Forwards Response to 830404 Ltr Re Category IV Equipment. Equipment Qualification File Packages Submitted in Support of Specific Identified Items.Response to 830126 Ltr Re Proposed Corrective Actions Expected by 830520
ML18139C338
Person / Time
Site: Surry  Dominion icon.png
Issue date: 05/11/1983
From: Stewart W
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: Harold Denton, Varga S
Office of Nuclear Reactor Regulation
References
PSE-SEW:LMF:049, PSE-SEW:LMF:49, QDR-5437-212-01, QDR-5437-212-1, QDR-5437-252-01, QDR-5437-252-1, NUDOCS 8305180372
Download: ML18139C338 (3)


Text

e VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261

'-- - -* ~

W. L. STEWART VxcE PRESXDENT NUCLEAR OPERATIONS May 11, 1983 Mr. Harold R. Denton, Director Serial No.: 085E

  • Office of Nuclear Reactor Regulation PSE/SEW:lmf:0469C Attention: Mr. Steven A. Varga, Chief Docket Nos.: 50-280 Operating Reactors Branch No. 50-281 Division of Licensing License Nos.:DPR-32 U. S. Nuclear Regulatory Commission DPR-37 Washington, D. C. 20555 Gentlemen:

TECHNICAL EVALUATION REPORTS ENVIRONMENTAL QUALIFICATION OF SAFETY-RELATED ELECTRICAL EQUIPMENT SURRY POWER STATION UNITS 1 AND 2 Vepco provided its thirty (30) day response to the NRC Safety Evaluatio~

Report for Surry Power Station, Unit Nos. 1 and 2 on the environmental qualification of safety-related electrical equipment by letter (Serial No.

085C) dated March 9, 1983. The response provided in this letter did not address Category IV equipment items, since it was not required by the SER.

Your letter of April 4, 1983 advised Vepco of this response requirement.

Attachments 1 and 2 provide the Vepco response to Category IV equipment items. Attachments 3 and 4 are equipment qualification file packages (QDR s) 1 which are submitted in support of specific equipment items identified in Attachments 1 and 2. These QDR s have not been previously submitted to the 1

NRC.

This completes the thirty (30) day response requirements of the April 4, 1983 letter. Additionally, it should be noted that the response to the January 26, 1983 letter with regard to plans for qualification or replacement and a schedule for accomplishing proposed corrective actions (Ninety (90) Day Response) has been superceded by the requirements of 10CFR50.49. In this regard, the Vepco response will be provided by May 20, 1983.

,8305180372 830511 PDR ADOCK 05000280 p PDR

e VIRGINIA ELECTRIC AND POWER COMPANY TO Q...-.--** This is consistent with the requirements of 10CFR50.49 and your April 4, 1983 clarification letter.

Very truly yours, I

µCv'4fY W. L. Stewart ~

cc: Mr. James P. 0 Reilly w/attachments 1

Regional Administrator Region II 101 Marietta Street, Suite 2900 Atlanta, Georgia 30303

J Attachments Atta~hment 1: Unit 1: Response to NRC Category IV Attachment 2: Unit 2: Response to NRC Category IV Attachment 3: QDR-5437-212-01: Compsip Delphi Hydrogen Analyser, Unit 1 Attachment 4: QDR-5437-252-0l: Compsip Delphi Hydrogen Analyzer, Unit 2

..: