ML18139A761
| ML18139A761 | |
| Person / Time | |
|---|---|
| Site: | Surry, North Anna |
| Issue date: | 10/22/1980 |
| From: | Sylvia B VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.) |
| To: | Eisenhut D Office of Nuclear Reactor Regulation |
| References | |
| 691, NUDOCS 8010240451 | |
| Download: ML18139A761 (1) | |
Text
'
VIRGINIA ELECTRIC AND POWER COMPANY RXCHMOND,VXRGXN.IA 23261 Mr. Darrel G. Eisenhut, Director Division of Licensing U. S. Nuclear Regulatory Commission Washington, D.C.
20555
Dear Mr. Eisenhut:
October 22, 1980 Serial No. 691 NO/RMT:ms Docket Nos. 50-280 50-281 50-338 50-339 License Nos. DPR-32 DPR-37 NPF-4 NPF-7
SUBJECT:
INTERIM CRITERIA FOR SHIFT STAFFING This is in response to your letter of July 31, 1980 regarding shift staffing requirements.
A thorough examination has been conducted of current staffing practices and capabilities as stipulated in your letter at both Surry and North Anna Power Stations.
Based on the results of that review it has been determined that shift staffing is in compliance with the criteria set forth.
Very truly yours,
~ii~-~
Operations and Maintenance cc:
Mr. James P. O'Reilly, Director Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission 101 Marietta Street, Suite 3100 Atlanta, Georgia 30303 V
~o~I s,lo