e VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND,VIROINIA 23261 August 30, 1978 Mr. James P. O'Reilly, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Region II 101 Marietta Street, Suite 3100 Atlanta, Georgia 30303
Dear Mr. O'Reilly:
Serial No. 381/062778C PO&M/DLB: das Docket N~
License Nos. DPR-32 DPR-37 This is in response to IE Bulletin 78-10, "Bergen-Patterson Hydraulic Shock Suppressor Accumulator Spring Coils," and is a supplement to our initial response dated August 17, 1978 (Serial No. 381/062778A).
The purpose of this letter is to correct a typographical error which occurred in our initial re-sponse.
In our original response of August 17, 1978, under Item 1, we stated that certain inspections and replacements would be performed "At the next scheduled outage on each unit...*.. ".
This should have read, "At the next scheduled re-fueling outage on each unit..... ".
Should an outage of sufficient duration occur on either unit prior to refueling, this work will be performed at that time.
Very truly yours, Z:*.)) ?. \\_);~*( (.,;: C ),);
~