<9' 1
..a 4
7
~ Exelon Generation April 30, 2018 U. S. Nuclear Regulatory Commission Office of Nuclear Regulatory Research ATTN: REIRS Project Manager Mail Stop: CSB-3A07M Washington, DC 20555-0001 Todd Tierney Plant Manager Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657 410 495 5205 Office 484 459 0142 Mobile www.exeloncorp.com todd.tierney@exelon.com Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 Renewed Facility Operating License Nos. DPR-53 and DPR-69 NRC Docket Nos. 50-317 and 50-318
Subject:
Electronic Reporting of Occupational Exposure Reporting Calvert Cliffs Nuclear Power Plant's 2017 Report of Individual Monitoring was electronically submitted on April 30, 2018, via the REIRS web page, in accordance with 1 O CFR 20.2206. This report was filed as indicated below:
File Name:
Date Submitted:
NRC20180427.dat April 30, 2018 Operating System:
Sentinel Radiation Protection Management Software v1.11.02.20151201 There are no regulatory commitments contained in this letter.
If you have any questions concerning this letter, please contact Mr. Larry D. Smith at (410) 495-5219.
Respectfully,
~
for To
. Tierney Plant Manager TAT/KLG/bjm cc:
Document Control Desk, NRC NRC Project Manager, NRC NRC Regional Administrator, Region I NRC Resident Inspector, Calvert Cliffs S. Gray, MD-DNR