Forwards Clarification of Points Re Proposed Emergency Plan Revs,Raised During 941121 Conference Call Between NRC & Util
ML18153B237
Person / Time
Site: Surry, North Anna  Dominion icon.png
Issue date: 02/21/1995
From: Ohanlon J
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
93-767A, NUDOCS 9503020042
Download: ML18153B237 (10)


Text

e e

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 February 21, 1995 United States Nuclear Regulatory Commission Attention: Document Control Desk Washington, D. C. 20555 Gentlemen:

VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNITS 1 AND 2 NORTH ANNA POWER STATION UNITS 1 AND 2 PROPOSED EMERGENCY PLAN REVISIONS Serial No.93-767 A NL&P/RPC Docket Nos. 50-280 50-281 50-338 50-339 License Nos. DPR-32 DPR-37 NPF-4 NPF-7 The purpose of this letter is to forward clarification of points raised during a November 21, 1994, conference call between the NRC staff and Virginia Electric and Power Company. The call concerned our request for approval of proposed emergency plan revisions submitted on February 18, 1994 (Serial No.93-767). Attachment 1 provides clarification pertaining to resources which augment the response capability.

The information provided herewith_ reflects our current normal operations and emergency response staffing practices. Referenced staffing levels may be adjusted up or down in the future as conditions dictate in order to maintain appropriate resource levels.

Should this proposed plan revision be approved, we will revise Table 5.1 of the Surry and North Anna plans to more clearly reflect the minimum staffing requirements consistent with the provisions discussed in Attachment 1. Furthermore, we will revise both plans to clearly reflect the emergency response facility activation goals now employed internally.

Should you require further information, please contact us.

Very truly yours, James P. O'Hanlon Senior Vice President - Nuclear ftDi.(s o I

cc:

U. S. Nuclear Regulatory Commission Region II 101 Marietta Street, N. W.

Suite 2900 Atlanta, Georgia 30323 Mr. M. W. Branch NRG Senior Resident Inspector Surry Power Station Mr. R. D. McWhorter NRG Senior Resident Inspector North Anna Power Station e

ATTACHMENT 1 POINTS OF DISCUSSION REQUESTED TO BE CLARIFIED

POINTS OF DISCUSSION REQUESTED TO BE CLARIFIED Point No. 1. The request for plan revision needs to be clarified to demonstrate the minimum onshift staffing requirements, inclusive of personnel responsibilities.

Response.

Onshift staffing requirements, as reflected in Table 5.1 ofthe North Anna Emergency Plan during full power operations are as follows:

Normal Position No.

Shift Supervisor 1

Asst. Shift Supervisor 1

Control Room Operator(RO) 3 Control Room Operator (AO) 3 Control Room Operator (AO) 1 HP Personnel 1

HP Personnel 1

HP Personnel 1

Chemistry Personnel 1

Shift Technical Advisor

.J.

Total 14 Emergency Position Station Emergency Manager*

Asst. Shift Supervisor Control Room Operator Control Room Operator Eme-rgency Communicator*

Rad. Assessment Director*

In-plant Mon. Team Leader In-plant Mort. Team Member Chemistry Team Member Shift Technical Advisor Those Emergency Response Organization (ERO) position titles marked With an asterisk ( *) are transferred to personnel responding to the Technical Support Center (TSC).

Upon TSC activation, the Shift Supervisor, assigned as the Station Emergency Manager (SEM) position at the onset of the event, reverts back to performing Control Room responsibilities.

In addition to the above personnel, the Fire Brigade is staffed as follows:

Normal Position Operator Security No.

3

.2.

5 Emergenc'y Position Fire Brigade Member**

Fire Brigade Member**

Total Those ERO position titles marked with a double asterisk ( * *) are available for other duties if the emergency event does not involve the need for the Fire Brigade.

1

Onshift staffing requirements pursuant to the Surry Emergen*cy Plan during full power operation are as follows:

Normal Position No.

Emergency Position Shift Supervisor (SRO) 2 Station Emergency Manager*

and Shift Supervisor Control Room Operator(RO) 3 Control Room Operators Control Room Operator (AO) 4 2 Control Room Operato'rs and 2 Emergency Communicators*

In-plant Mon. learn Leader In-plant Mon. Team Member Chemistry Team Member HP Personnel 1

HP Personnel 1

Chemistry Personnel 1

Shift Technical Advisor

_1 Shift Technical Advisor Total 13 Those ERO position titles marked with an asterisk ( *) are transferred to personnel responding to the TSC. The person assigned the SEM position and the person assigned the Emergency Communicator position revert back to Control Room responsibilities.

lhe Radiological Assessment Director position, shown on Table 5.1 of the Surry plan as being covered by personnel who may be assigned other duties, is covered by the HP Shift Supervisor. Although on shift, this person is not reflected in, and is in addition to, the 13 persons shown above.

