Application for Amend to Licenses DPR-32 & DPR-37 Consisting of Changes to Tech Specs Re Auxiliary Feedwater Flow Rate Instrumentation Surveillance Requirements & Containment Isolation Valves
ML18139B502
Person / Time
Site: Surry  Dominion icon.png
Issue date: 08/21/1981
From: Leasburg R
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: Harold Denton, Varga S
Office of Nuclear Reactor Regulation
Shared Package
ML18139B503 List:
References
486, NUDOCS 8109010271
Download: ML18139B502 (2)


Text

l VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND., VIRGINIA 23261 August 21, 1981 R.H.LEASBURG VXOE PRESIDENT NucLEAR OPERATIONS Mr. Harold R. Denton, Director Serial No. 486 Office of Nuclear Reactor Regulation NO/WRM:acm Attn: Mr. Steven A. Varga, Chief Docket Nos. 50-280 Operating Reactors Branch No. 1 50-281 Division of Licensing License Nos. DPR-32 U. S. Nuclear Regulatory Commission DPR-37 Washington, D. C. 20555 Gentlemen:

AMENDMENT TO OPERATING LICENSES DPR-32 AND DPR-37 SURRY POWER STATION UNITS NO. 1 AND NO. 2 SUPPLEMENT TO PROPOSED TECHNICAL SPECIFICATION CHANGE In a letter dated November 14, 1980 (Serial No. 915), we requested a change to the Technical Specifications for Surry Power Station, Units No. 1 and No. 2.

Enclosed are proposed Technical Specification changes to supplement our November 14, 1980 license amendment application.

These supplemental changes address comments received from members of the Staff during their review of the November 14, 1980 submittal. Specifically, the changes incorporate additional actions required for failing to fulfill certain Limiting Conditions of Operation, modify auxiliary feedwater flow rate instru-mentation surveillance requirements, incorporate a listing of containment isolation valves in Section 3.8 as requested by the July 2, 1980 Staff letter, and reformat previous information provided in the original license amendment application.

This request has been reviewed and approved by the Surry Station Nuclear Safety and Operating Committee and by the Safety Evaluation and Control staff.

It has been determined that this request does not pose an unreviewed safety question.

We have reviewed this request in accordance with the criteria in 10 CFR 170.22. Since this request supplements our November 14, 1980 submittal, no additional license amendment fee is required.

VeryliZ;-

/f Leasburg

Attachment:

1. Supplement to Proposed Technical Specification Change cc: Mr. James P. O'Reilly, Director Office of Inspection and Enforcement Region II
  • , Ei9it~l1~~IsHti, PDR

e COMMONWEALTH OF VIRGINIA)

)

CITY OF RICHMOND )

The foregoing document was acknowledged before me, in and for the City and Commonwealth aforesaid, today by R.H. Leasburg, who is Vice President-Nuclear Operations, of the Virginia Electric and Power Company. He is duly authorized to execute and file the foregoing document in behalf of that Company, and the statements in the document are true to the best of his knowledge and belief.

Acknowledged before me this ~ / _,,,.,7 day of . t ' . ~ , 19 ~ i My Commission expires: ~~  ;;l. b , 19 ~ S .

Notary Public (SEAL)