Text
soo5ozo S'S~
_D COMMONWEALTH of VIRGINIA J. B. JACKSON, JR.
ADMINISTRATOR Council on the Environment April 29, 1980 Mr. Ronald L. Ballard, Chief Environmental Projects Branch 1 Division of Site Safety and Environmental Analysis Nuclear Regulatory Commission Washington, D.C.
20555
Dear Mr. Ballard:
903 NINTH STREET OFFICE BUILDING RICHMOND 23219 804-766-4500 The Commonwealth of Virginia has completed its review of the Draft Environmental Impact Statement for steam generator repair at Surry Power Station(Docket No. 50-280).
The Council on the Environment is responsible for coordinating the State's review of environmental impact statements and responding to appropriate federal officials on behalf of the Commonwealth.
The following agencies took part in the review of this document:
Commission of Game and Inland Fisheries Commission of Outdoor Recreation Department of Agriculture and Consumer Services Department of Conservation and Economic Development Department of Health Marine Resources Commission State Office of Emergency and Energy Services State Water Control Board Virginia Institute of Marine Science Crater Planning District Commission County of Surry The Commonwealth has no objection to the proposed repair of the steam generator at Surry Power Station, Unit #1, since the repair will reduce the amount of radiation to which the public and VEPCO employees are exposed.
Thank you for the opportunity to review this draft environmental statement.
Sincerely;
~,~~
(I,, J. B. Jackson, J:)
JBJr:CHE/gcj Enclosure cc:
The Honorable Maurice B. Rowe, Secretary of Commerce and Resources Mr. Bruce B. Meador, Department of Conservation and Economic Development Dr. Robert B. Strobe, Department of Health
~-
- 8.
REVIEW INSTRUCTIONS:
A)
Please review the docum~nt carefully.
reviewed earlier (e.g., if the current please cons{dc:r previous comrncn~s *
/,~f*...
If the prop~sal has bccn*/,/i "**-'
document is a FINAL EIS),
B)
~.~
Prep.:-,)7e* your agency s comments in a form which would be. acceptab_le for responding di~ectly to a project sponsoring agency.
C)
Use the space below for your connnents.
needed, please attach extra sheets
- Return your comments to:
If additional spa~e is.
.:*r* "*
1Q.?7..
Charles Il. Ellis III
- Environmental Impact Statement Coordinator Council on the Environment 903 Ninth Street Office Building Richmond, Virginia 23219
/bgj (SI,CNED)
(TITLE)
(AGENCY)
- APR j.'.J,:'
I'*
- '
- i:
..,,, ~: ;:tf ~'
- *. ~
.~;
~.. *:.
r e
80 REVI~1? L~STRUCTIONS:
A)
Please review the document carefully. If the proposal has been reviewed earlier (e.g., if the current document is a FINAL EIS),
please consider previous CO!llIIlents.
B)
Prepare your agencyws cor:1ments in a form which would be acceptable for responding directly to a project sponsoring agency.
C)
Use the space below for your comments.
If additional space is needed, please attach extra sheets.
Return your comments to:
Ch~rles ~. Ellis III
- Environmental Impact Statement Coordinator Council on the Envirodr:tE:!nt 903 Ninth Street Office Building Richmond> Virginia 23219
. jk;;/c#'.(270 ~
c-Cffil~1-r.-E1L-'IS---I-TI---
ENVIRONHENTAJ;. IHPACT STATEMENT COORDINATOR COMMENTS Based on the material presented in the Draft Environmental Statement and on independent monitoring by the Health Department of the generator repair project on Surry Unit #1, the Health Department conclude~ that we.
have no objection to the proposal project for Unit #1..
Our findings indicate that the proposed project can be accomplished
.without significant environmental impact.
The steam,generator repair project should avoid future occupational exposures to VEPCO personnel that*
would occur if this equipment is not replaced *.
(SIGNED)
(TITLE)
(AGENCY)
Acting Assistant State Health Commissioner State Health Department