App to SALP Repts 50-280/88-05,50-281/88-05,50-338/88-04 & 50-339/88-04,containing Meeting Summaries of 880727 & 28 Meetings & NRC Response to Util 880826 Comments on Rept
ML18153B517
Person / Time
Site: Surry, North Anna, 05000000
Issue date: 09/15/1988
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18153B516 List:
References
50-280-88-05, 50-280-88-5, 50-281-88-05, 50-281-88-5, 50-338-88-04, 50-338-88-4, 50-339-88-04, 50-339-88-4, NUDOCS 8810110069
Download: ML18153B517 (4)


See also: IR 05000280/1988005

Text

SEP 15 1988.

ENCLOSURE 1

APPENDIX TO VIRGINIA ELECTRIC POWER COMPANY

NORTH ANNA PLANT UNITS 1 AND 2

SALP BOARD REPORT NOS. 50-338/88-04 AND 50-339/88-04

(DATED JULY 26, 1988)

SEP 15 1988

Enclosure 1

2

I.

Meeting Summary

A.

A meeting was held at 2:00 p.m. on July 27, 1988, at the North Anna

facility, to discuss the SALP Board Report for this facility.

B.

Licensee Attendees

L. Ferguson, President and Chief Executive Officer

W. Stewart, Senior Vice President

D. S. Cruden, Vice President, Nuclear Operations

N. E .. Hardwick, Manager - Nuclear Programs and Licensing

G. E. Kane, Station Manager

M. Bowling, Assistant Station Manager

The list of Licensee Attendees above does not include the large

number of VEPCO employees that were present at the SALP presentation.

The personnel were managers, supervisors, and various p1ant staff.

This large turnout was beneficial to the SALP process and is highly

recommended for future presentations.

C.

NRC Attendees

D.

M. L. Ernst, Deputy Regional Administrator, RII

C .. W. Hehl, Deputy Director, Division of Reactor Projects (DRP), RII

H. N. Berkow, Director, Project Directorate II-2, Division of

Reactor Projects, Office of Nuclear Reactor Regulation (NRR)

L. Engle, Project Manager, Project Directorate II-2, NRR

C. Patel, Project Manager, Project Directorate II-2, NRR

B. A. Wilson, Chief, Reactor Projects Branch 2, DRP, RII

J. Caldwell; Senior Resident Inspector, North Anna, DRP, RII

L. King, Resident Inspector, North Anna, DRP, RII

SALP Meeting Slides

See Attachment 1

ENCLOSURE 2

APPENDIX TO VIRGINIA ELECTRIC AND POWER COMPANY

SURRY PLANT UNITS 1 AND 2

SALP BOARD REPORT NOS. 50-280/88-05 AND 50-281/88-05

(DATED JUlJ 26, 1988)

SEP 15 1988

SEP 15 1988

Enclosure 2

2

I.

Meeting Summary

A.

A meeting was held at 9:30 a.m. on July 28, 19'88, at the Surry

facility, to discuss the SALP Board Report for this facility.

B.

Licensee Attendees

L. Ferguson, President and Chief Executive Officer

D. S. Cruden, Vice President, Nuclear Operations

N. E. Hardwick, Manager - Nuclear Programs and Licensing

D. L. Benson, Station Manager

H. Miller, Assistant Station Manager

E. Grecheck, Assista.nt Station Manager

The list of Licensee Attendees above does not include the large

number of VEPCO employees that were present at the SALP presentation.

The personnel were managers, supervisors, and various plant staff.

This large turnout was beneficial to the SALP process and is highly

recommended for future presentations.

C.

NRC Attendees

D.

M. L. Ernst, Deputy Regional Administrator, RI!

.

C. W. Hehl, Deputy Director, Division of Reactor Projects (DRP), RII"

H. N. Berkow, Director, Project Directorate *II-2, Division of

Reactor Projects, Office of Nuclear Reactor Regulation (NRR)

C. Patel, Project Manager, Project Directorate II-2, ~RR

L. Engle, Project Manager, Project Directorate II-2, NRR

B. A. Wilson, Chief, Reactor Projects Branch 2, DRP, RII

W. Holland, Senior Resident Inspector, Surry, DRP, RII

L. Nicholson, Resident Inspector, Surry, DRP, RI!

SALP Meeting Slides