Suppls 830503 Request for Exemption to 10CFR50.48(c)(4),due to Rev in Refueling Outage Schedule for 10CFR50,App R,Section III.G.3 Mods.Outage Scheduled for 830627
ML18141A028
Person / Time
Site: Surry Dominion icon.png
Issue date: 06/27/1983
From: Stewart W
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: Harold Denton, Varga S
Office of Nuclear Reactor Regulation
References
728B, NUDOCS 8307010020
Download: ML18141A028 (1)


Text

-

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 W. L. STEWART VICE PRESIDENT NUCLEAR 0Jc>ERATI0NS June 27, 1983 Mr. Harold R. Denton, Director Serial No. 728B Office of Nuclear Reactor Regulation NO/WDC:cfm Attn: Mr. Steven A. Varga, Chief Docket No. 50-281 Operating Reactors Branch No. 1 License No. DPR-37 Division of Licensing U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Gentlemen:

EXEMPTION TO 10 CFR 50.48(c)(4)

INSTALLATION SCHEDULE FOR APPENDIX R TO 10 CFR 50, SECTION III.G.3 SURRY POWER STATION UNIT NO. 2 This letter supplements our letter dated May 3, 1983 (Serial No. 728A) in which Vepco requested an exemption to 10 CFR 50.48(c) (4) because of a revision in the refueling outage schedule for Surry Unit 2. Due to power needs, the refueling outage for Surry Unit 2 has been delayed until the completion of the Surry Unit 1 refueling outage. The Surry Unit 2 outage previously scheduled for May 1, 1983 is now scheduled to commence approximately June 27, 1983.

The 10 CFR 50. 48 (c) ( 4) exemption request was to allow Appendix R modifications for Surry Unit 2 to be completed during the 2nd refueling outage after May 17, 1983. The 2nd refueling outage after May 17, 1983 for Surry Unit 2 is presently scheduled to begin in February, 1985.

Very truly youJS, I

/ffld.Lytr' W. L. Stewart I'(""

cc: Mr. James P. O'Reilly Regional Administrator Region II Mr. R. C. DeYoung, Director NRC Office of Inspection and Enforcement Division of Reactor Operations Inspection Mr. D. J, Burke NRC Resident Inspector Surry Power Station