Text
e VIRGINIA ELECTRIC AND POWER COMPANY RJ:ClDlOND,VJ::BGJ:N.[A 23261 March 3, 1980 Mr. Harold R. Denton~ Director Office of Nuclear Reactor Regulation Attn: Mr. A. Schwencer, Chief Operating Reactors Branch No. 1 Division of Operating Reactors U.S. Nuclear Regulatory ColllIIlission Washington, D. C. 20555
Dear Mr. Denton:
Serial No.
168 PO/SPS: sjl Docket Nos. 50-280 50-281 License Nos. DPR-32 DER-37 Enclosed herein is the Final Report (Progress Report No. 6) for the Surry Power Station, Unit No. 2 Steam Generator Repair Program.
This final report completes and fully satisfies the requirements of the license conditions issued under Amendment No. 46 to the operating license for Surry, Unit No. 2.
The report describes the occupational radiation expo-sure expended, the dose reduction techniques employed and their effective-ness, and the radioactive effluents and solid waste generated during the repair program, which connnenced on February 3, 1979 and was completed on December 31, 1979.
If you have any questions on this matter, do not hesitate to contact us.
Enclosure cc: Mr. James P. 0 'Reilly, Director Office of Inspection and Enforcement Region II Very truly yours, z;. m. ~ad:a.~
C. M. Stallings Vice President-Power Supply and Production Operations 80030rJO