KA.NSLER SURRY STATION MANAGER

I I I UNIT 2 OUTAGE ENHANCEMENTS M

  • PERFORM 1 OCFR50.59 SAFETY ANALYSES FOR OUTAGE ACTIVITIES l

OUTAGE SAFETY FUNCTION ASSESSMENTS DEVELOP RESTART LIST WllH OUTAGE PLAN

  • UN.IT 2 OUTAGE WORK *SCOPE TOTAL OUTAGE DURATION - 67 DAYS PRIMARY AND SAFETY SYSTEM INSPECTION/MAINTENANCE ACTIVITY REACTOR.REFUELING STEAM GENERATORS REACTOR COOLANT PUMPS AND MOTORS INSIDE RECIRCULATION SPRAYPUMPS DIESEL GENERATORS SAFETY SYSTEMS CONTROL ROOM/ESGR AIR HANDLING UNITS TYPE A TEST DURATION*

49 DAYS 25 DAYS 50 DAYS 7DAYS 14 DAYS.

21 DAYS 51 DAYS 5 DAYS

UNIT 2 OUTAGE WORK SCOPE (continued).

TURBINE/GENERATOR AND SECONDARY SYSTEMS ACTIVITY TURBINE GENERATOR SECONDARY SYSTEMS DURATION 48 DAYS 48 DAYS 50 DAYS MISCELLANEOUS WORK CMs, PMs, REPACKS, SNUBBERS I

i, II.. a a

I I

I

.;..r;~.:-

1'"' * ' -'

J.......,......, *-

~

9"'*"1..... t lau'"

~,...

14 I

I I

t S

I 1

I 11 11 11 I

It I

11 11 1* *a VIRGINlfl PUWLR * ~l<HYPOWlR SIIHION lJ.? PR[IIM llVfl I RIIU(IIN6 SCH[DIJLE.

JIMI

(.,-,, 1 rr.,nr1i* "'*""*nrao l'J. II a a 11 II 14 II Ill I

I t

I. '

I 1

I II II I/

i(O l!i/~V I

001.*

ft "rDmlN

PLANNED IMPROVEMENTS DESCRIPTION BASIS STATUS INDEPENDENT RCS LEVEL INDICATION COMMITMENT PLANNED EMERGENCY VENT DAMPERS & SEMI VITAL BUS COMMITMENT PREOUTA.GE VOLT AGE INDICATION CONTROL ROOM /EMERGENCY SWITCH GEAR _

COMMITMENT

. PLANNED ROOM AIR HANDLING UNITS UNIT 2 ATWS (AMSAC) COMPLETION COMMITMENT PLANNED -

ASME XI INSTRUMENTATION COMMITMENT PLANNED AFW RECIRC MODIFICATION COMMITMENT PLANNED MOTOR OPERATED VALVE/OPERATOR REPLACEMENT -

COMMITMENT PLANNED SERVICE WATER PIPING* INSPECTION/REPAIRS COMMITMENT,_

PLANNED SECONDARY PIPING INSPECTION PACKAGE COMMITMENT PLANNED THIMBLE TUBE INSPECTION

- COMMITMENT PLANNED CHECK VALVE INSPECTION

- COMMITMENT PLANNED

PLANNED IMPROVEMENTS

( continued)

DESCRIPTION RAD MONITOR SW-RM-107 C INSTALLATION CONTROL ROD M-12 AND CHANGEOUT 2-H BUS ELECTRICAL SEPARATION TESTING THERMAL BARIER CC PENETRATION EDG BASE & DAY TANK CLEANING S/G UPGRADE (MOISTURE SEPARATORS)

AFW PUMP GOVERNOR MODIFICATION BLACK BATIERY REPLACEMENT RSHX FLOW TEST MAIN TRANSFORMER INSPECTIONS/REPAIR

  • ASSESSING, DEPENDENT UPON INSPECTION BASIS COMMITMENT
  • COMMITMENT COMMITMENT COMMITMENT STATION STATION STATION STATION STATION STATION STATUS PLANNED PLANNED PLANNED PLANNED PLANNED PLANNED*

PLANNED PLANNED PLANNED I PLANNED

PLANNED IMPROVEMENTS

( continued)

DESCRIPTION BASIS TEST LINE THROTTLE VALVE (INSIDE RECIRC SPRAY)

STATION REPLACEMENT NEW LETDOWN ISOLATION VALVE

. STATION UNIT 2 FUEL TRANSFER CART MODIFICATION STATION SR PIPE IN CONTAINMENT (FW) REPLACEMENT STATION NSR SINGLE PHASE PIPE REPLACEMENT STATION

