& Technologies 2768 North u:s. 45 Road P.O. Box430 Metropolis, IL 62960 www.honeywell.com April 25, 2018 UPS/Next Day Air ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Director, Office of Nuclear Material Safety and Safeguards 11555 Rockville Pike Rockville, MD 20852 Docket No. 40-3392; License No. SUB-526
SUBJECT:
HONEWYWELL METROPOLIS WORKS RESPONSES TO REQUEST FOR ADDITIONAL INFORMATION CONCERNING LICENSE RENEWAL APPLICATION IN THE AREAS OF INTEGRATED SAFETY ANALYSIS AND MANAGEMENT MEASURES On February 9, 2017 Honeywell Metropolis Works submitted to the USNRC an application for renewal of USNRC Source Materials License SUB-526; the application also included the submittal of an Environmental Report (ER). On February 12, 2018 the USNRC provided to Honeywell Requests for Additional Information (RAI) on the following sections of the License Application:
- Section 3.0 Integrated Safety Analysis (ISA)
- Section 11.0 Mangement Measures (MM) The responses were originally due by April 13, 2018, however, Honeywell was granted an extension during a meeting held on April 12, 2018 to April 30, 2018. Honeywell prepared and submited draft responses to the ISA/MM RAls on April 6, 2018. During the meeting on April 12, 2018, the NRC had additional questions related to the draft submittal.
Those questions have been answered and incorporated in this version of the RAI responses.
This letter transmits Honeywell's final responses to the ISNMM RAls. To the extent that Honeywell has identified the need for changes to the submitted License Renewal Application (LRA), the enclosed RAI responses include the proposed changes in the form of mark-ups of the affected text. We hope that you find the enclosed materials to be complete and that our responses are helpful in furthering your review of Honeywell's License Renewal Application.
Enclosure 1 contains security sensitive information.
If you have questions or comments regarding this submittal, please contact Mr. Sean Patterson, Regulatory Affairs Manager, at (618) 524-6341.
>*' Sincerely, Plant Manager Enclosure 1 -Final Responses to RAls on Section 3.0 Integrated Safety Analysis and Section 11.0 Management Measures of the MTW License Renewal Application Cc: U.S. NRG Region 11 Marquis One Tower Attention:
Tilda Liu 245 Peachtree Center Avenue N.E., Suite 1200 Atlanta, GA 30303 Honeywell THE POWER OF CONNECTED Performance Materials
& Technologies 2768 North u:s. 45 Road P.O. Box430 Metropolis, IL 62960 www.honeywell.com April 25, 2018 UPS/Next Day Air ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Director, Office of Nuclear Material Safety and Safeguards 11555 Rockville Pike Rockville, MD 20852 Docket No. 40-3392; License No. SUB-526
SUBJECT:
HONEWYWELL METROPOLIS WORKS RESPONSES TO REQUEST FOR ADDITIONAL INFORMATION CONCERNING LICENSE RENEWAL APPLICATION IN THE AREAS OF INTEGRATED SAFETY ANALYSIS AND MANAGEMENT MEASURES On February 9, 2017 Honeywell Metropolis Works submitted to the USNRC an application for renewal of USNRC Source Materials License SUB-526; the application also included the submittal of an Environmental Report (ER). On February 12, 2018 the USNRC provided to Honeywell Requests for Additional Information (RAI) on the following sections of the License Application:
- Section 3.0 Integrated Safety Analysis (ISA)
- Section 11.0 Mangement Measures (MM) The responses were originally due by April 13, 2018, however, Honeywell was granted an extension during a meeting held on April 12, 2018 to April 30, 2018. Honeywell prepared and submited draft responses to the ISA/MM RAls on April 6, 2018. During the meeting on April 12, 2018, the NRC had additional questions related to the draft submittal.
Those questions have been answered and incorporated in this version of the RAI responses.
This letter transmits Honeywell's final responses to the ISNMM RAls. To the extent that Honeywell has identified the need for changes to the submitted License Renewal Application (LRA), the enclosed RAI responses include the proposed changes in the form of mark-ups of the affected text. We hope that you find the enclosed materials to be complete and that our responses are helpful in furthering your review of Honeywell's License Renewal Application.
Enclosure 1 contains security sensitive information.
If you have questions or comments regarding this submittal, please contact Mr. Sean Patterson, Regulatory Affairs Manager, at (618) 524-6341.
>*' Sincerely, Plant Manager Enclosure 1 -Final Responses to RAls on Section 3.0 Integrated Safety Analysis and Section 11.0 Management Measures of the MTW License Renewal Application Cc: U.S. NRG Region 11 Marquis One Tower Attention: