Requests Addl Info Re GL 97-04, Assurance of Sufficient Net Positive Suction Head for Emergency Core Cooling Heat Removal Pumps, Issued on 971007
ML18153A318
Person / Time
Site: Surry, North Anna  Dominion icon.png
Issue date: 09/01/1998
From: Edison G
NRC (Affiliation Not Assigned)
To: Ohanlon J
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
References
GL-97-04, GL-97-4, TAC-MA0015, TAC-MA0016, TAC-MA0050, TAC-MA0051, TAC-MA15, TAC-MA16, TAC-MA50, TAC-MA51, NUDOCS 9809030324
Download: ML18153A318 (4)


Text

      • Mr. J. P. O'Hanlon
  • Septe m berl, 1998
  • Senior Vice President Virginia Electric and Power Company 5000 Dominion Boulevard Glen Allen, VA 23060

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION RELATED TO GENERIC LETTER 97 SURRY POWER STATION (SPS), UNITS 1 AND 2; NORTH ANNA POWER STATION (NAPS), UNITS 1 AND 2 (TAC NOS: MA0050, MA0051, MA0015 AND MA0016)

Dear Mr. O'Hanlon:

The NRC staff issued Generic Letter (GL) 97-04, "Assurance of Sufficient Net Positive Suction Head for Emergency Core Cooling and Containment Heat Removal Pumps" on October 7, 1997.

The GL requested that licensees provide information necessary to confirm the adequacy of the net positive suction head (NPSH) available for emergency core cooling and containment heat removal pumps. By letter dated December 29, 1997, Virginia Electric and Power Company submitted its 90-dayresponse to GL 97-04.

The NRC staff has reviewed your response and is concerned that SPS, Units 1 and 2 and, NAPS, Units 1 and 2 may not be within its licensing basis because it appears that the containment overpressure needed to assure adequate NPSH is greater than the overpressure previously approved by the NRC staff.* As discussed with and agreed to by Mr. Sommers of your staff on August 27, 1998, please provide a response within 60 days discussing how your response to GL 97-04 related to containment overpressure compares with your current licensing basis. If it is determined that SPS, Units 1 and 2, and NAPS, Units 1 and 2 are outside of their licensing bases, the staff expects that you will take prompt action to modify your licensing basis as appropriate in accordance with the regulations, or otherwise restore the facility to a condition consistent with the licensing basis. Should you have any questions, please contact Mr. Edison at (301) 415 1448 and Mr. Kalyanam at (301) 415 1480.

Sincerely, N. Kalyanam, Project Manager Project Directorate 11-1 Division of Reactor Projects - 1/11 Office of Nuclear Reactor Regulation Docket Nos. 50-280, 50-281, 50-338 and 50-339 cc: See next page DISTRIBUTION

. (Docke.[Fi@

Public ACRS RCaruso DSkay JKudrick, NRR (SEs need to be E-mailed to T. Harris, TLH3)

FILENAME: G:\\NOANNA\\MA0015-6.SMP OFFICE PM:PDll-1 PM:PDll-1 NAME NKalyanamP Sincerely, Original Signed by:

Gordon E. Edison, Senior Project Manager Project Directorate 11-1 Division of Reactor Projects - 1/11 Office of Nuclear Reactor Regulation f.7;'1 Fi :T?i 0:1 pf,_j;.~I:.~

  • . '1~j1.-... ~~_:

r-.:,(*_:;~ \\1,*:i_,._:_.. -,-_:\\,_'. ~_.li::;1:'*.-_i,' ;! __ J ;.;,:.- *. *.**ii,

\\.*._;_*,~.:~;~; __ *.-.* '_.,*:~.~-~.-.!;;\\*.:ill t,t~'ci(;


. " I_

~

L Plisco, R II KKavanagh, NRR LA:PDll-1 EDunningt J. Zwolinski OGC DATE g-127-198

/98


-9809030324 980901 PDR ADOCK 05000280 P

PDR Yes I No

September1~ 1998

-~

Mr. J. P. O'Hanlon Senior Vice President Virginia Electric and Power Company 5000 Dominion Boulevard Glen Allen, VA 23060

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION RELATED TO GENERIC LETIER 97-04-SURRY POWER STATION (SPS), UNITS 1 AND 2; NORTH ANNA POWER STATION (NAPS), UNITS 1 AND 2 (TAC NOS: MA0050, MA0051, MA0015 AND MA0016)

Dear Mr. O'Hanlon:

The NRC staff issued Generic Letter (GL) 97-04, "Assurance of Sufficient Net Positive Suction Head for Emergency Core Cooling and Containment Heat Removal Pumps" on October 7, 1997.

The GL requested that licensees provide information necessary to confirm the adequacy of the net positive suction head (NPSH) available for emergency core cooling and containment heat removal pumps. By letter dated December 29, 1997, Virginia Electric and Power Company submitted its 90-day response to GL 97-04.

The NRC staff has reviewed your response and is concerned that SPS, Units 1 and 2 and, NAPS, Units 1 and 2 may not be within its licensing basis because it appears that the containment overpressure needed to assure adequate NPSH is greater than the overpressure previously approved by the NRC staff. As discussed with and agreed to by Mr. Sommers of your staff on August 27, 1998, please provide a respon~e within 60 days discussing how your response to GL. 9t-04 related to containment overpressure compares with your current licensing basis. If it is determined that SPS, Units 1 and 2, and NAPS, Units 1 and 2 are outside of their licensing bases, the staff expects that you will take prompt action to modify your licensing basis as appropriate in accordance with the regulations, or otherwise restore the facility to a condition consistent with the licensing basis. Should you have any questions, please contact Mr. Edison at (301) 415 1448 and Mr. Kalyanam at (301) 415 1480.

