ML18142B400
| ML18142B400 | |
| Person / Time | |
|---|---|
| Site: | Ginna |
| Issue date: | 04/07/1975 |
| From: | Platt C Rochester Gas & Electric Corp |
| To: | Office of Nuclear Reactor Regulation |
| References | |
| Download: ML18142B400 (10) | |
Text
MONTHSPORTS iFOR GRAY BOOK PRBPARAT)
NRC DISTRIBUTION FOR PART 50 DOCKET MATERIAL (TEMPORARY FORM)
CONTROL NO:
FILF MONTHLY REPORT FILE FROM.Rochest:er Gas and Electri Corp Rochester, NY C E Platt DATE OF DOC 5
~e 2e TWX RPT 'OTHER TO:
Office of Plans 6 Schedules ORIG l<<signed CC OTI.IE R SENT AEC PDR SENT LOCALPDR CLASS UNCLASS PROPINFO XXXX DESCRIPTION:
Ltr trans the following:
INPUT NO CYS REC'D 1
ENC LOSUR ES:
DOCKET NO:
50-244 Monthly Report for March 1975 Plant 6 Component Operability 6 Availability This Report to be used in preparing Gray Book by Plans 6 Operations.
NUMBER OF COPIES REC'D:
PLANT NAME:
REGinna 81 FOR ACTION/INFORMATION "14-75 JGB BUTLER (L)
W/ Copies CLARK (L) ihlI Co~inc PARR (L)
W/ Copies KNIEL (L)
W/ Copies SCHWENCER (L)
W/ Copies STOLZ (L) lhlI r nnies VAS nL"LO (L)
Copies
.URPLE (L)
W/ICopies ZIEMANN(L)
W/ Copies DICKER (E) lhl/ Cnesine KNIGHTON (E)
W/ Copies YOUNGBLOOD W/ Copies REGAN (E)
W/ Copies LEAR (L) ihlI Cnesirse SPE LS W/ Copies W
opies INTERNALDISTRIBUTION EG-DR OGC, ROOM P-506A GOSSI CK/STAFF CASE GIAMBUSSO BOYD MOORE (L)
DEYOUNG (L)
SKOVHOLT (L)
GOLLER (L) (Ltr)
P. COLLINS DENISE REG OPR FILE gi REGION (2)
T.R. WILSON STEELE TECH REVIEW SCHROEDER MACCARY KNIGHT PAW LICK I SHAO STE LLO HOUSTON NOVAK ROSS IPPOLITO TEDESCO LONG LAINAS BENAROYA VOLLMER DENTON GR IMES GAMMI LL KASTNER BALLARD SPANGLER ENVIRO MULLER DICKER KNIG HTON YOUNGBLOOD REGAN PROJECT LDR HARLESS LIC ASST R. DIGGS (L)
H. GEARIN (L)
F. GOULBOURNE (L)
P. KREUTZE R (E)
J. LEE (L)
M. MAIGRET (L)
S. REED (E)
M. SERVICE (L)
~SHEPPARD (L)
M. SLATER (E)
H. SMITH (L)
S. TEETS (L)
G. WILLIAMS(E)
V. WILSON (L)
R. INGRAM (L)
A/T IND
~
BRAITMAN SALTZMAN ME LTZ PLANS
~ MCDONALD
~ CHAPMAN DUBE (Ltr).
E. COUPE PETERSOiN HART F I E LD (2)
KLECKER EISENHUT WIGG I NTON EXTERNAL DISTR IBUTION Lpphh ppH~Bnons NY end Rochester, NY
~1 TIC (ABERNATHY)
(1)(2)(10) NATIONALLABS
~1 NSIC (BUCHANAN) 1 W. PENNINGTON, Rm E-201 GT 1 ASLB 1
CONSULTANTS 1 Newton Anderson NEWMARK/BLUME/AGBABIAN ACRS HOLDING/SENT 1 PD R-SAN/LA/NY 1 BROOKHAVEN NAT LAB 1 G. ULRIKSON, ORNL 1 AGMED (RUTH GUSSiVIAN)
Rm B-127 GT 1 J. D. RUNKLES, Rm E-201 GT
l!!l/!/l//////!////////l!<t//'li!!!!/!
Ill A NiR
!/// /l/((I(Il/ji!!I////l!!/!l!//!//l/
Il//lllil/Ills!Pal/A!/////////l/Nil ROCHESTER GAS AND ELECTRIC CORPORATION RICR LJs ~ OSIS ~ II TURK
(
RTATR o
89 EAST AVENUE, ROCHESTER, N.Y. 14649 TKLKPHONC AiRKAcooc Tlo 546.2700 Ginna Station April 7, 1975 Office of Plans and Schedules Directorate of Licensing U. S. Nuclear Regulatory Commission Washington, D. C.
20555 I/
I IR h
Subject:
Monthly Report for March, 1975 Operating Status Information R. E. Ginna Nuclear Power Plant Unit No.
1 Docket No. 50-244 I 'I I I= I 4'entlemen:
Pursuant to the letter dated February 19, 1974 of Mr. L. Manning Muntzing, Director of Regulation, enclosed herewith is the re-quested operating status information of the Ginna Station for the month of March, 1975.
Very truly yours, G. E. Platt Superintendent LSL:dal Enclosures cc:
Mr. James P. O'Reilly IIIp
f1 v<
ii
4 UNI'F NAhlE:
DATF.
