Responds to NRC 940629 Verbal Comments Re Util Amend Request to Increase Min Required Vol of Fuel Oil Stored in 30,000 Gallon Diesel Fuel Oil Storage Tanks
ML18101A688
Person / Time
Site: Salem  PSEG icon.png
Issue date: 05/02/1995
From: Hagan J
Public Service Enterprise Group
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
LCR-94-15, LR-N95017, NUDOCS 9505110064
Download: ML18101A688 (3)


Text

<;

Joseph J. Hagan Public Service Electric and Gas Company Vice President - Nuclear Operations Public Service Electric and Gas CMAYY O ilSSSx 236, Hancocks Bridge, NJ 08038 609-339-1200 LR-N95017 LCR 94-15 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

ADDITIONAL INFORMATION -

FUEL OIL STORAGE TANK SALEM GENERATING STATION UNIT NOS. 1 AND 2 FACILITY OPERATING LICENSES DPR-70 AND DPR-75 DOCKET NOS. 50-272 AND 50-311 By letter dated June 29, 1994, PSE&G requested a Technical Specification amendment for Salem Unit Nos. 1 and 2, to increase the minimum required volume of fuel oil stored in the 30,0oo*

gallon Diesel Fuel Oil Storage Tanks (DFOST's).

Based on their review of the amendment request, the NRC staff verbally requested confirmation that 1) the procedure changes discussed in the June 29, 1994 letter would be implemented; 2) the minimum level (20 ft. indicated) of the 840,000 gallon capacity bulk Fuel Oil Storage Tank (FOST) is administratively controlled; and 3) the FOST is subject to the same maintenance provisions as the DFOST's.

our response to the NRC comments is provided below.

1)

Operations and Emergency Preparedness Procedures The revisions to the Operations and Emergency Preparedness procedures described in the June 29, 1994 amendment request have been completed.

2)

Fuel Oil storage Tank Level Daily FOST level readings are taken per operations department procedure with a minimum specified level of 20 feet.

If a reading indicates less than 20 feet, shift supervision is notified and additional fuel is ordered.

With approximately 21,000 gallons of<fuel per foot of FOST level, this practice provides assurance that fuel well in excess of a seven day supply is maintained onsite.

3)

Tank Maintenance Periodic maintenance for the FOST and the DFOST's consists of fuel oil sampling for fuel quality, bacteriological sampling and a tank integrity test.

These activities are similar for the FOST and the DFOST, with the exception that the FOST is sampled r-9505110064 950502


..\\

I PDR ADOCK 05000272 P

PDR

"(,.

~;./11:::~-:/

MAY 021995 Document Control Desk LR-N95017 monthly for fuel oil quality, whereas the DFOST's are each sampled quarterly in accordance with Technical Specifications.

Please feel free to contact us if there are. any questions regarding this submittal.

Affidavit c

Mr. T. T. Martin, Administrator - Region I

u. s. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Mr. Leonard N. Olshan Licensing Project Manager -

Salem

u. s. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Mail Stop 14E21 Rockville, MD 20852 Mr. c. Marschall (S09)

USNRC Senior Resident Inspector Mr. K. Tosch, Manager, IV NJ Department of Environmental Protection Division of Environmental Quality Bureau of Nuclear Engineering CN 415 Trenton, NJ 08625 95-4933

~J,.;

STATE OF NEW JERSEY COUNTY OF SALEM

)

SS.

)

REF: LR-N95017 J. J. Hagan, being duly sworn according to law deposes and says:

I am Vice President - Nuclear Operations of Public Service Electric and Gas Company, and as such, I find the matters set forth in the above referenced letter, concerning the Salem Generating Station, Unit Nos. 1 and 2, are true to the best of my knowledge, information and belief.

and Sworn to before me KIMBERL V JO BROWN NOTARY PUBLIC OF NEW JERSEY My Commission expires on --~~-M~y~Co~m~m~iss~io~n~Ex~ri~res~A~p~ril~2~1.~1~99~8.__~~