Text
_,--------
I e
VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 United States Nuclear Regulatory Commission Attention: Document Control Desk q-,6-qs Washington, D.C. 20555 Gentlemen:
VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNITS 1 AND 2 MONTHLY OPERA TING REPORT Serial No.
SPS Lie/JCS Docket Nos.
License Nos.98-534 RO 50-280 50-281 DPR-32 DPR-37 The Monthly Operating Report for Surry Power Station Units 1 and 2 for the month of August 1998, is provided in the attachment.
The Unit Shutdown and Power Reduction report for the June 1998 Monthly Operating Report 98-06 incorrectly stated that the reason for the power reduction on June 2, 1998, was for work on a governor valve. The report should have stated that the power reduction was a scheduled activity for the replacement of a belt on the isophase bus duct. The activity should have been designated with a system code of "TB" and a component code of "FAN." The governor valve repairs were performed on June 10, 1998 and did not require a power reduction greater than twenty per cent.
If you have any questions or require additional information, please contact us.
Very truly yours, E. S. Grecheck, Site Vice President Surry Power Station Attachment Commitments made by this letter: None 9809180234 980915 PDR ADOCK 05000280 R
-~1:::.::*..... 1 <./ ti J-
-- v'
cc:
U.S. Nuclear Regulatory Commission Region II Atlanta Federal Center 61 Forsyth Street, S. W.
Suite 23T85 Atlanta, Georgia 30303 Mr. R. A. Musser NRG Senior Resident Inspector Surry Power Station Serial No. 98-534: SPS Monthly Operating Report Page 2 of 2