Responds to NRC 870916 Request for Addl Info Concerning Util Response to Generic Ltr 83-28,Item 4.2 Part 3 & 4 Re Cycle Determination & Replacement of Reactor Trip Breakers &/Or Components Consistent W/Determined Life Cycle
ML18151A114
Person / Time
Site: Surry, North Anna, 05000000
Issue date: 10/16/1987
From: Stewart W
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
87-593, GL-83-28, NUDOCS 8710220332
Download: ML18151A114 (2)


Text

e e

VIRGINIA EL.ECTRIC AND POWER COMPANY RICHMOND, v.lJ:SMOO.d3!;:i3 2 61 W. L. STEWART VICE PllESIDE:NT NUCLEAR OPERATIONS

/. fQ81 OCT 22 A ro*

  • 02 October* 16, 1987 United States Nuclear Regulatory Commission Attention:

Document Control Desk Washington, D.C.

20555 Gentlemen:

VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNITS 1 AND 2 NORTH ANNA POWER STATION UNITS l AND 2 REQUEST FOR ADDITIONAL INFORMATION ON GENERIC LETTER 83-28 ITEM 4.2 PARTS 3 AND 4 Serial No.

NO/TAH:jmj Docket Nos.

License Nos.87-593 50-280 50-281 50-338 50-339 DPR-32 DPR-37 NPF-4 NPF-7 In your letter of September 16,

1987, the USNRC requested additional information concerning Virginia Electric and Power Company's response to Item 4.2 parts 3 and 4 of Generic Letter 83-28.

These items pertain to life cycle determination and replacement of the Reactor Trip Breakers (RTBs) and/or breaker components consistent with the determined life cycle.

As we stated in our April 7, 1986 presentation to the USNRC, and confirmed in our letters of June 27, 1986 and July 20, 1987, Virginia Electric and Power Company has implemented a refurbishment program which has Westinghouse inspect and rebuild the RTBs to an "as built or new condition" during each refueling outage for 3 consecutive fuel cycles.

Currently, North Anna has undergone two fuel cycles and Surry one cycle under this program resulting in a total of 24 breaker refurbishments.

Upon completion of the program, a review of the wear data obtained will be used to revise the program as appropriate.

To

date, no components affecting the safety functions of the RTBs have been found to be in a condition which would inhibit these components or the RTBs from functioning.

Our experience during the refurbishment program demonstrates that the qualified life of the refurbished breakers is expected to exceed the intervals between refurbishments.

---.~-~---*... - \\

~8710220332 871010

.**.. I 1*, PDR ADOCI( 05000280 p

p~

The Westinghouse Owners Group (WOG) discussed the request for information on these items at the General Session, September 24-25, 1987, and it was decided that the WOG Technical Specification Subcommittee would be the appropriate group to address these concerns.

The subcommittee is to meet during November 1987 and we will provide a more specific action plan by January 15, 1988.

Very truly yours,

~~

W. L. Stewart cc:

U. S. Nuclear Regulatory Commission 101 Marietta Street, N.W.

Suite 2900 Atlanta, GA 30323 Mr. W. E. Holland NRC Senior Resident Inspector Surry Power Station Mr. J. L. Caldwell NRC Senior Resident Inspector North Anna Power Station