VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 March 30, 1995 United States Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555 Gentlemen:
VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNITS l AND 2 Serial No.
95 -11 O NURPC Docket Nos. 50-280 50-281 License Nos. DPR-32 DPR-37 SYSTEMATIC ASSESSMENT OF LICENSEE PERFORMANCE ($ALP)
INSPECTION REPORT NOS. 50-280/95-99 AND 50-281/95-99 On February 13, 1995, you transmitted the results of the NRC's Systematic Assessment of Licensee Performance (SALP) for Surry Power Station for the period of July 4, 1993, through January 21, 1995. Your assessment concluded that Surry's performance was superior in three of the functional areas:
Plant Operations, Engineering, and Plant Support. The Maintenance functional area was assessed as good.
We have reviewed the SALP report in detail. Your recognition of the overall high level of performance achieved at Surry Power Station is appreciated. We also appreciate the opportunity to have met with you on March 9, 1995 to discuss the results of the assessment along with our continuing efforts to improve.
We are committed to ensuring nuclear safety in every facet of our nuclear operations by striving to achieve a high level of performance in each category evaluated by the SALP process.
Very truly yours,
~7?&!~~
James P. O'Hanlon Senior Vice President - Nuclear cc:
U. S. Nuclear Regulatory Commission Region II 101 Marietta Street, N. W.
Suite 2900 Atlanta, Georgia 30323 Mr. M. W. Branch NRC Senior Resident Inspector Surry Power Station 9504050035 950330