MONTHYEARML24261B9282024-09-17017 September 2024 NRR E-mail Capture - for Your Action Discussion Points - Steam Generator Tube Inspection Call with SNC Regarding Vogtle, Unit 3 ML24250A1132024-09-0303 September 2024 Inspection Report 2024004 Radiation Safety Baseline Inspection Information Request ML24247A0092024-09-0303 September 2024 NRR E-mail Capture - Fyi - Revised Estimated Completion Date - Vogtle 3 and 4 - UFSAR Scheduler Exemption Request ML24250A1922024-08-29029 August 2024 Amendment Nos. 223/206 (1) - Email ML24232A0052024-08-16016 August 2024 NRR E-mail Capture - Acceptance Review - LAR and Exemption Request to Remove Tier 1 and Tier 2 Requirements for Vogtle 3 and 4 ML24253A0722024-08-15015 August 2024 Perspectives on Proposed Removal of Tier 1 and Tier 2 Requirements ML24225A0062024-08-0909 August 2024 NRR E-mail Capture - Acceptance Review - Vogtle 3 and 4 - LAR Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves), Action a and SR 3.7.6.6 (L-2024-LLA-0101) ML24206A0252024-07-20020 July 2024 NRR E-mail Capture - for Your Comments - State of Georgia - Vogtle Unit 1 - Emergency License Amendment Request for Technical Specification 3.7.9 ML24199A1592024-07-17017 July 2024 NRR E-mail Capture - Request for Additional Information - Vogtle 3 and 4 - Exemption for the Requirements in 10 CFR 50.71 Pertaining to the Submittal of Updated Final Safety Analysis Report ML24198A1672024-07-16016 July 2024 NRR E-mail Capture - Acceptance Review Vogtle 3 and 4 - License Amendment Request Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Surveillance Requirement L-2024-LLA-0083 ML24197A1572024-07-15015 July 2024 NRR E-mail Capture - Acceptance Review - Farley and Vogtle 1 and 2, LAR - TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown ML24197A0172024-07-12012 July 2024 NRR E-mail Capture - Fyi - Acceptance Review - Farley and Vogtle 1 and 2 - Alternative Request for Pressurizer Welds ML24194A0032024-07-11011 July 2024 NRR E-mail Capture - Fyi - Acceptance Review - Farley, Hatch, and Vogtle 1 and 2 - Alternative Request for Code Case N-572 ML24180A0012024-06-26026 June 2024 NRR E-mail Capture - Acceptance Review Farley 1 and 2 and Vogtle 1 and 2 - Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) (L-2024-LLR-0041) ML24170A9362024-06-18018 June 2024 NRR E-mail Capture - Fyi - Change to Estimated Completion Date for the SNC Fleet Physical Barrier Exemptions (L-2023-LLE-0018 and L-2023-LLE-0021) ML24178A3422024-05-16016 May 2024 NRR E-mail Capture - Request for Call - Proposed Vogtle 3 & 4 Tier 1 and Tier 2 Exemptions and LAR ML24120A0462024-04-29029 April 2024 COL Docs - Re Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Power Ascension Tests ML24120A0262024-04-29029 April 2024 COL Docs - FW Vogtle Electric Generating Plant, Unit 4 - Project Manager Reassignment ML24119A0012024-04-28028 April 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Power Ascension Tests ML24108A0132024-04-16016 April 2024 NRR E-mail Capture - (External_Sender) Responses from Wednesday 4/10/2024 Call with Southern Nuclear Operating Co. Vogtle 3&4 Licensing Actions ML24107A7292024-04-15015 April 2024 Request for Vogtle Electric Generating Plant Units 1 & 2 - Radiation Protection Inspection - Inspection Report 2024-02 ML24107A9322024-04-15015 April 2024 Document Request for Vogtle Electric Generating Plant Units 1 & 2 - Radiation Protection Inspection Report 2024-02 ML24106A0522024-04-12012 April 2024 NRR E-mail Capture - Acceptance Review - Vogtle 1 and 2 - Emergency Diesel Generator (EDG) Voltage and Frequency License Amendment Request (LAR) (L-2024-LLA-0031) ML24100A7842024-04-0909 April 2024 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) - Vogtle, Units 3 and 4 - Alternative Request for Explosively Actuated Valves (L-2023-LLR-0016) ML24099A0372024-04-0505 April 2024 NRR E-mail Capture - Acceptance Review - Vogtle Unit 3, License Amendment Request (LAR) Technical Specification (TS) 5.5.13, Ventilation Filter Testing Program (VFTP) - L-2024-LLA-0043 ML24095A2412024-04-0404 April 2024 NRR E-mail Capture - Acceptance Review for the