Informs of Intent to Provide Written Summary Rept within 120 Days in Response to GL 97-01, Degradation of Control Rod Drive Mechanism Nozzle & Other Vessel Closure Head Penetrations
ML18153A402
Person / Time
Site: Surry, North Anna  
Issue date: 04/28/1997
From: Ohanlon J
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
97-214, GL-97-01, GL-97-1, NUDOCS 9705060200
Download: ML18153A402 (2)


Text

,*

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 April 28, 1997 United States Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001 Gentlemen:

VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNITS 1 AND 2 NORTH ANNA POWER STATION UNITS 1 AND 2 Serial No.

NL&OS/MWH:

Docket Nos.

License Nos.97-214 R2 50-280 50-281 50-338 50-339 DPR-32 DPR-37 NPF-4 NPF-7 DEGRADATION OF CONTROL ROD DRIVE MECHANISM NOZZLE AND OTHER VESSEL CLOSURE HEAD PENETRATIONS On September 30, 1996, the Nuclear Regulatory Commission issued NRC Generic Letter 97-01, "Degradation Of Control Rod Drive Mechanism Nozzle And Other Vessel Closure Head Penetrations." The generic letter requested that licensees provide the following information for: (1) CROM nozzle and other VHPs inspection activities including, (a) a description of all inspections and results performed to the date of the generic letter, (b) the scope and schedule if a plan has been developed to periodically perform inspections, (c) the analysis that supports why no augmented inspection is necessary if a plan has not been developed to perform periodic inspections, (d) the analysis that supports the selected course of action for inspections, and (2) a description of any resin bead intrusions that have exceeded the current EPRI PWR Primary Water Chemistry Guidelines.

The generic letter requests two written responses. First, within 30 days of the issuance of the generic letter, a written response is required indicating:

(1) whether or not the requested information will be submitted and (2) whether or not the requested information will be submitted within the requested time period.

Second, within 120 days of the issuance of the generic letter, a written report is to be submitted providing the requested information describing the CROM nozzle & other VHP inspection activities and describing any resin bead intrusions.

, I IHIIIHIII IIIII IIIII IIIIII Ill// Ill Ill/ ':

  • &&&6BA*

-~

It is our intent to provide the requested information by a written summary report to the NRC within 120 days consistent with the generic letter. Should you have any questions, please contact us.

Very truly yours,

~?.~

James P. O'Hanlon Senior Vice President - Nuclear Committment contained in this letter: Provide the requested information by a written summary report to the NRC within 120 days consistent with the generic letter cc:

U.S. Nuclear Regulatory Commission Region II Atlanta Federal Center 61 Forsyth Street, S.E.

Suite 23T85 Atlanta, Georgia 30303 Mr. R. A. Musser NRC Senior Resident Inspector Surry Power Station NRC Senior Resident Inspector North Anna Power Station