In addition to the above personnel, the Fire Brigade is staffed as follows:

Normal Position Operator Security No.

3

.2 5

Emergency Position Fire Brigade Member**

Fire Brigade Member**

Total Those ERO position titles marked with a double asterisk ( * *) are available for other duties if the emergency event does not involve the need for the i=ire Brigade.

An approval of the proposed plan revision will result in a revision of Table 5.1 of both plans to clearly reflect the minimum staffing requirements discussed herein.

2

e Point No: 2. The request for plan revision needs to be clarified to explicitly state the activation goal for each emergency response facility.

Response.

With the exception of the Surry Local Emergency Operations Facility (EOF) and the Joint Public Information Center (JPIC), internal goals for emergency response facility activation are within about 60 minutes. The goal for the Surry Local EOF is about 90 minutes. There is no set goal limitation for the JPIC. lhat facility starts to function as soon as each functional area is staffed and becomes operational.

Point No. 3. The request for plan revision needs to be clarified to demonstrate the number of responders augmenting the response effort.

Response.

The information provided below reflects Virginia Electric and Power Company's current emergency response otganization staffing practices.

Referenced staffing levels may be adjusted up or down in future as conditions dictate and in order to continue to maintain resources at levels determined to be appropriate.

The current internal minimum staffing requirements for North Anna needed to activate the referenced emergency response facilities are as follows:

TSC Minimum Staff - 13. Full Staff - 28 or more.

OSC Minimum Staff - 9 plus AOs. Full Staff - 13 or more.

HP Minimum Staff - 15. Full Staff - 15 or more.

Chemistry Minimum Staff - 3. Full Staff-3 ot more.

LEOF Minimum Staff - 7. Full Staff - 18 or more.

During an actual event at North Anna, a second full operations shift would be called in, in addition to the above personnel.

The current internal minimum staffing requirements for Surry needed to activate the referenced emergency response facilities are as follows:

TSC Minimum Staff - 13. Full Staff - 23 or more.

OSC Minimum Staff - 10. Full Staff - 21 or more.

3

e HP Minimum Staff - 15. Full Staff - 15 or more.

Chemistry Minimum Staff - 3. Full Staff - 3 or more.

LEOF Minimum Staff - 7. Full Staff - 18 or more.

During an actual event at Surry, and depending on the specifics of the event, applicable operations personnel will be called in to augment the shift in addition to that presented above.

Damage Control Team management is provided in the TSC at North Anna and in the Operational Support Center (OSC) at Surry. This results in the difference between the two stations with respect to staffing the iSC and the OSC as reflected above.

The current internal minimum staffing requirements for the Corporate Emergency Response Center (CERC) and the Joint Public Information Center needed to activate the various emergency response facilities are as follows:

CERC JPIC This facility supports a formalized headquarters support function inclusive of access to vendor and service support groups and the additional resources of the Company.

Minimum Staff - 12. Full Staff - 34 or more.

This facility starts to function as Soon as each functional area is staffed. Areas include (with an approximate number of staff) JPIC Management (4), News Release Generation (8), Rumor Control (20), Media Monitoring (3), Government

_Affairs (5), and other corporate resources (as needed).

Excluding the addition of operations personnel and the resources of the JPIC for either station, the above listed response augmentation, or facilities manning total, for North Anna is 59 minimum staff and at least 111 when fully staffed. Similarly, the augmentation, or manning total, for Surry is 60 minimum staff and at least 114 when fully staffed.

While these numbers do not reflect the addition of ope*rations personnel, they do reflect select onshift personnel anticipated to fill emergency response functions. Within the emergency response organization charts provided in the February 18, 1994, submittal, there are several minimum staffing positions that may fall into this situation. At North Anna, the OSC chart refers to Auxiliary Operator(s) (AO).

These are all AOs available onsite when the facility is activated.

This includes those 4

e onshift. Additional positions that may be staffed by onshift personnel include three (3) of the fifteen (15) Health Physics positions in the HP office, one (1) of the three (3) Chemistry personnel and the Rad. Waste Operator position in the OSC.

