NRC Integrated Inspection Report 05000456/2018503; 05000457/2018503
ML18100A365
Person / Time
Site: Braidwood Constellation icon.png
Issue date: 04/10/2018
From: Steven Orth
NRC/RGN-III
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
References
IR 2018503
Download: ML18100A365 (7)


See also: IR 05000456/2018503

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE RD. SUITE 210

LISLE, ILLINOIS 60532-4352

April 10, 2018

Mr. Bryan C. Hanson

Senior VP, Exelon Generation Company, LLC

President and CNO, Exelon Nuclear

4300 Winfield Road

Warrenville, IL 60555

SUBJECT: BRAIDWOOD STATION, UNITS 1 AND 2NRC INTEGRATED INSPECTION

REPORT 05000456/2018503; 05000457/2018503

Dear Mr. Hanson:

On March 8, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an Emergency

Preparedness Inspection at your Braidwood Station, Units 1 and 2. On March 8, 2018, the

NRC inspectors discussed the results of this inspection with the Site Vice President,

Ms. M. Marchionda, and other members of your staff. The results of this inspection are

documented in the enclosed report.

The NRC inspectors did not identify any finding or violation of more-than-minor significance.

This letter, its enclosure, and your response (if any) will be made available for public inspection

and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document

Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for

Withholding.

Should you have any questions concerning this inspection, we will be pleased to discuss them

with you.

Sincerely,

/RA/

Steven K. Orth, Chief

Plant Support Branch

Division of Reactor Safety

Docket Nos. 50-456; 50-457

License Nos. NPF-72; NPF-77

Enclosure:

IR 05000456/2018503; 05000457/2018503

cc: Distribution via LISTSERV

B. Hanson

-2-

Letter to Brian C. Hanson from Steven K. Orth dated April 10, 2018

SUBJECT: BRAIDWOOD STATION, UNITS 1 AND 2NRC INTEGRATED INSPECTION

REPORT 05000456/2018503; 05000457/2018503

DISTRIBUTION:

Jeremy Bowen

RidsNrrDorlLpl3

RidsNrrPMBraidwood Resource

RidsNrrDirsIrib Resource

Steven West

Darrell Roberts

Richard Skokowski

Allan Barker

DRPIII

DRSIII

ROPreports.Resource@nrc.gov

ADAMS Accession Number ML: 18100A365

OFFICE

RIII

RIII

RIII

RIII

NAME

GHansen:cl

SOrth

DATE

04/09/18

04/10/18

OFFICIAL RECORD COPY

Enclosure

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Docket Numbers:

50-456; 50-457;72-073

License Numbers:

NPF-72; NPF-77

Report Numbers:

05000456/2018503; 05000457/2018503

Enterprise Identifier: I-2018-503-0000

Licensee:

Exelon Generation Company, LLC

Facility:

Braidwood Station, Units 1 and 2

Location:

Braceville, IL

Dates:

March 5, 2018, through May 8, 2018

Inspectors:

G. Hansen, Senior Emergency Preparedness Inspector

M. Garza, Emergency Preparedness Inspector

J. McGhee, Senior Resident Inspector

D. Sargis, Reactor Engineer

Approved by:

S. Orth, Chief

Plant Support Branch

Division of Reactor Safety

2

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring licensees performance

by conducting an Emergency Preparedness Inspection at Braidwood Station, Units 1 and 2, in

accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs

program for overseeing the safe operation of commercial nuclear power reactors. Refer to

https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations were identified.

Additional Tracking Items

None

3

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures in effect

at the beginning of the inspection unless otherwise noted. Currently approved Inspection

Procedures with their attached revision histories are located on the public website at

http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.

Samples were declared complete when the IP requirements most appropriate to the inspection

activity were met consistent with Inspection Manual Chapter 2515, Light-Water Reactor

Inspection Program - Operations Phase. The inspectors reviewed selected procedures and

records, observed activities, and interviewed personnel to assess licensee performance and

compliance with Commission rules and regulations, license conditions, site procedures, and

standards.

REACTOR SAFETY

71114.01Exercise Evaluation (1 Sample)

On March 7, 2018, the inspectors evaluated the Biennial Emergency Plan Exercise. The

exercise scenario simulated an event at Braidwood Station that initiated with the declaration

and notification of an Alert in response to a hazardous plant condition. The scenario

conditions simulated the escalation of the significance of the event, requiring the declaration

and notification of a Site Area Emergency and a General Emergency, as well as the

development of Protective Action Recommendations that were communicated to the

required state and local government agencies.

