Independent Spent Fuel Storage Installation - Submittal of Emergency Plan Update
ML18116A465
Person / Time
Site: Fort Calhoun  Omaha Public Power District icon.png
Issue date: 04/18/2018
From: Blome B
Omaha Public Power District
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation
References
LIC-18-0018
Download: ML18116A465 (2)


Text

-~

Omaha Public Power District April 18, 2018 LIC-18-0018 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 Fort Calhoun Station, Unit No. 1 Renewed Facility Operating License No. DPR-40 NRC Docket No. 50-285 Fort Calhoun Station Independent Spent Fuel Storage Installation NRG Docket No.72-054

SUBJECT:

Emergency Plan Update 10 CFR 72.44(f) 10 CFR 50.54(q) 10 CFR 50, Appendix E 10 CFR 50.4(b)(5)

In accordance with 10 CFR 72.44(f), 10 CFR 50.54(q), 10 CFR 50, Appendix E, Section V, and 10 CFR 50.4(b)(5), please find procedure EP-FC-1001 Rev 4, EP-FC-1001 Addendum 3 Rev 4, and EP-FC-1001 Addendum 4 Rev O enclosed for the Document Control Desk (holder of Copy 165) and the NRC Region IV Branch 1 Secretary (holder of Copies 154 and 155).

REMOVE SECTION INSERT SECTION EP-FC-1001 Rev 3 issued 12/13/2017 EP-FC-1001 Rev 4 issued 04/09/2018 EP-FC-1001 Addendum 3 Rev 3 issued 02/02/2017 EP-FC-1001 Addendum 3 Rev 4 issued 04/09/2018 New document

. EP-FC-1001 Addendum 4 Rev O issued 04/09/2018 This change was reviewed and does not constitute a decrease in effectiveness. No commitments are made in this letter. If you have any questions regarding the previous transmittal, please contact Mr.

Jason Fickbohm at 402-533-6072.

Sincerely, Bradley H. Blome Director - Licensing and Reg Assurance BHB/mec c:

NRC Region IV Plant Support Branch 1 Secretary (2 sets)

J. Kim, NRC Senior Project Manager (w/o enclosures)

Emergency Planning Department (w/o enclosures)

Fort Calhoun Station, PO Box 550 Fort Calhoun, NE 68023/9610 Power Lane, Blair, NE 68008

+I-4 5
lfvl~52b
vtfl fLI/V/ ss

EP-1 Confirmation of Transmittal for Emergency Planning Documents/Information Emergency Plan Page 1 of 1 Rev. 9 Radiological Emergency

[X]

Response Plan (RERP)

D Implementing Procedures D

Emergency Planning Forms EP-FC-1001-(& Addendums)

(EPIP)/(EP-FC-110 thru 115, (EPF) 1001)

D Emergency Planning Department Manual D Other Emergency Planning Document(s)/ Information (EPDM)

Date:

Transmitted to:

Name:

Document Control Desk Copy No: 165 Date:

Plant Support Branch Secretary Copy No: 154 Plant Support Branch Secretary Copy No: 155 The following document(s) / information are forwarded for your manual:

REMOVE SECTION INSERT SECTION EP-FC-1001 Rev 3 Issued 12/13/2017 EP-FC-1001 Rev 4 issued 04/09/2018 EP-FC-1001 Addendum 3 Rev 3 issued 02/02/2017 EP-FC-1001 Addendum 3 Rev 4 issued 04/09/2018 New document EP-FC-1001 Addendum 4 Rev O issued 04/09/2018 Summary of Changes: Please see the enclosed summary of changes.

4~

)

~

Manager - Emergency Planning I hereby acknowle~e receipt of the above documents/information and have included them in my assigned manuals.

Signature:

Date:

Please sign above and return by: 06/18/2017 Beth Cooper Fort Calhoun Station, FC-3-1 Omaha Public Power District 444 South 161h Street Mall Omaha, NE 68102-2247 NOTE: If the document(s)/information contained in this transmittal is no longer requested or needed by the recipient, or has been transferred to another individuals, please fill out the information below.

D Document(s)/lnformation No Longer Requested/Needed D Document(s)/lnformation Transferred to:

Name:

Mailing Address: