Advises That Steam Generator Replacement Will Be Considered Complete on 791231 for Purpose of Progress Reporting Requirements.Final Rept to Be Issued by 800229
ML18136A354
Person / Time
Site: Surry  Dominion icon.png
Issue date: 01/02/1980
From: Stallings C
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: Harold Denton, Schwencer A
Office of Nuclear Reactor Regulation
References
1183, NUDOCS 8001040555
Download: ML18136A354 (1)


Text

l VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND,VIROINIA 23261 January 2, 1980 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation Attention:

Mr. Albert Schwencer, Chief Operating Reactors Branch No. 1 Division of Operating Reactors U. S. Nuclear Regulatory Commission Washington, D. C.

20555

Dear Mr. Denton:

Serial No. 1183 PO/HSM:smv Docket Nos:

50-280 50-281 License Nos:

DPR-32 DPR-37 At the present time, the steam generator replacement activities on Surry Unit 2 are nearing completion (approximately 98% complete).

The tasks which remain are essentially the refueling and startup activities.

For this reason, on December 31, 1979, the steam generator replacement will be considered complete for the purpose of progress reporting requirements in amendment 46 to the operating license for Surry Unit No. 2.

As required by amendment 46, a final report will be issued 60 days thereafter by February 29, 1980.

The tasks which will not have been completed by December 31, 1979 are as follows:

1.

Refueling

2.

Hydrostatic Testing (presently in progress)

3.

Installation of Insulation

4.

Reassembly of the Shroud Cooling System

5.

Touch-up Painting All of these tasks have been previously performed so that the occupational exposure can be estimated for these tasks based on past experience.

The ex-posure for these tasks will then be added to the actual expsosure as of Decem-ber 31, 1979 to determine the total occupational exposure.

If you have any questions on this matter, do not hesitate to contact us.

HSM/smv:3B23 cc:

Mr. James P. O'Reilly, Director Office of Inspection and Enforcement Region II Very truly yours,

~. 2f2!?.,JitU&~ 'y C. M. Stallings Vice President - Power Supply And Production Operations A-oo I 1/0 8001040 ~~