71114.08Exercise EvaluationScenario Review (1 Sample)

The inspectors reviewed and evaluated the proposed scenario for the March 7, 2018,

Biennial Emergency Plan Exercise.

OTHER ACTIVITIESBASELINE

71151Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below. (3 Samples)

(1) EP01: Drill/Exercise Performance-1 Sample (July 1, 2017, through December 31, 2017)

(2) EP02: Emergency Response Organization Drill Participation-1 Sample (July 1, 2017,

through December 31, 2017)

(3) EP03: Alert And Notification System Reliability-1 Sample (July 1, 2017, through

December 31, 2017)

INSPECTION RESULTS

No findings or violations were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors confirmed that proprietary information was controlled to protect from public

disclosure. No proprietary information was documented in this report.

4

On March 8, 2018, the inspectors presented the Emergency Preparedness Inspection

results to the Site Vice President, Ms. M. Marchionda, and other members of the licensee

staff.

DOCUMENTS REVIEWED

71114.01Exercise Evaluation (71114.01)

- EP-AA-1000; Exelon Nuclear Standardized Radiological Emergency Plan; Revisions 29

- EP-AA-1001; Exelon Nuclear Radiological Emergency Plan Annex for Braidwood Station;

Revision 34

- EP-AA-1001, Addendum 3; Emergency Action Levels for Braidwood Station; Revision 3

- EP-AA-111; Emergency Classification and Protective Action Recommendations; Revision 21

- EP-AA-111-F-02; Braidwood PAR Flowchart; Revision H

- EP-AA-112; Emergency Response Organization (ERO)/Emergency Response Facility (ERF)

Activation and Operation; Revision 18

- EP-AA-112-400; Emergency Operations Facility Activation and Operation; Revision 13

- EP-AA-113; Personnel Protective Action; Revision 13

- EP-AA-114; Notifications; Revision 14

- EP-AA-122; Drills and Exercise Program; Revision 19

- EP-AA-125-1001; EP Performance Indicator Guidance; Revision 9

- Two Years of Drill and Exercise Timelines; 03/2016-03/2018

- Braidwood 2016 NRC Exercise Evaluation Report; 04/27/2016

- Braidwood September 20, 2016 Focused Area Drill 2014 Evaluation Report; 09/23/2016

- Braidwood December 20, 2016 Emergency Exposure Drill Evaluation Report; 12/22/2016

- Braidwood 4th Quarter 2016 Performance Indicator Drills Report; 01/04/2017

- Braidwood 2017 2nd Half Health Physics Drill Findings and Observations Report; 11/23/2017

- Braidwood 2017 Core Damage Assessment Drill Report; 12/05/2017

- Braidwood 4th Quarter 2017 Performance Indicator Drills Report; 12/11/2017

- Two Year List of Drill and Exercise Corrective Action Program Issues; 03/2016-03/2018

- AR 02622561; EP DEP PI Drill Used Duplicate Players; 02/05/2016

- AR 02638642; Comments and Improvement Items from Jan-Feb EP Drills; 03/10/2016

- AR 02667962; Adverse Trend in DEP Failures/Needs Improvement in LORT; 05/11/2016

- AR 02679189; EPMedical Drill Issue; 06/08/2016

- AR 02718795; EPERO Focus Area Drill (FAD) Lessons Learned; 09/22/2016

- AR 03957101; EP12/20/2016 DEP Drill Lessons Learned; 12/28/2016

- AR 03970916; EPNear Miss on OYE Drill Scenario Confidentiality; 02/06/2017

- AR 04084139; Braidwood EP 12-13-2017 4th Quarter Call In Drill; 12/14/2017

- AR 04103315; Braidwood EP Pre-Exercise Failed Overall Objective J.1; 02/12/2018

- AR 04103318; Braidwood EP Pre-Exercise Failed Facility Objective B.6; 02/12/2018

71114.08Exercise EvaluationScenario Review

- Braidwood Station 2018 NRC Graded Exercise 60 Day Submittal; 12/20/2018

71151Performance Indicator Verification (71151)

- NRC Performance Indicator Data; Emergency PreparednessAlert and Notification System

Reliability; 3rd Quarter 2017-4th Quarter 2017

- NRC Performance Indicator Data; Emergency PreparednessNRC ERO Drill Participation;

3rd Quarter 2017-4th Quarter 2017

5

- NRC Performance Indicator Data; Emergency PreparednessDrill/Exercise Performance;

3rd Quarter 20174th Quarter 2017

- NEI 99-02; Regulatory Assessment Performance Indicator Guideline; Revision 7