ML18142B885

From kanterella
Jump to navigation Jump to search
COL Docs - SNC Response to Comment on Uin for ITAAC Index No. 613
ML18142B885
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 05/22/2018
From:
NRC
To:
References
Download: ML18142B885 (3)


Text

1 Vogtle PEmails From:

Hoellman, Jordan Sent:

Tuesday, May 22, 2018 7:05 AM To:

Kent, Lauren Cc:

Gaslevic, James; Kleeh, Edmund

Subject:

SNC Response to Comment on UIN for ITAAC Index No. 613 Attachments:

UIN 613 comment response final for NRC.PDF Attached is SNCs response to the comment on UIN for ITAAC Index No. 613. If we want to discuss the response at a future public meeting, please let me know.

Thank you, Jordan Jordan Hoellman Project Manager NRO / DNRL / LB4 U.S. Nuclear Regulatory Commission office: OWFN 08-C18 phone: (301) 415-5481 email: Jordan.Hoellman2@nrc.gov

Hearing Identifier:

Vogtle_COL_Docs_Public Email Number:

278 Mail Envelope Properties (SN6PR09MB26085D4920EDF96114AAF35FD5940)

Subject:

SNC Response to Comment on UIN for ITAAC Index No. 613 Sent Date:

5/22/2018 7:04:47 AM Received Date:

5/22/2018 7:04:52 AM From:

Hoellman, Jordan Created By:

Jordan.Hoellman2@nrc.gov Recipients:

"Gaslevic, James" <James.Gaslevic@nrc.gov>

Tracking Status: None "Kleeh, Edmund" <Edmund.Kleeh@nrc.gov>

Tracking Status: None "Kent, Lauren" <Lauren.Kent@nrc.gov>

Tracking Status: None Post Office:

SN6PR09MB2608.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 430 5/22/2018 7:04:52 AM UIN 613 comment response final for NRC.PDF 340422 Options Priority:

Standard Return Notification:

No Reply Requested:

No Sensitivity:

Normal Expiration Date:

Recipients Received:

1 VOGTLE ICN/UIN ISSUES TRACKING SHEET Date ITEM ICN UIN TOPIC ITAAC INDEX #

ISSUE Licensee Comment 5/11 2

UIN Ancillary generators cabling inspections 613 The UIN states that in-progress cable installation was inspected, but does not state that the final installation of cables was inspected. It should state that, to ensure that the final route of cables was the same as their in-progress route.

In the same paragraph, the phrase A review of the as-built circuit inspection records is performed to confirm indicates that the final installation of cables is inspected.

This wording is consistent with previously submitted UINs for ITAAC 789, 790, & 791 UINs.