t

-.\\ Mr. J.P. O'Hanlon A Senio~ Vice Presid~ - Nuclear

.. _ Vi rgi tli a Electric and Power Company Innsbrook Technical Center 5000 Dominion Blvd.

Glen Allen, Virginia 23060 August 29, 199~

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION (RAI) REGARDING INSERVICE INSPECTION (ISI) RELIEF REQUEST, SURRY UNIT 2 (TAC NO. M95138)

Dear Mr. O'Hanlon:

The purpose of this letter is to request additional information so that we can complete our review of your ISi relief request submitted February 7, 1996.

Your relief request, designated SR-14 through SR-17, relates to weld examination coverage requirements of ASME Code,Section XI.

The NRC staff is reviewing your submittal and requires additional information (enclosure) to complete its review.

The information requested was discussed with Mr. G.

Miller of your staff on August 2, 1996.

Please respond within 30 days of recei~t of this letter.

Docket No. 50-281

Enclosure:

cc w/encl:

Distribution

  • Docket File PUBLIC PDil-1 RF S. Varga J. Zwo l ins k i OGC ACRS RAI See next page FILENAME - G: SURRY M95138.RAI OFFICE LA:PDII-1 PM:PDII-NAME DATE COPY

(----------- ------*

9609050325 960829 PDR ADOCK 05000281 G

PDR Sincerely, (Original Signed By)

Gordon E. Edison, Senior Project Manager Project Directorate 11-1 Division of Reactor Projects - 1/11 Office of Nuclear Reactor Regulation D:PDII-1 Elmbro ff;'k.-

)

e Mr. J. P. O'Hanlon Virginia Electric and Power Company cc:

Mr. Michael W. Maupin, Esq.

Hunton and Williams Riverfront Plaza, East Tower 951 E. Byrd Street Richmond, Virginia 23219 Mr. David Christian, Manager Surry Power Station Virginia Electric and Power Company 5570 Hog Island Road Surry, Virginia 23883 Senior Resident Inspector Surry Power Station U. S. Nuclear Regulatory Commission 5850 Hog Island Road Surry, Virginia 23883 Chairman Board of Supervisors of Surry County Surry County Courthouse Surry, Virginia 23683 Dr. W. T. Lough Virginia State Corporation Commission Division of Energy Regulation P. 0. Box 1197 Richmond, Virginia 23209 Regional Administrator, Region II U. S. Nuclear Regulatory Commission 101 Marietta Street N.W., Suite 2900 Atlanta, Georgia 30323 Robert B. Strobe, M.D., M.P.H.

State Health Commissioner Office of the Commissioner Virginia Department of Health P.O. Box 2448 Richmond, Virginia 23218 Surry Power Station Office of the Attorney General Commonwealth of Virginia 900 East Main Street Richmond, Virginia 23219 Mr. M. L. Bowling, Manager Nuclear Licensing & Operations Support Innsbrook Technical Center Virginia Electric and Power Company 5000 Dominion Blvd.

Glen Allen, Virginia 23060 Mr. Al Belisle U.S. Nuclear Regulatory Commission 101 Marietta Street, N.W. Suite 2900 Atlanta, Georgia 30323-0199 Mr. W. R. Matthews, Manager North Anna Power Station P. 0. Box 402 Mineral, Virginia 23117.

__ I

t REQUEST FOR ADDITIONAL INFORMATION SURRY POWER STATION, UNIT 2 ENCLOSURE I.

Request for Relief SR-14 addresses relief from preservice examination coverage as stated in the "Alternate Provisions."

Is the subject request for relief based on a new weld?

The Code requires a 100%

volumetric examination.

Has an alternate volumetric examination technique {radiography) been considered?

2.

For Requests for Relief SR-15, SR-16, and SR-17, you have presented coverages obtained from actual examinations and estimated coverages for the remaining scheduled portion of the subject welds.

It should be noted. that relief requests should present coverages obtained/obtainable, based on actual examinations. Typically, licensees submit requests for relief following completion of the entire weld.

Provide a basis for submitting the request for relief prior to the completion of the examinations.