Notifies of Revised Listed Completion Schedules for Generic Ltr 83-28 Items Re Classification Administrative Procedure, Installation of Counters on DB-50 Breakers & Nutac Review for Vendor Interface Program
ML18143B414
Person / Time
Site: Surry  Dominion icon.png
Issue date: 08/21/1985
From: Stewart W
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: Harold Denton, Varga S
Office of Nuclear Reactor Regulation
References
85-063C, 85-63C, GL-83-28, NUDOCS 8508270023
Download: ML18143B414 (2)


Text

......

WILUAM L SrEwART Vice President Nuclear Operations August 21, 1985 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation Attn:

Mr. Steven A. Varga, Chief Operating Reactors Branch No. 1 Division of Licensing U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Gentlemen:

VIRGINIA POWER SURRY POWER STATION, UNITS 1 AND 2 GENERIC LETTER 83-28 SCHEDULE REVISION Nuclear Operations Department Past Office Bax 26666 One fames River Plaza Richmond, Virginia 23261 VIRGINIA POWER Serial No. 85-063C NO/DWS:cfm Docket Nos. 50-280 50-281 License Nos. DPR-32 DPR-37 As described in our February 8, 1985 revised response to Generic letter 83-28, various items of improvements were planned for completion.

A schedule was provided indicating general milestones of April 1, 1985 and July 1, 1985.

Some of the items planned for completion remain incomplete and a

rev1s1on of our February 8, 1985 schedule is necessary.

Specifically, the following items are rescheduled for completion:

  • Revisions to Station Classification Administrative Procedure For item 2.2.1, improvements to our classification Administrative Procedure 73 were originally planned for completion by April 1, 1985.

These improvements will clarify the use of Safety Related definitions in the classification process. These changes are rescheduled for completion by September 1, 1985.

  • Installation of Counters on the DB-50 Breakers For item 4.2.1, improvements to install counters on the main & bypass Reactor Trip B~eakers, which will assist in the maintenance and trending activities, were originally planned for installation by July 1, 1985. Due to material receipt problems, these counters were not installed by July 1, 1985.

The counters are now on site and will be installed during the next outage of sufficient duration but not later than the 1986 refueling outages.

18508270023* 850821 *

, PDR.ADOCK 05000280 I

1, P PDR

VIRGINIA POWER

  • Submittal of our NUTAC Review for the Vendor Interface Program Certain items under Item 2.2.2 were scheduled for submittal at a milestone date of July 1, 1985.

These items involve the completion of our program description for vendor interface. Specifically, submittal of our review of the March 1984 NUTAC as it supports Phase II of a Vendor Interface Program.

This review as it relates to the aspects of SEE-IN, NPRDS and Vendor Service will be submitted by September 1, 1985.