Forwards Revised Schedule for Svc Water Sys Operational Performance Insp Self Assessment
ML18100B040
Person / Time
Site: Salem  PSEG icon.png
Issue date: 04/25/1994
From: Thomson F
Public Service Enterprise Group
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NLR-N94079, NUDOCS 9405020135
Download: ML18100B040 (3)


Text

PS~G Public Service Electric and Gas Company P.O. Box 236 Hancocks Bridge, New Jersey 08038 Nuclear Department APR 2 5 1994 NLR-N94079 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

REVISED SWSOPI SELF ASSESSMENT SCHEDULE SALEM GENERATING STATION UNIT NOS. 1 & 2 DOCKET NOS. 50-272 AND 50-311 This letter is to submit a revised schedule, attached, for the Service Water System Operational Performance Inspection (SWSOPI) self assessment that was conditionally accepted by the NRC on March 15, 1994 for Salem Units 1 and 2.

Public Service Electric & Gas had initially proposed a start date of April 18, 1994, but due to recent activities requiring substantial Salem Station manpower and the effort involved with supporting the SWSOPI review, it was determined that the assessment could be more rigorously performed with a one month postponement.

PSE&G had previously apprised Region I personnel of this delay.

The new start date for the SWSOPI self assessment is scheduled for May 16, 1994, with the subsequent weeks moved back correspondingly, and is to end on June 17, 1994.

PSE&G does not anticipate any other changes to assessment activities that were presented to the NRC on March 8, 1994.

Please contact us if there are any questions pertaning to the revised schedule.

,---A_tj:_g._c_hI!l~Dt. __ ( _:i L_ ----.. -- ---

9405020135 940425 PDR ADOCK 05000272*

Q PDR The Energy People Sincerely,

.5?~~1 F. X. Thomson, Jr.

Manager -

Licensing & Regulation 95-2168 (B7.5M) 12-90

.. r Doc;::~ament Control Desk NLR-N94079 c

Mr. J. c. Stone Licensing Project Manager Mr. C. Marschall Senior Resident Inspector 2

Mr. T. Martin, Administrator Region I Mr. Kent Tosch, Manager IV New Jersey Department of Environmental Protection Division of Environmental Quality Bureau of Nuclear Engineering CN 415 Trenton, NJ 08625 APR 2 5 1C~r4

WEEK 1

2 3

4 5

6 7

8-13 94MM3-11 SALEM GENERATING STATION SWSOPI SELF ASSESSMENT SCHEDULE DATE ACTIVITIES MAY 16-20 ENTRANCE MEETING WALKDOWN DOCUMENT RETRIEVAL START INSPECTION AT SALEM MAY 23-27 DOCUMENT REVIEWS AT HOME OFFICES MAY 30-JUNE 3 DOCUMENT REVIEWS, WALKDOWNS, INTERVIEWS AT SALEM JUNE 6-10 DOCUMENT REVIEWS AT HOME OFFICES JUNE 13-17 FINAL INSPECTION WEEK AT SALEM EXIT MEETING JUNE 20-24 PREPARE DRAFT REPORT JULY 1 SUBMIT DRAFT REPORT AUGUST 12 ISSUE FINAL REPORT