Provides Updated Schedule for Completion of Lessons Learned short-term Requirement for Redundant Indication of Emergency Condensate Storage Tank Water level.Long-term Requirements for safety-grade Class IE Indication Sys Under Evaluation
ML18139A248
Person / Time
Site: Surry, North Anna  
Issue date: 05/19/1980
From: Sylvia B
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: Harold Denton, Eisenhut D
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0578, RTR-NUREG-0585 NUDOCS 8005220611
Download: ML18139A248 (2)


Text

'-~ -

e Vu101NIA ELECTRIC AND PowER COMPANY RICHMOND,VIRGINIA 23261 May 19, 1980 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation Attn:

Mr. Darrell G. Eisenhut, Director Division of Licensing U. S. Nuclear Regulatory Commission Washington, D. C.

20555

Dear Mr. Denton:

Serial No.

NO/FHT:baw Docket Nos:

License Nos:

Surry Power Station Units 1 and 2 North Anna Power Station Units 1 and 2 Auxiliary Feedwater System Requirements 406 50-280 50-281 50-338 50-339 DPR-32 DPR-37 NPF-4 NPF-7 Our previous letters, Serial No. 016, dated January 15, 1980, and Serial No.

149/02080, dated March 31, 1980, for North Anna 1 and Surry 1 and 2, respective-ly, provided commitments for implementation of the Short Term Requirement for redundant indication of Emergency Condensate Storage Tank water level.

We are presently procuring materials to accomplish these modifications and are providing the following updated schedule for completion of these changes.

Surry Units 1 and 2 We anticipate receipt of equipment and materials necessary to implement the short term requirement of redundant level indication during September, 1980.

We expect to accomplish the installation of the redundant indication during the first outage of sufficient duration following receipt of materials.

North Anna Unit 1 We expect delivery of equipment needed to accomplish the short term requirement of redundant indication by the end of October, 1980.

Installa-tion will be scheduled for the first outage of sufficient length following receipt of materials.

North Anna Unit 2 Installation of modifications to fulfill the short term requirements is proceeding at this time.

We expect that, if no problems are encountered, these modifications will be completed shortly.

so 052 2 0'1 I/

()

l l

e VIRGINIA ELECTRIC AND POWER COMPANY TO Mr. Harold R. Denton 2

All Units We are presently evaluating environmental qualification of control room in-dicators to be used in the long term to satisfy the requirement for a safety-grade Class lE indication system.

Procurement schedules are not known at this time, but implementation of the long term requirements will be scheduled for the first outage of sufficient duration following receipt of qualified equipment.

If you have any questions, or require additional information, please contact this office.

cc:

Mr. James P. O'Reilly Very truly yours, (U P.~1,L)

B. R. *via Manager-Nuclear Operations and Maintenance