October 6, 1995 Virginia Electric and Power Company ATTN:

Mr. J. P. O'Hanlon-Senior Vice President - Nuclear Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060

SUBJECT:

PLANT PERFORMANCE REVIEW (PPR) - SURRY

Dear Mr. O'Hanlon:

e On September 21, 1995, the NRC staff completed the semiannual Plant Performance Review (PPR) of Surry.

The staff conducts these reviews for all operating nuclear power plants to develop an integrated understanding of safety performance.

The results are used by regional management to facilitate planning and allocation of inspection resources.

The PPR for Surry involved the parti~ipation of all Regional Technical Divisions and NRR in evaluating inspection results and safety performance information for the period from March 1995 to September 1995.

PPRs provide regional management with a current summary of licensee performance and serve as inputs to the NRC Systematic Assessment of Licensee Performance (SALP) and senior management meeting (SMM) reviews.

This letter advises you of our planned inspection effort resulting* from the Surry PPR review.

It is provided to minimize the resource impact on your staff and to allow for scheduling conflicts and personnel availability issues to be resolved. in advance of inspector arrival onsite.

The enclosure details our inspection plan for the next 6 months.

The rationale or basis for each inspection outside the core inspection program is provided so that you are aware of the reason for emphasis in these program areas.

Resident inspections are not listed due to their ongoing and continuous nature.

We will inform you of any changes to the inspection plan.

If you have any questions, please contact G. Belisle at (404) 331-4196.

Sincerely, Orig signed by Ellis W. Merschoff 9510190177 90550100006280 PDR ADOCK PDR Ellis W. Merschoff, Director Division of Reactor Proje~ts G

Docket No.:

50-280, 50-281 License No.:

DPR-32, DPR-37

Enclosure:

Inspection Pl an cc w/encl:

(See page 2) 1...,.,.,..(1

.....,uvcG OFFICIAL COPY

VEPCO cc w/encl:

M. L.* Bowling, Manager Nuclear Licensing & Operations Support Virginia Electric & Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060 David A. Christian Station Manager Surry Power Station 5570 Hog Island Road Surry, VA 23883 Ray D. Peace, Chairman Surry County Board of Supervisors P. 0. Box 130 Dendron, VA 23839 Dr. W. T. Lough Virginia State Corporation Commission Division of Energy Regulation P. 0. Box 1197 Richmond, VA 23209 Michael W. Maupin Hunton and Williams Riverfront Plaza, East Tower 951 E. Byrd Street Richmond, VA 23219 Robert B. Strobe~ M.D., M.P.H.

State Health Commissioner Office of the Commissioner Virginia Department of Health P. 0. Box 2448 Richmond, VA 23218 Attorney General Supreme Court Building 900 East Main Street Richmond, VA 23219 2

'.I

'<I VEPCO Distribution w/encl:

B. Buckley, NRR G. Hallstrom, RII PUBLIC NRC Resident Inspector U.S. Nuclear Regulatory Commission Surry Nuclear Power Station 5850 Hog Island Road Surry, VA 23883 NRC Resident Inspector U.S. Nuclear*Regulatory Commission Route 2, Box 78-A Mineral, VA 23117 SEND TO PUBLIC DOCUMENT ROOM?

OFFICE RIIDRP RIIDRP SIGNATURE ~~

NAME LGarner DATE S / 95 COPY?

OFFICIA 3

10 /

/ 95 NO YES NO

L SURRY INSPECTION PLAN IP - Inspection Plan TI - Temporary Instruction Core Inspection - Minimum NRC Inspection Program (mandatory all plants)

INSPECTION TITLE/

NUMBER OF PLANNED TYPE OF INSPECTION PROGRAM AREA INSPECTORS INSPECTION COMMENTS DATES IP 83750 Occupational Radiation 1

10/02-06/95 Core Inspection Exposure IP 71001 Licensed Operator 2

10/30-11/03/95 Core Inspe_ction Requalification Program Evaluation IP 81700 Physical Security Program 1

10/30-11/03/95 Core Inspection for Power Reactors IP 84750 Radioactive Waste Systems, 1

12/11-15/95 Core Inspection Water Chemistry Confirmatory Measurements and Radiological Environmental Monitoring.

IP 86750 Solid Radioactive Waste Management and Transportation of Radioactive Materials IP 82701 Operational Status of the 1

01/08-12/96 Core Inspection Emergency Preparedness Program IP 81700 Physical Security Program 1

02/26/-03/01/96 Core Inspection for Power Reactors Page 1 of 2 ENCLOSURE

INSPECTION TITLE/

NUMBER OF PLANNED TYPE OF INSPECTION PROGRAM AREA INSPECTORS INSPECTION COMMENTS DATES IP 84750 Radioactive Waste Systems, 1

03/18-22/96 Core Inspection Water Chemistry Confirmatory Measuremen~s and Radiological Environmental Monitoring.

IP[ 86750 Solid Radioactive Waste Management and Transportation of Radioactive Materials TI 2515/109 Inspection Requirements TBD TBD Area of Emphasis -

for Generic Letter 89-10, Inspection to close Safety-Related Motor-out Generic Letter Operated Valve Testing and 89-10 Surveillance Page 2 of 2 ENCLOSURE