Exemption Request Regarding the Final Safety Analysis Report Update Schedule at Vogtle, Units 3 and 4 ML24072A3982024-03-12012 March 2024 NRR E-mail Capture - for Your Action - Second Round Request for Additional Information (RAI) - Vogtle, Unit 1 - SG Tube Inspection Report - 1R24 (L-2023-LRO-0067) ML24061A2372024-03-0101 March 2024 SNC Email Dated March 1, 2024, Regarding SNC Response to NRC Letter for Vogtle 3 & 4 RES Info ML24057A0872024-02-23023 February 2024 NRR E-mail Capture - Acceptance Review - Alternative Request for Explosively Actuated Valves at Vogtle, Units 3 and 4 ML24046A1352024-02-15015 February 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Initial Criticality and Low-Power Testing ML24039A0882024-02-0808 February 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24039A1922024-02-0808 February 2024 COL Docs - Correction - Re Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24039A1122024-02-0808 February 2024 COL Docs - Re Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24031A0502024-01-31031 January 2024 COL Docs - FW Erroneous Description of Tier 2 Change Process in Construction Lessons-Learned Report ML24017A1122024-01-17017 January 2024 NRR E-mail Capture - Request for Access to Cyber Security Data - Vogtle, Units 3 and 4 ML23360A0042023-12-23023 December 2023 NRR E-mail Capture - Fyi - Office of Nuclear Regulatory Research (RES) Requests for Vogtle 3 & 4 ML23348A0782023-12-13013 December 2023 NRR E-mail Capture - Voluntary Request for Closed Meeting Regarding Cyber Security Assessments at Vogtle, Units 3 and 4 ML23342A0802023-12-0808 December 2023 NRR E-mail Capture - Request for Additional Information (RAI) - Vogtle, Unit 1 - Review of SG Tube Inspection Report for Refueling Outage 24 (L-2023-LRO-0067) ML23331A9992023-11-27027 November 2023 COL Docs - Re Re Re ML23079A125 - Vogtle Electric Generating Station, Unit 3, NRC Response Letter to P. Durand, Regarding Comment on Federal Register Notice License Amendment No. 189 ML23331A9492023-11-26026 November 2023 Email Dated November 26, 2023, from Bo Pham to SNC and NRC - Vogtle Seismic Hazard Report ML23331A9622023-11-22022 November 2023 Email Dated November 22, 2023, from SNC to NRC - Vogtle Seismic Hazard Report ML23326A2802023-11-22022 November 2023 COL Docs - Re Re ML23079A125 - Vogtle Electric Generating Station, Unit 3, NRC Response Letter to P. Durand, Regarding Comment on Federal Register Notice License Amendment No. 189 ML23320A0342023-11-16016 November 2023 COL Docs - Re Acceptance Review of Southern Nuclear Operating Companys License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23320A2372023-11-0808 November 2023 NRR E-mail Capture - (External_Sender) Proposed LAR Regarding the Ultimate Heat Sink at Vogtle, Units 1 and 2 ML23312A2632023-11-0808 November 2023 COL Docs - Action Request for State of Georgia Comment by 5pm Monday, November 13, 2023 - Vogtle Units 3&4, LAR-22-002, TS 3.8.3, Inverters - Operating Completion Time Extension ML23311A1512023-11-0707 November 2023 COL Docs - Re Acceptance Review of Southern Nuclear Operating Companys License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23304A2272023-10-31031 October 2023 NRR E-mail Capture - Request for State of Georgia Comment by 5pm Monday, Nov. 6, 2023 - License Amendment Request for Vogtle Unit 4 - to Remove Combined License Appendix C ML23289A1362023-10-16016 October 2023 COL Docs - Action Request for State of Georgia Comment by 5pm Friday, October 20, 2023 - Vogtle Units 3&4, LAR-23-006, Rev.1, More Restrictive Action for Tech. Spec. 3.1.9 ML23283A0332023-10-10010 October 2023 COL Docs - FW Vogtle Units 3 and 4 (LAR 23-009) ML23283A0452023-10-0808 October 2023 E-Mail Re Plant Vogtle - Neop Letter Dated October 8, 2023 - Vogtle 3 & 4 - TS 3.7.6 License Amendment Request 2024-09-03
[Table view] |
Text
Vogtle PEmails From: Hoellman, Jordan Sent: Friday, June 1, 2018 9:35 AM To: Vogtle PEmails
Subject:
SNC Response to NRC Comment on UIN for ITAAC Index No. 872 Below is SNCs response to NRC comment on the UIN for ITAAC Index No. 872 (ADAMS Accession No. ML18151B054).
