Forwards Target Date List of Required Mods to Fire Protection Plan Based on First Draft of Ser.Mods Requiring Extensive Engineering & Analysis Will Be Implemented During Refueling Outage Tentatively Scheduled for Mar 1981
ML18130A545
Person / Time
Site: Surry  Dominion icon.png
Issue date: 09/07/1979
From: Stallings C
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: Schwencer A
Office of Nuclear Reactor Regulation
References
354C-061478, 354C-61478, NUDOCS 7909110607
Download: ML18130A545 (4)


Text

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGIN IA 23261 September 7,

  • 1979*

Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation Attn:

Mr. Albert Schwencer, Chief Serial No. 354C/061478 PO/SWB:svm Docket Nos.:

50-280 50-281 License Nos.:

DPR-32 DPR-37 Operating Reactors Branch No. 1 Division of Reactor Licensing Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Washington, D. C.

20555

Dear Mr. Denton:

NRC FIRE PROTECTION sA-JU:SU' 11 TnRy on~..

EVALUATION REPORT

,I.JUU, Utaf\\[j Fil£ co*

SURRY POWER STATION f'f VEPCO letter serial No. 354B/061478 agreed to implement fire protection modi-fications based on the first draft of the Safety Evaluation Report for Surry 1

& 2.

The purpose of this letter is to submit target dates keyed to a second draft fire protection Safety Evaluation Report fot Surry Units 1 and 2.

The target dates as shown in attachment (1) are realistic schedule dates that will be used to complete the modifications in an orderly fashion.

We commit to implementing all modifications listed in attachment (1) by October 1980 except as noted.

The below listed modifications will be implemented by the end of the next Unit 2 refueling outage following the present steam generator replacement outage.

This refueling is tentatively scheduled to begin March, 1981.

3.1.5 Safe Shutdown Circuitry Unit 2 3.1.9 3.1.15 The design will be complete by October 1980 however an outage of approximately 2 weeks is required to install the modified circuitry.

If an outage of the required length occurs prior to the next Unit 2 refueling, the modification will be installed, however the modi-fication is being scheduled for the next Unit 2 refueling.

Fire Detection Systems The fire detection modification requires smoke detector installa-tion in almost all areas of the station.

Locating the detectors and designing and installing the electrical panels and wiring is a l/\\

large task and will require the schedule indicated.

t\\.~Y.,

Reactor Coolant Pump Oil Collection System - Unit 2

~ ~\\\\

The design and fabrication of the reactor coolant pump oil collec-l\\

?909110 bD:7 °F

e e

VIRGINIA ELECTRIC AND POWER COMPANY TO Mr. Harold R. Denton, Director tion system will be complete by October 1980, however the refuel-ing outage is required for final fit up of the collecting cans and the containment equipment hatch must be opened to install the oil storage tank.

3.1.23 Monitoring Panels Design of the Fuel Building Monitoring Panels will be complete by August 1980.

However, the Unit 2 refueling outage is required to install the monitoring panels and reactor coolant monitoring in-strumentation.

3.1.25 Safe Shutdown Charging Pump Cross - Connect The charging pump cross connect requires an in depth evaluation and analysis of the implications involved in the cross connect.

Approval of the NSSS Vendor is also required.

The Unit 2 refuel-ing is required to complete the modification.

3.2.5 In-situ Testing In-situ Testing of the smoke detectors cannot be completed until the smoke detector installation is complete.

The above modifications require either extensive engineering and analysis or an extended outage for installation.

Every effort will be made to complete installation and testing prior to the target dates.

However, these dates al-ready reflect an optimistic schedule.

SWB/svm:2H3 Attachment cc:

Mr. James P. O'Reilly, Director Office of Inspection and Enforcement Region II Very truly yours, lJ.c. &1<<1 ~

C. M. Stallirlg/f-Vice President - Power Supply And Production Operations

ATTACHMENT (1)

TARGET DATES FOR COMPLETION OF FIRE PROTECTION MODIFICATIONS 3.1.1 Administrative Controls 3.1.2 Air Flow Detectors 3.1.3 Breathing Appa!atus * - -

3.1.4 Cable Tray Co!~-~s,,

3.1.6 Combustibles 3.1.7 Charcoal Filters 3.1.8 Emergency ~ighting 3.1~9 Fire Detection Systems 3.1.10 Fire Barriers -

3.1.11 Fire Doors 3.1. 12 Fire Dampers 3.1.13 Fire Extinguishers 3.1.14 Fire Ladder 3.1.15 *Floor Drains, Dikes, Curbs Oil Collection Systems 3.1.16 Gas Suppression Systems 3.1.17 Hose Nozzles 3.1.18 Hose Stations_

3. 1. 19
  • Hydrogen Lines 3.1.20 Hose Foam Carts 3.1.21 3.1. 22 3.1. 23 3.1. 24 3.1. 25 Hydrants Valve Supervision Monitoring Panels Penetrations Safe Shutdown 3.1.26 Water Suppression Systems 3.1. 27 Ventilation System 3.1.28 Fire Detection Power Supply 3.1.29 Water Spray phield 3.1.30 Technical Specifications 11/79

,... ;t.**:.*

1/80

°-n-.-;!_,* ::.,

Unit.l~ 4/80~/::it2 -6/8:\\II!.,t Unit 1 - 10 /80/-~riit 2 - 5 /8i'..,.

10/79.*

  • 3/80 -

4/80 ***,

  • 5/81 *. --

9/80.

6/80' 6/80 1/80 11/79.

2/80 Unit 1 - 7 /80; Unit 2 - 3/81 Unit 1 - 10/80; Unit 2 -

10/80, 12/79

i7l80' si80 4/80..

10/79 12/79 Unit 110/80; Unit 2 - 4/81 8/80 5/81 10/80 10/80 8/80 7 /80

. 1/80

~-

.. ~'.,,. :.

3.2.l 3.2.2 3.2.3 3.2.4 3.2.5

~-~-.

Auxiliary Boiler Room Fire Dampers Safe Shutdown Charcoal Filter Hazard In-situ Testing

.. /,,:.

/

4/80 6/80 4/80 4/80 5/81