Advises of Status of Instrumentation for Detection of Inadequate Core Cooling Per NUREG-0737,Item II.F.2.Reactor Vessel Level Indication Sys Will Be Completed During Next Refueling Outage Scheduled for 830603
ML18139B886
Person / Time
Site: Surry Dominion icon.png
Issue date: 05/25/1982
From: Leasburg R
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: Harold Denton, Varga S
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-2.F.2, TASK-TM 314, NUDOCS 8206020335
Download: ML18139B886 (2)


Text

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND., VIRGINIA. 23261 R.H.LEASBURG VICE PRESIDENT NucJ.E..u< OPERATIONS May 25, 1982 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation Attn:

Mr. Steven A. Varga, Chief Operating Reactors Branch No. 1 Division of Licensing U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Gentlemen:

Serial No. 314 NO/JHL:acm Docket No. 50-281 License No. DPR-37 INSTRUMENTATION FOR THE DETECTION OF INADEQUATE CORE COOLING NUREG-0737, ITEM II.F.2 SURRY POWER STATION UNIT NO. 2 The purpose of this letter is to report the status of the Reactor Vessel Level Indication System as required by Item II.F.2 of NUREG-0737.

In Vepco I s response to NUREG-0737, Revision 2, it was stated, "that all in containment work with the exception of filling and venting the system will be complete by January 1, 1982."

The Unit 2 system is now "scheduled to be operational after the system is filled and vented during the Spring maintenance outage.

The system will be fully operational when the reactor vessel vent system is operational in July, 1982."

While performing hydro testing the isolation bellows were destroyed, New material has been ordered but the delivery schedule will not accommodate the unit startup schedule.

In addition, Westinghouse recommended that relocating three resistance temperature detectors would improve system accuracy.

Also, isolation valves that are manufactured by Autoclave Manufacturing have been recalled because of a "stick open" or nstick closed" problem.

It is Vepco I s commitment to have the Reactor Vessel Level Indication System fully operational during the next scheduled refueling outage, for Surry Unit 2, which is currently scheduled for June 3, 1983.

This information concerning the delay in filling and venting the Reactor Vessel Level Indication System has been conveyed by telephone on May 21, 1982 to Mr. D. J. Burke, NRC Resident Inspector at Surry Power Station and to Mr.

J. D. Neighbors, NRC Project Manager for Surry Power Station.

If you have any questions, please contact us.

J320"6020335 820525

  • poR :**ADOCK 05000281
  • p.*..

PD~:..,

Very truly yours,

, nL ~)/1a

\\ J

~)

,J R: H. Leas urg

e VIROINIA ELECTRIC AND POWER COMPANY TO Harold R. Denton cc:

Mr. Richard C. DeYoung, Director Office of Inspection and Enforcement Washington, D. C. 20555 Mr. James P. O'Reilly Regional Administrator Region II Atlanta, Georgia 30303