Responds to NRC Request at 800326 & 27 Meeting for Emergency Plans Revised in Accordance w/NUREG-0654.North Anna Emergency Plan Will Be Submitted on 800501.Surry Plan Will Be Submitted on 800602
ML18139A147
Person / Time
Site: Surry, North Anna  Dominion icon.png
Issue date: 04/08/1980
From: Baum E
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: Grimes B
NRC - EMERGENCY PREPAREDNESS TASK FORCE
References
317, NUDOCS 8004140258
Download: ML18139A147 (1)


Text

-

VIRGINIA ELECTRIC AND POWER COMPANY RJ:CHMOND,Vn~G:INIA 23261 April 8, 1980 Mr. Brian K. Grimes Serial No. 317

~mergency Preparedness Task Group LQA/PRB:pwc U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Docket Nos. 50-280 50-281 50-338 50-339

Dear Mr. Grimes:

REVISION TO EMERGENCY PLANS SURRY AND NORTH ANNA POWER STATIONS It was requested by Mr. Roe at our meeting with the joint NRC/FEMA team reviewing Surry Emergency Preparedness at Williams-burg, VA on March 26th and 27th, that we inform you of the date we will be prepared to submit a revised version of the North Anna and Surry Power Stations Emergency Plans.

We are now preparing the revised version of the North Anna Emergency Plan in accordance with the Criteria in NUREG-0654. We estimate that this plan will be submitted to you on May 1, 1980.

The Surry Emergency Plan will be submitted to you on June. 2, 1980.

The plan will be implemented within 90 days following acceptance by your staff. This time is needed for the preparation of new procedures and training our personnel.

If you have any questions concerning this schedule, please contact Mr. Peter Beament at (804)771-4411, who is ready to assist you.

Very truly yours,

,,..--)

p?;t/-5$~

E. A. Baum, Executive Manager Licensing & Quality Assurance