Requests Deferral of Completion Date for Insps Until 791023 or 90 Days After Issuance of Revised IE Bulletin 79-17, Whichever Is Later
ML18136A031
Person / Time
Site: Surry, North Anna  Dominion icon.png
Issue date: 09/14/1979
From: Stallings C
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
622B, NUDOCS 7910050129
Download: ML18136A031 (1)


Text

RICHMOND, VIBGIN J:A 23261

? g s E p \\ 7 A 10 : 2 I September 14, 1979 Mr. James P. O'Reilly, Director

.Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Region II 101 Marietta Street, Suite 3100 Atlanta, Georgia 30303 Serial No.

622B PO/FHT:baw Docket Nos. 50-280-50-281 50-338 50-339 License Nos. DPR-32 DPR-37 NPF-4 CPPR-78

Subject:

IE Bulletin 79-17

Dear Mr. O'Reilly:

Surry Power Station Units 1 and 2 North Anna Power Station Units 1 and 2 We have reviewed the subject Bulletin, "Pipe Cracks in Stagnant Borated Water Systems at PWR Plants", and have had discussions with your Mr. Economos and Mr. Herdt about the scope of the required UT inspections and the techniques to be used.

We understand that a revision to this bulletin is forthcoming clarifying the inspection requirements.

We therefore request a 90 day deferral of the completion date for the inspections until January 23, 1979, or until 90 days after the issuance of the revised bulletin, whichever is later.

We will forward the results of the inspections consistent with the requirements of the bulletin.

cc:

Director Division of Operating Reactors Office of Inspection and Enforcement Washington, _D. C.

20555 Very truly yours, ZP.J2?.~~

C. M. Stallings Vice President-Power Supply and Production Operations