e VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 December 6, 1994 United States Nuclear Regulatory Commission Attention: Document Control Desk Washington, D. C. 20555 Gentlemen:

VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNITS 1 AND 2 UPDATED RESPONSE TO GENERIC LETTER 89-13 SERVICE WATER SYSTEM PROBLEMS AFFECTING SAFETY-RELATED EQUIPMENT Serial No.94-408 NUVAS/RPC R3 Docket Nos. 50-280 50-281 License Nos. DPR-32 DPR-37 In our letter (Serial No. 89-572G) dated October 2, 1991, Virginia Electric and Power Company provided additional details about our program to ensure the continued operability of the service water system at Surry Power Station. That letter included a summary of the program to flow test recirculation spray heat exchangers (RSHXs) which has continued during each Surry refueling outage since 1990. The identified RSHX flow test program was completed during the 1994 Unit 1 refueling outage.

The purpose of this letter is to notify the NRC of our future plans for periodic RSHX flow testing at Surry. Based on test results to date, we intend to flow test one RSHX service water subsystem every other refueling outage. The next flow tests are planned for Unit 2 in 1996 and Unit 1 in 1997. Thereafter, alternate subsystems will be tested every other refueling outage. Thus, functional flow testing will continue to verify system performance quantitatively without excessive impact to Company outage resources.

Post-test data assessment will include confirmation and modification of the testing frequency.

Should you have any questions, please contact us.

Very truly yours, James P. O'Hanlon Senior Vice President - Nuclear cc:

U. S. Nuclear Regulatory Commission Region II 101 Marietta Street, N. W.

Suite 2900 Atlanta, Georgia 30323 Mr. M. W. Branch NRC Senior Resident Inspector Surry Power Station

'i,-, r~,*'1 ~,...,.

,,----------------~

J. ~ u v 0 o 9412120090 941206 PDR ADOCK 05000280 P

PDR

r*,

  • ,./ *

~...)*Ll COMMONWEAL TH OF VIRGINIA )

)

COUNTY OF HENRICO

)

The foregoing document was acknowledged before me, in and for the County and Commonwealth aforesaid, today by J. P. O'Hanlon, who is Senior Vice President -

Nuclear, of Virginia Electric and Power Company. He is duly authorized to execute and file the foregoing document in behalf of that Company, and the statements in the document are true to the best of his knowledge and belief.

Acknowledged before me this ft, 7JI day of /&Ctm/u,1), 1 s<i!/_.

My Commission Expires: c/J(;-~, 3/

, 19a.

(SEAL)