With respect to, and as a result of a review of the history of, the Rad.

Waste Operator position, it appears that this position was established strictly in accordance with the guidance of NUREG-0654 and NUREG-0737, Supp. 1. It is not anticipated that an event at either North Anna or Surry would produce sufficient need to maintain a formalized position.

These functions are now performed by operators trained on the applicable systems. As the rad. waste function may be performed by onshift personnel, the minimum staffing figure for activating the OSC may rely on the availability of shift personnel. therefore, a person on shift may be reflected in the minimum staffing figure provided above for the OSC.

Should this proposed plan revision be approved, s*pecific reference to a formal Rad. Waste Operator position will be deleted. A deletion of this position will not result in a deletion of any required response activities or a lesser number of personnel responding during an emergency.

Although the onshift First Aid Team and the onshift Fire Team are identified on the OSC organization chart, they are not, however, included in the minimum staffing number provided above for staffing the OSC. It should be noted that Table 5. 1 of both plans identifies both of these functions as being augmented by offsite local support.

All other positions are anticipated to be staffed by augmenting pEfrsonnel either available from the applicable work shift (e.g., mobilization occurs during the normal work schedule) or called in.

Point No. 4. The request for plan revision needs to be clarified to demonstrate that the Fire Brigade is staffed by onshift personnel in addition to the 14 reflected in Table 5.1 of the North Anna plan and the 13 reflected in Table 5.1 of the Surry plan.

Response.

See response to Point No. 1. Furthermore, the governing administrative procedure, OPAP-0001, Operations Department Responsibilities and Authorities, references the onshift Fire Brigade. With respect to the five (5) Fire Brigade members, OPAP-0001 states:

"a.

3 from Operations (1 must be a qualified scene leader) and 2 from Security, the operators are not included in the RO/AO manning 5

e

[listed]."

OPAP-0001 at page 15, footnote a.

Should this proposed plan revision be approved, Virginia Power will revise Table 5.1 of both plans to clearly reflect the minimum staffing requirements including the provisions discussed herein.

Point No. 5. The request for plan revision needs to be clarified with respect to the Rad. Waste Operator function reflected on Table 5.1 of both plans.

Response.

During normal operations, rad. waste treatment functions are routinely performed during the day shift. As discussed above for both stations, during a response it is anticipated that no one individual would be called in solely for the purpose of operating rad. waste systems.

If this function was required, an operator, or operators, trained on the systems would be assigned to perform the function(s). This function would be performed by onshift or augmenting personnel, as needed.

Furthermore, it is anticipated that rad. waste activities would be most likely performed during the recovery phase of a response and would be considered in the associated recovery planning. If, during a response, this function was identified as requiring additional support, additional personnel resources would be called in over and above those already identified.

As stated above, it appears that the position of Rad. Waste Operator was established pursuant to the guidance of NUREG-0654 and NUREG-0737, Supp. 1, and not for an organizational need. It is not anticipated that an event at either North Anna or Surry would produce sufficient need to maintain an ERO position.

These functions are now performed by operators trained on the applicable systems. Should this proposed plan revision be approved, specific reference to a formal Rad. Waste Operator position will be deleted. A deletion of this position will not result in a deletion of any required response activities or produce a decrease in the number of personnel mobilized in response to an emergency.

Point No. 6. The request for plan revision needs to be clarified with respect to the minimum staffing requirements of the Corporate Emergency Response Center (CERC) and the Joint Public Information Center (JPIC).

Response.

For both stations, the CERC supports a formalized headquarters support function inclusive of access to vendor and service support groups.

Twelve ( 12) personnel are needed to staff the CERC before this facility 6

can be declared activated.

The CERC organization relies on a JPIC Director position and a Chief Technical Spokesperson as part of the minimum staffing requirements. Full staffing of this facility is currently identified at thirty four (34) personnel plus any resources identified as being needed at the time of the emergency response.

Other than the CERC staffing positions discussed above, the JPIC has no minimum staffing requirements, per se. The JPIC provides a location for coordinating public information from utility, State, local and Federal representatives.

This facility starts to function as soon as each functional area is staffed. Areas include (with approximate number of staff) JPIC Management (4), News Release Generation (8), Rumor Control (20), Media Monitoring (3), Government Affairs (5), and other corporate resources (as needed).

7