  • NSR TWO PHASE PIPE REPLACEMENT STATION

. RCP OIL COLLECTION SYSTEM MODIFICATION 1

  • STATION CROM DUCT FLANGE SWING BOLT MODIFICATION STATION RHR PUMP VENT STATION REACTOR HEAD VENT PIPING STATION RECIRC SPRAY INSTRUMENTATION (TEMP ELEMENTS)

STATION STATUS I

  • PLANNED PLANNED

.PLANNED PLANNED PLANNED PLANNED PLANNED PLANNED PLANNED PLANNED

.PLANNED

RESCHEDULED PLANNED IMPROVEMENTS DESCRIPTION BASIS STATUS*

PZR SPRAY & RELIEF TANK PIPING SUPPORTS COMMITMENT RESCHEDULED CRDR CONTROLLERS AND SWITCH MODIFICATldNS COMMITMENT REASSESSING INDICATOR, RECORDER, AND CONTROLLER COMMITMENT REASSESSING MODIFICATIONS

  • REPLACE EDG & AUX SHUTDOWN PANELS COMMITMENT REASSESSING FLOW INDICATION AND RECORDER COMMITMENT REASSESSING MODIFICATIONS PZR SPRAY VALVE POSITION INDICATION COMMITMENT REASSESSING STATUS LIGHT MODIFICATIONS COMMITMENT REASSESSING MAIN STEAM ATMOSPHERIC DUMP VALVES.

COMMITMENT REASSESSING RCP THERMAL BARRIER CC SYSTEM

    • COMMITMENT RESCHEDULED CCHX 01-CC-E-1C & VACUUM PRIMING COMMITMENT RESCHEDULED PIPING REPLACEMENT REACTOR CAVITY SEAL

. STATION REASSESSING

BASIS FOR COMMITMENT SCHEDULE CHANGE PRESSURIZER SAFETY VALVE PIPING/SUPPORTS SAFETY VALVE SETPOINT DRIFT ISSUE RESOLUTION ENGINEERING RECOMMENDING A STEAM TRIM PACKAGE WITH DRAINED LOOP SEALS AS SOLUTION REDUCED MAN-REM FOR INSTALLATI.ON OF SUPPORTS

  • J BASIS FOR COMMITMENT SCHEDULE CHANGE (continued)

CRDR PRESENT PLAN:

SCOPE BEING REASSESSED COMPLETE BY 1994 CONSISTENT WITH LONG TERM ACTIONS MATERIAL DELIVERY CONTROL ROOM ACTIVITIES

BASIS FOR COMMITMENT SCHEDULE CHANGE (continued)

RCP THERMAL* BARRIER COMPONENT COOLING WATER MODIFICATION PENETRATION WORK WILL BE PERFORMED THIS OUTAGE MATERIALS (VALVES) CANNOT BE PROCURED TO SUPPORT OUTAGE DISCUSSED AND AGREED TO DURING JUNE 28, 1990

  • MEETING

. i

BASIS FOR COMMITMENT SCHEDULE CHANGE (continued)

CCHX 01-CC-E-1C & VACUUM PRIMING PIPING REPLACEMENT

  • CONDITION OF EXISTING c*cHX IS ACCEPTABLE FOR CONTINUED OPERATION
  • RAD MONITORS WILL BE INSTALLED ON EXISTING CCHX DURING THIS OUTAGE
  • CONSIDERING AS A NON-OUTAGE REPLACEMENT I.

BASIS FOR COMMITMENT SCHEDULE CHANGE (continued)

INSTALLATION OF NEW CAVITY SEAL RING 1,1

  • COMMITMENT WAS TO EVALUATE A NEW DESIGN
  • EVALUATION COMPLETE-NEW.DESIGN COULD NOT
  • BE INSTALLED FOR UNIT 1
  • OLD CAVITY SEAL RING WAS FOUND TO BE ADEQUATE AND WAS REINSTALLED FOR UNIT 1 *
  • OLD CAVITY SEAL RING WILL ALSO BE USED FOR UNIT 2
  • REASSESSING DESIGN
  • SPECIAL TESTING COMMITMENT FOR OLD CAVITY SEAL RING WILL BE PROCEDURALIZED

NRC REQUIRED ACTIONS CONTROL ROOM/EMERGENCY SWITCHGEAR ROOM AIR CONDITIONING TECH SPEC SNUBBER SURVEILLANCE TECH SPEC.

BORON CONCENTRATION TECH SPEC ONE TIME TURBINE BLADE INSPECTION DEFERRAL 4

I

CLOSING REMARKS E. W. HARRELL VICE PRESIDENT - NUCLEAR OPERATIONS