Requests Extension of Completion Date to 831231 for Charging Pump Svc Water Pump Relocation Mod Committed to in Response to Alternative Safe Shutdown Requirements of App R to 10CFR50,Section III.G.3
ML18141A072
Person / Time
Site: Surry  Dominion icon.png
Issue date: 08/01/1983
From: Stewart W
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: Harold Denton, Varga S
Office of Nuclear Reactor Regulation
References
407, NUDOCS 8308090305
Download: ML18141A072 (2)


Text

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261

w. L. STEWART VrcE PJ.<ESrDENT NUCLEAR 0PERATXONS August 1,1983 Mr. Harold R. Denton, Director Serial No. 407 Office of Nuclear Reactor Regulation PSE/RCC/jdm:0576C Attn: Mr. Steven A. Varga, Chief Docket Nos. 50-280 Operating Reactors Branch No. 50-281 Division of Licensing License Nos. DPR-32 U.S. Nuclear Regulatory Commission DPR-37 Washington, D.C. 20555 Gentlemen:

APPENDIX R TO 10CFR50, SECTION III.G.3 ALTERNATIVE SAFE SHUTDOWN SURRY UNIT NOS. 1 AND 2 In our letter dated December 31, 1982 (Serial No. 728) Vepco committed, for item number 7, to have installed the Charging Pump Service Water Pump Relocation modification at Surry Power station by the 1st refueling of Unit II after January 1, 1983.

Since the submittal and acceptance of our commitment, Vepco has been in the process of engineering design modifications and procuring materials to comply with this co~mitment. As of this time, our engineering and construction to remove existing interferences is complete and construction has begun to construct the new pump enclosure. Purchase orders have been placed for long lead time items which include new safety related and environmentally qualified pumps, strainers and associated valves and controls. Delivery estimates from vendors have necessitated Vepco to review construction schedules and revise accordingly based on promised delivery dates for required equipment.

Schedules for the delivery of the qualified pump motors are in development. Substitute motors will however be used prior to receipt of the qualified motors and will be qualified for interim usage. All other equipment deliveries will support a December 31, 1983 implementation date. Therefore, Vepco requests an extension for the completion of this project to December 31 , 1983. This extension is required in order for Vepco to install and functionally test the new system and is based on promised delivery dates from our vendors. Vepco will continue to expedite the construction and delivery of equipment associated with this project in an effort to improve the completion date.

8308090305 830801 PDR ADOCK 05000280 F PDR

VIRGINIA. ELECTRIC AND POWER COMPANY TO Mr. Harold R. Denton

  • 2 Should you need further information, please feel free to contact us.

Very truly yours, r,r*

U.L~ ~t~--

'-\ I

w. L. Stewart cc: Mr. R. C. DeYoung, Director NRC Office of Inspection and Enforcement Division of Reactor Operations Inspection Washington, DC 20555 Mr. J. P. 0 Reilly, Regional Administrator 1

Region II 101 Marietta Street, Suite 2900 Atlanta, GA 30303