ML18153B100

From kanterella
Jump to navigation Jump to search
Forwards Rev 0,Change 1 to Surry Unit 1 Third Interval IST Program & Rev 0,Change 1 to Surry Unit 2 Third Interval IST Program
ML18153B100
Person / Time
Site: Surry  Dominion icon.png
Issue date: 10/11/1994
From: Ohanlon J
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML18151A617 List:
References
94-565, NUDOCS 9410180164
Download: ML18153B100 (1)


Text

'

~

it e

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 October 11, 1994 United States Nuclear Regulatory Commission Attention: Document Control Desk Washington, D. C. 20555 Gentlemen, VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNITS 1 AND 2 INSERVICE TESTING PROGRAM PROGRAM CHANGES Serial No.

SPS/ETS Docket Nos.

License Nos.94-565 50-280 50-281 DPR-32 DPR-37 In accordance with 1 O CFR 50.55a(f)(5)(iv), Virginia Electric and Power Company is submitting changes to the third ten-year interval inservice testing program for Surry Units 1 and 2. These program changes include relief requests for Code requirements that are considered impractical. The changes to the programs, including a description and the basis for each change, are included as Attachments 1 and 2 to this letter.

The changes to the third interval inservice testing programs for Surry Power Station Units 1 and 2 have been reviewed by the Station Nuclear Safety and Operating Committee.

If you have any questions, please contact us.

Very truly yours,

~{!~,_,,___

James P. O'Hanlon Senior Vice President-Nuclear cc:

U.S. Nuclear Regulatory Commission Region II 101 Marietta Street, N.W.

Atlanta, Georgia 30323 Mr. Morris Branch NRC Senior Resident Inspector Surry Power Station 9410180164 941011 PDR ADOCK 05000280 p