A ril 4 1975 CohlPLETED BY:
Andrew E. McNamara Operations Aide 0
NIT 1 Telep o e OPERATING STATUS
-2700, ext. 291-214 at Ginna='.
REPORTING PERIOD:
000l 750301 TO.
2400 750331 GROSS HOURS IN REPORTING PERIOD:
744 2.
CURRENTLY AUTHORIZED POWER LEVEL hlWt hlax. Depend.
Capacity (hGVe-Net) 3.
POWER LEVEL TO WHICH RESTRICTED (IF ANY): (hIWe Net) 4.
REASONS FOR RESTRICTIONS (IF ANY):
470 THI S MONTH YEAR TO DATE CUMULATIVE TO DATE 5
~
NUhlBER OF HOURS THE REACTOR WAS CRITICALLY 6
~
REACTOR RESERVE SHUTDOWN HOURS,..........
7.
HOURS GENERATOR ON LINE.....
~ ~
~.
~....
~.
~
- 1. 18 231 1.18 1,646 NA+
34,848.13 8.
UNIT RESERVE SHUTDOWN HOURS....
~....
~...,.
8 ~
GROSS THERhlAL ENERGY GENERATED (MWH) ~
~
~
~
~
~
10 'ROSS ELECTRICAL ENERGY GENERATED (MWH) ~
~
~
11.
NET ELECTRICAL ENERGY GENERATED (hiWH).... ~
12 REACTOR AVAILABILITYFACTOR (1)
~..
~..
~.
~.
13 'NIT AVAILABILTYFACTOR (2)...........
~..
14.
UNIT CAPACITY FACTOR (3) 15.
UNIT FORCED OUTAGE RATE (4)..........
~.
~..
33.33%
31.04%
- 29. 197 3.5%
77.03%
76.24%
76.29%
.5%
325 920 2 467 771 107 414 812 925 102,062 774,089 43 132 090 14 419 743 13,625,251 76.15%
74.39%
66.45%
9;3%
'6.
SHUTDOWNS SCHEDULED OVER NEXT 6 hlONTHS, (TYPE, DATE AND DURATION OF EACH):
Unit Shutdown 3-10-75 for annual refueling - other maintenance.du.Duration F:.8;weeks,.
- 17. IF SHUT DOWN AT END OF REPORT
- PERIOD, ESTIMATED DATE OF STARTUP:
18.
UNITS IN TEST STATUS (PRIOR TO COMhlERCIAL OPERATION):
INITIAL CRITICALITY INITIAL ELECTRICAL POWER GENERATION COhlhlERCIAL OPERATION DATE FORECASTED DATE ACHIEVED (2)
UNIT AVAILABILITYFACTOR (1)
REACTOR AVAILABILITYFACTOR =
HOURS REACTOR WAS CRITICAL GROSS HOURS IN REPORTING PERIOD HOURS GENERATOR ON"LINE GROSS HOURS IN REPORTING PERIOD a1 00 v100 (3)
UNIT CAPACITY FACTOR = NET ELECTRICAL POWER GENERATED 8100 CURRENTLY LICENSED POWER LEVELcGROSS HRS.
IN REPORTING PERIOD (4)
FORCED OUTAGE RATE FORCED OUTAGE HOURS 8100 HOURS GENERATOR ON-LINE + FORCED OUTAGE HOURS
+ Data Not Available 49 88
'l~
ENCLOSURE A
UNZT GINNA STATION UNIT F1 April 4, 1975 Andrew E.
McNamara AndTelejh'one;gP=-1=716-546-2700 Operations Aide Opdezt~o291L214~ at Ginna DAILY PLANT POWER OUTPUT hlONTll March 1975 DAY 10 AVERAGE DAILY hlWe-net 478.88 479.25 479.08 479.04 268.42 246.67 425M) 476.46 410.13 0
DAY 25 26 27 28 29 30 31, AVERAGE DAILY htWe-net 0
0 0
0 0
0 12 13 15 17 18 0
0 0
0
~
0 0
20 21 22 24 0
"'0~ 0 0
49 87
I
SUMMARY
Reactor power level at 100/ from 3-1 to 3-4.
On 3-5 reactor was taken to hot shutdown condition to retrieve two dropped control rods.
Reactor power returned to 100/ level after rod retrieval and remained at this level until plant was shutdown on 3-10 for annual refueling and other mainten-ance.
REPORT MONTH UNIT NAME DATE COMPLETED BY Andrew E. McNamara Operations Aide F.W~~~
Telephone
- t. 1-716-546-2700 ext.
291-214 at Ginna PLANT SHUTDOWNS DATE TYPE F-FORCED S-SCHEDULED DURATION (HOURS)
REASON (I)
METHOD OF SHUTTING DOWN THE REACTOR (2)
COCAENTS 750305 8.5 A
Dropped rods apparently due to water drippage into rod control cabinets during core boring for.h system modification.
750310 504.5 Annual refueling shutdown - other maintenance.
(1)
REASON:
A -
EOUIPMENT FAILURE (EXPLAIN) 8 - MAINT. OR TEST C -
REFUELING D -
REGULATORY RESTRICTION E -
OPERATOR TRAINING AND LICENSE EXAMINATION F - ADMINISTRATIVE G - OPERATIONAL ERROR (EXPLAIN)
(2)
METHOD:
A -
MANUAL B -
MANUAL SCRAM C -
AUTOMATIC SCRAM
ty
( P 4i
)