Forwards Agreement to Implement Previously Proposed Fire Protection Mods & Technical Evaluations Documented in Sections 3.1 & 3.2 of Ser.All Mods to Be Implemented by Mar 1981 Refueling Outage
ML18116A385
Person / Time
Site: Surry  
Issue date: 08/17/1979
From: Stallings C
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: Schwencer A
Office of Nuclear Reactor Regulation
References
NUDOCS 7908210420
Download: ML18116A385 (5)


Text

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND,VIRGINIA 23261

.August,17; 1979:

Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation Attn:

Mr. Albert Schwencer, Chief Operating Reactors Branch No. 1 Division of Reactor Licensing Nuclear Regulatory Commission U. S. Nuclear Regulatory Commission Washington, D. C.

20555

Dear Mr. Denton:

Serial No. 354B/061478 PO/SWB:svm Docket Nos. 50-280 50-281 License Nos. DPR-32 DPR-37 NRC FIRE PROTECTION SAFETY EVALUATION REPORT SURRY POWER STATION We have reviewed the draft fire protection Safety Evaluation Report.for Surry Units 1 and 2.

As requested by the Commission, Attachment (1) confirms agree-ment to implement previously proposed fire protection modific.ations, additional modifications and technical evaluations documented in Section 3.1 and 3.2 of the Safety Evaluation Report.

All modifications will be implemented by the end of the next Unit 2 refueling following the present steam generator replacement outage.

This refueling is tentatively scheduled to begin March, 1981.

Attachment (2) lists target dates for completion of each modification.

These dates ar~ not commitment dates and represent only estimated completion dates.

These dates may be rearranged if it becomes feasible to shift emphasis to another fire protection modification.

In some cases, the target date represents the date which the work will be sub-stantially complete, but an outage is needed to complete the work.

The modifications proposed and re-evaluation of the adequacy of the fire pro-tection systems should resolve NRC concerns regarding fire protection capa-bility of Surry Power Station. L SWB/svm:3Fl Attachments Very truly yours,

-z;r })?. ~/'a:&';.oe/'

C. M. Stallings Vice President - Power Supply And Production Operations

~

79082lo~Lo

\\f._'

e e

VIUOINIA ELECTRIC AND POWER COMPANY TO Mr. Harold R. Denton, Director cc:

Mr. James P. O'Reilly, Director Office of Inspection and Enforcement Region II ATTACHMENT (1)

Fire Protection Modification Agreements

. A.

VEPCO agrees to implement the modifications as given in Section 3.1 of the draft Safety Evaluation Report for Surry Power Station subject to the following changes as agreed to per a telephone conversation (NRC -

VEPCO, 7-30-79).

(1)

Paragraphs 3.1.3(6) and 5.1.6(6) -

Delete requirement to store self-contained breathing apparatus in storage boxes in control room.

The breathing apparatus will be mounted on the wall.

(2)

Paragraph 3.1. 7 (1) -

Several references are made to smoke and heat detectors alarming in the security building and the control room.

The detectors will alarm in. the security building only.

(3)

Paragraph 3.1.13(3) -

Change all references to "20 lb. carbon dioxide fire extinguisher" to read "15 lb. carbon dioxide fire extinguisher."

(4)

Paragraph 3.1.16(2) bottle.

Change "storage cylinders" to read "pilot (5)

Paragraph 3.1. 17 (1)

Change "variable gallonage fog nozzles with ball valve

  • shutoff" to read "ABC rated adjustable fog nozzles".

(6)

Paragraph 3.1.18 (14) -

Change rrwa11 cabinets" to read "wall mounted hydrant hose house".

(7)

Paragraph 3.1. 27 (1) -

Change paragraph to read "An automati~ sprinkler system will be added to each new filter unit added to the auxiliary building vent-ilation sys tern."

B.

VEPCO agrees to implement the modifications and provide additional infor~

mation as required by Section 3.2 with the following exceptions as agreed per telephone (NRC -

VEPCO, 7-30-79).

(1)

Paragraph 3.2.3(1) -

Change paragraph to read "Ventilation ducts that supply air to the main control room from adjacent areas of the con-trol room complex should be provided with smoke dampers that can be manually operated."

(2)

Paragraph 3.2.5(1) - Delete requirements for one hour fire-rated door.

This door has been replaced with a bullet proof door locked closed with a card reader.

(3)

Paragraph 3.2.5(2) * -

Delete requirement for 3 hour3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> fire door.

The present door is a 3 11 thick rolling steel door that is used for a radiation barrier and always kept closed except when moving equipment in or out.

(4)

Paragraph 3.2.9(1) - Delete "and the charging pump cooling water pump motors".

ATTACHMENT (2)

TARGET DATES FOR COMPLETION OF FIRE PROTECTION MODIFICATIONS 3.1.1 3.1. 2 3.1. 3 3.1.4 3.1. 5 3.1.6 3.1. 7 3.1. 8 3.1. 9 3.1.10 3.1.11

3. 1. 12 3.1.13
3. 1. 14
3. 1. 15 Administrative Controls Air Flow Detectors Breathing Apparatus Cable Tray Covers

_ Safe Shutdown.Circuitry Combustibles Charcoal Filters Emergency Lighting Fire Detection Systems Fire Barriers Fire Doors Fire Dampers Fire Extinguishers Fire Ladder Floor Drains, Dikes, Curbs Oil Collection Systems 3.1.16 Gas Suppression Systems 3.1.17 Hose Nozzles 3.1.18 Hose Stations 3.1.19 Hydrogen Lines 3.1.20 Hose Foam Carts 3.1.21 Hydrants 3.1.22 Isolation Valves for the Water Supply 3.1.23 In-Situ Testing 3.1.24 Monitoring Panels 3.1.25 Penetr_ations 3.1.26 Safe Shutdown 3.1.27 Water Suppression Systems 3.1. 28 Ventilation System 11/79 1/80 1/80 Unit 1 - 4/80; Unit 2 - 6/80 Unit 1 - 6/80; Unit 2 - 1/80 10/79 3/80 4/80 3/81 9/80 9/79 6/80 1/80 11/79 2/80 Unit 1 - 7/80; Unit 2 - 3/81 Unit 1 - 10/80; Unit 2 - 11/80 12/79 7 /80 5/80

  • 4/80 10/79 12/79 4/81 Unit 1 11/80; Unit 2 - 12/80 8/80 4/81 10/80 11/80

3.2.1 Auxiliary Boiler Room 4/80 3.2.2 Diesel Fuel Pumps 7 /80 3.2.3 Fire Dampers 6/80 3.2.4 Fire Detection Systems 8/80 3.2.5 Fire Doors 6/80 3.2.6 Fire Extinguishers 1/80 3.2.7 Safe Shutdown 4/80 3.2.8 Water Suppression System 12/80 3.2.9 Water Spray Shields 7 /80 3.2.10 Charcoal Filter Hazard 4/80 3.2.11 Technical Specifications 1/80