From: Stacy, Kara M. [1]
Sent: Tuesday, May 29, 2018 12:24 PM To: Hoellman, Jordan <Jordan.Hoellman2@nrc.gov>
Cc: Nist, Lauren <lauren.nist@nrc.gov>; Petrak, Tom G. <TGPETRAK@southernco.com>
Subject:
[External_Sender] RE: NRC Comment on UIN for ITAAC Index No. 872 Thank you Jordan for providing the FEMA memo.
SNC agrees with the Staffs suggestion below regarding the addition of the FEMA 5/15/15 memo as a UIN reference as well as revising the sentence in the UIN body. Since the ICN for 872 will be submitted close to 103g, we are currently revising the UIN and will be resubmitting it shortly.
Kara From: Hoellman, Jordan [2]
Sent: Monday, May 21, 2018 10:52 AM To: Stacy, Kara M. <KMSTACY@southernco.com>
Cc: Kent, Lauren <Lauren.Kent@nrc.gov>
Subject:
NRC Comment on UIN for ITAAC Index No. 872 Hi Kara - Please see the comment below regarding the UIN for ITAAC Index No. 872. Please let us know if you have any questions.
Thank you, Jordan Comment on UIN for ITAAC Index # 872 In the first paragraph (last sentence) of the ITAAC Completion Description section of Notice of Uncompleted ITAAC Letter No. ND-18-0637 (May 11, 2018), for ITAAC No. E.3.9.08.01.03 (Index No. 872), SNC states:
Offsite deficiencies as used in this ITAAC are considered to be Level 1 Findings, Level 2 Findings, and Plan Issues as defined in FEMA P-1028, Federal Emergency Management Agency (FEMA) Radiological Emergency Preparedness Program (Reference 1).
1
In addition to the reference to FEMA P-1028 (i.e., FEMA P-1028, Program Manual - Radiological Emergency Preparedness, January 2016), the UIN should also reference FEMAs May 15, 2015, Memorandum from Andrew Mitchell (Director, Technological Hazards Division (THD)), to Radiological Emergency Preparedness Program (REPP) Staff, Regional Assistance Committee (RAC) Chairs, and Federal Preparedness Coordinators (FPCs);
Subject:
New Terms to Classify REPP Exercise-Related Observations and Issues. (See ADAMS Accession No. ML18138A258). The reference to this FEMA memorandum is necessary because it provides the direct connection between a Level 1 Finding and a Deficiency classification (offsite deficiencies is the term used in ITAAC No. E.3.9.08.01.03, Index No. 872, Acceptance Criterion 8.1.3).
FEMAs May 15, 2015, memorandum specifically states (in part) that Level 1 Findings will have the same requirements as the current Deficiency classification, while Level 2 Findings and Plan Issues will be afforded additional HSEEP-compliant avenues for resolution. Given this direct correlation between Level 1 Findings and Deficiencies, as well as the definition of Level 1 Findings (in both the FEMA memo and P-1028), the correlation of deficiencies with the new FEMA classifications (indicated above) should be limited to Level 1 Findings only. This is due to the importance of FEMA deficiencies (now Level 1 Findings), with regard to the protection of the health and safety of the public living in the vicinity of a nuclear power plant.
A suggested revision to SNCs letter (quoted sentence above) is: Offsite deficiencies as used in this ITAAC are considered to be Level 1 Findings, as defined in FEMAs January 2016 Program Manual - Radiological Emergency Preparedness (FEMA P-1028), and as addressed in FEMAs May 15, 2015, Memorandum, entitled New Terms to Classify REPP Exercise-Related Observations and Issues.
2
Hearing Identifier: Vogtle_COL_Docs_Public Email Number: 289 Mail Envelope Properties (SN6PR09MB2608D64AD3AD2ABB875F5800D5620)
Subject:
SNC Response to NRC Comment on UIN for ITAAC Index No. 872 Sent Date: 6/1/2018 9:34:59 AM Received Date: 6/1/2018 9:35:01 AM From: Hoellman, Jordan Created By: Jordan.Hoellman2@nrc.gov Recipients: