Forwards 10CFR50,App R Rept - App A,Summary Comparison of 1984 App R Reanalysis & 1980-1982 Post-Fire Safe Shutdown Review. Rept Should Be Incorporated Into Chapter 7 of App R Rept,Per Encl Table of Changes
ML18142A219
Person / Time
Site: Surry  Dominion icon.png
Issue date: 03/21/1985
From: Stewart W
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: Harold Denton, Varga S
Office of Nuclear Reactor Regulation
Shared Package
ML18142A220 List:
References
85-027, 85-27, NUDOCS 8503270490
Download: ML18142A219 (3)


Text

'W1!.LMM L STEW'ART Vice President Nuclear Operations -

March 21, 1985 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation Attn:

Mr. Steven A, Varga, Chief Operating Reactors Branch No. 1 Division of Licensing U.S. Nuclear Regulatory Commission Washington, D. C. 20555 Gentlemen:

VIRGINIA POWER Nuclear Operations Department Post Office Box 26666 One James River Plaza Richmond, Virginia 23261 VIRGINIA POWER Serial No.85-027 NO/JDH:pa Docket Nos. 50-280 50-281 License Nos: DPR-32 DPR-37 SURRY POWER STATION UNIT NOS. 1 AND 2 ADDITIONAL INFORMATION REGARDING THE APPENDIX R REANALYSIS In response to an informal NRC staff request, we submitted information on July 27, 1984, (Serial No. 231A) for North Anna's Appendix R reanalysis which was designated the "Delta Report."

The information consisted of a

summary comparison for North Anna of Vepco's 1984 Appendix R reanalysis and Vepco's 1982 Post-Fire Safe Shutdown Review.

The corresponding Delta Report for Surry Power Station is attached.

The 'Surry Delta Report compares Vepco' s 1984 Appendix R reanalysis and Vepco 's June 18, 1982 (Serial No. 363) Post Fire Safe Shutdown Review.

The attached Surry Delta Report should be incorporated into Chapter 7 of the Surry 10 CFR 50 Appendix R Report binder in accordance with the enclosed Table of Changes.

If you have any questions or need additional information, please contact us immediately.

I VJy truly yours, l\\,~-() n

\\ l "*"""\\. f' A,/,;

\\.Q.v, -µ W. L. Stewart Attachments (10 copies) 850327A8dta ~~85B~ao PDR PDR F

e cc:

Dr. J. Nelson Grace Regional Administrator Mr. D. J. Burke NRC Resident Inspector Surry Power Station Mr. J, Taylor, Director Office of Inspection and Enforcement Mr. T. E. Conlon NRC Region II VIRGINIA POWER

e e

TABLE OF CHANGES The Surry Appendix R reanalysis consists of seven chapters.

Chapters 6 and 7 were submitted to the NRC on July 6, 1984, and supplemented on November 30, 1984.

The attached Delta Report is considered to be an appendix to Chapter 7 and should be inserted in the binder directly behind the last page of Chapter 7.

JH/pa/736/LTR2/pg.4