Sincerely, N. Kalyanam, Project Manager Project Directorate 11-1 Division of Reactor Projects - 1/11 Office of Nuclear Reactor Regulation Docket Nos. 50-280, 50-281, 50-338 and 50-339 cc: See next page DISTRIBUTION Docket File Public ACRS RCaruso DSkay JKudrick, NRR (SEs need to be E-mailed to T. Harris, TLH3)

FILENAME: G:\\NOANNA\\MA0015-6.SMP OFFICE PM:PDll-1 PM:PDll-1 NAME NKalyanam.

I Sincerely, Original Signed by:

Gordon E. Edison, Senior Project Manager Project Directorate 11-1 Division of Reactor Projects - 1/11 Office of Nuclear Reactor Regulation L. Plisco, R II KKavanagh, NRR LA:PDll-1 EDunningt J. Zwolinski OGC DATE 9 0-7 /98

/98 I

COPY Yes/ No

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555--0001 September 1, 1998 Mr. J. P. O'Hanlon Senior Vice President

  • Virginia Electric and Power Company 5000 Dominion Boulevard Glen Allen, VA 23060

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION RELATED TO GENERIC LETTER 97-04-SURRY POWER STATION (SPS), UNITS 1 AND 2; NORTH ANNA POWER STATION (NAPS), UNITS 1 AND 2 (TAC NOS: MA0050, MA0051, MA0015 AND MA0016)

Dear Mr. O'Hanlon:

The NRC staff issued Generic Letter (GL) 97-04, "Assurance of Sufficient Net Positive Suction Head for Emergency Core Cooling and Containment Heat Removal Pumps" on October 7, 1997.

The GL requested that licensees provide information necessary to confirm the adequacy of the net positive suction head (NPSH) available for emergency core cooling and containment heat removal pumps. By letter dated December 29, 1997, Virginia Electric and Power Company submitted its 90-day response to GL 97-04.

The NRC staff has reviewed your response and is concerned that SPS, Units 1 and 2 and NAPS, Units 1 and 2 may not be within its licensing basis because it appears that the containment overpressure needed to assure adequate NPSH is greater than the overpressure previously approved by the NRC staff. As discussed with and agreed to by Mr. Sommers of your staff on August 27, 1998, please provide a response within 60 days discussing how your response to GL 97-04 related to containment overpressure compares with your current licensing basis. If it is determined that SPS, Units 1 and 2, and NAPS, Units 1 and 2 are outside of their licensing bases, the staff expects that you will take prompt action to modify your licensing basis as appropriate in accordance with the regulations, or otherwise restore the facility to a condition consistent with the licensing basis. Should you have any questions, please contact Mr. Edison at (301) 415 1448 and Mr. Kalyanam at (301) 415 1480.

Sincerely,

~

~..

N. Kalyanam, Project Manager Project Directorate 11-1 Division of Reactor Projects - 1/11 Office of Nuclear Reactor Regulation Docket Nos. 50-280, 50-281, 50-338 and 50-339 cc: See next page Sincerely, 9'C,~

Gordon E. Edison, Senior Project Manager Project Directorate 11-1 Division of Reactor Projects - 1/11 Office of Nuclear Reactor Regulation

Virginia Electric & Power Company Mr. J. Jeffrey Lunsford County Administrator, Louisa County P.O. Box 160 Louisa, Virginia 23093 Michael W. Maupin, Esq.

Hunton and Williams Riverfront Plaza, East Tower 951 E. Byrd Street Richmond, Virginia 23219 Dr. W. T. Lough Virginia State Corporation Commission Division of Energy Regulation P.O. Box 1197 Richmond, Virginia 23209 Old. Dominion Electric Cooperative 4201 Dominion Boulevard Glen Allen, Virginia 23060 J. H. McCarthy, Manager Nuclear Licensing and Operations Support Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard

. Glen Allen, Virginia 23060 Office of the Attorney General Commonwealth of Virginia 900 East Main Street Richmond, Virginia 23219 Senior Resident Inspector North Anna Power Station U.S. Nuclear Regulatory Commission 1024 Haley Drive Mineral, Virginia 23117 Senior Resident Inspector Surry Power Station,*us Nuclear Regulatory Commission 5850 Hog Island Road Surry, Virginia 23883 Robert B. Strobe, M.D., M.P.H.

State Health Commissioner Office of the Commissioner Virginia Department of Health P.O. Box 2448

  • Richmond, Virginia 23218 Regional Administrator, Region II U.S. Nuclear Regulatory Commission Atlanta Federal Center 61 Forsyth St., SW, Suite 23T85 Atlanta, Georgia 30303 W.R. Matthews Site Vice President North Anna Power Station Virginia Electric and Power Company P.O. Box 402 Mineral, Virginia 23117 J.P. O'Hanlon
  • Senior Vice Pre$ident - Nuclear Virginia Electric and Power Co.

Innsbrook Technical Center*

5000 Dominion Boulevard Glen Allen, Virginia 23060 Mr. Eugene S. Grecheck Site Vice President Surry Power Station.

Virginia Electric and Power Company 5570 Hog Island Road Surry, Virginia 23883 Chairman Board of Supervisors

  • of Surry County Surry County Courthouse Surry, Virginia 23683 Mr. R. C. Haag U.S. Nuclear Regulatory Commission Atlanta Federal Center 61 Forsyth St., SW, Suite 23T85 Atlanta, Georgia 30303

- ~