Forwards SE Granting Licensee 931019 Request for Relief Re Inservice Testing Program Third 10-yr Interval for Pumps & Valves for Plant
ML18153B125
Person / Time
Site: Surry  Dominion icon.png
Issue date: 10/20/1994
From: Thadani M
Office of Nuclear Reactor Regulation
To: Ohanlon J
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
Shared Package
ML18151A385 List:
References
GL-89-04, GL-89-4, TAC-M88107, TAC-M88108, TAC-M89438, TAC-M89439, NUDOCS 9411040067
Download: ML18153B125 (4)


Text

I

l.

e UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 Mr. J.P. O'Hanlon Senior Vice President - Nuclear Virginia Electric and Power Company 5000 Dominion Blvd.

Glen Allen, VA 23060 October 20, 1994

SUBJECT:

SURRY POWER STATION, UNITS 1 AND 2 - INSERVICE TESTING PROGRAM THIRD TEN-YEAR INTERVAL FOR PUMPS AND VALVES, SURRY 1 AND 2 (TAC NOS.

M88107, M88108, M89438 AND M89439)

Dear Mr. O'Hanlon:

We, with technical assistance from Idaho National Engineering Laboratory (INEL),

have reviewed the information concerning Revision O of Inservice Testing (IST)

Program requests for reli~f submitted for the third ten-year interval for the Surry Power Station, Units 1 and 2, in a Virginia Electric and Power Company letter dated October 19, 1993.

An additional relief request for each unit was submitted in a letter dated April 26, 1994.

We adopt the evaluations and recommendations for granting relief or authorizing alternatives contained in the attached Technical Evaluation Report (TER) prepared by INEL, as reflected in the enclosed Safety Evaluation (SE). Relief is granted from or alternatives are authorized for the testing requirements which have been determined to be impractical to perform, where an alternative provides an acceptable level of quality and safety, or where compliance would result in a hardship or unusual difficulty without a compensating increase in quality or safety. The Surry Units 1 and 2 IST Program is based on the requirements in the 1989 Edition of ASME Section XI.

A summary of the NRC's action is provided in Table 1 of the enclosed SE.

The IST Program relief requests which are granted or authorized are acceptable for implementation provided the anomalies identified in Appendix A of the TER are addressed within one year of the date of the SE or by the end of the next refueling outage, whichever is later, unless another period is specified.

The granting of relief is based upon the fulfillment of any commitments you have made*

in the basis for each relief request and the alternatives proposed.

Where interim relief has been granted, you should resolve the issues before expiration of the interim period.

It is requested that you respond to the NRC within one year of the date of this SE describing actions taken, actions in progress, or actions to be taken, to address each of these items.

Program changes involving new or revised relief requests should be submitted to NRC.

New.or revised relief requests that meet the positions in GL 89-04, Attachment I, should be submitted to the NRC but may be implemented provided the guidance in GL 89-04, Section D, is followed. Program changes that add or delete components from the 1ST Program should also be periodically submitted to the NRC.

941104Ao0o 0~~ i3A8B~eo PDR PDR p

e J.P. O'Hanlon October 20, 1994 This completes our efforts on this issue and we are, therefore, closing out TAC Nos. M88107, M88108, M89438, and M89439.

Sincere l Y',

/s/

Mohan Thadani, Acting Director Project Directorate II-2 Division of Reactor Projects - I/II

Enclosure:

As stated cc w/enclosure:

See next page Docket Nos. 50-280 and 50-281 Distribution Docket File PUBLIC PDII-2 RF SVarga Document Name: C:\\AUTOS\\WPDOCS\\SURRY\\SURRY.SE

  • See prev;ous concurrence*

To receive a copy of this doc1.111ent, indicate in the box C=Copy attachment/enclosure N = No copy OFFICE LA: PDII-2

£ NAME EDunn in ton ? fr> BBuckl ey JSwolinski OGC ACRS (10)

DVere 11 i, RII OGC E=Copy with EHoller*

DATE 10/,.//94 10/?,,i:/94 10/ 20/94

~/4/94 OFFICIAL RECORD COPY

e J. P. 0' Han "Ion October 20, 1994 This completes our efforts on this issue and we are, therefore, closing out TAC Nos. M88107, M88108, M89438, and M89439.

Sincerely,

/s/

Mohan Thadani, Acting Director Project Directorate II-2 Division of Reactor Projects - I/II

Enclosure:

As stated cc w/enclosure:

See next page Docket Nos. 50-280 and 50-281 Distribution

~o o cket-=:ETTe!

PUBLIC

.PDII-2 RF.

SVarga Document Name: C:\\AUTOS\\WPDOCS\\SURRY\\SURRY.SE

  • See previous concurrence*

To receive a copy of this document, indicate in the box C=Copy w/o attachment/enclosure N = No copy OFFICE LA: POI I-2

£ PM:PDII-2 NAME EDunnington E,1J>

  • BBuckley -

JSwol inski OGC ACRS (10)

DVere 11 i, RII OGC E=Ccipy with EHoller*

DATE 10/ /t//94 10/~/94 10/20/94

~/4/94 OFFICIAL RECORD COPY

Mr. J. P. O'Hanlon Virginia Electric and Power Company cc:

Michael W. Maupin, Esq~

Hunton and Williams Riverfront Plaza, East Tower 951 E. Byrd Street Richmond, Virginia 23219 Mr. Michael R. Kansler, Manager Surry Power Station Post Office Box 315 Surry, Virginia 23883 Senior Resident Inspector Surry Power Station U.S. Nuclear Regulatory Convnission 5850 Hog Island Road Surry, Virginia 23883 Mr. Sherlock Holmes, Chairman Board of Supervisors of Surry County Surry County Courthouse Surry, Virginia 23683 Dr. W. T. Lough Virginia State Corporation Convnission Division of Energy Regulation Post Office Box 1197 Richmond, Virginia 23209 Regional Administrator, Region II U.S. Nuclear Regulatory Convnission 101 Marietta Street N.W., Suite 2900 Atlanta, Georgia 30323 Robert B. Strobe, M.D., M.P.H.

State Health Conunissioner Office of the Convnissioner Virginia Department of Health P.O. Box 2448 Richmond, Virginia 23218 Surry Power Station Attorney General Supreme Court Building 101 North 8th Street Richmond, Virginia 23219 Mr. M. L. Bowling, Manager Nuclear Licensing l Programs Innsbrook Technical Center Virginia Electric -and Power Company 5000 Dominion Blvd.

Glen Allen, Virginia 23060