ML18100A365
| ML18100A365 | |
| Person / Time | |
|---|---|
| Site: | Braidwood |
| Issue date: | 04/10/2018 |
| From: | Steven Orth NRC/RGN-III |
| To: | Bryan Hanson Exelon Generation Co, Exelon Nuclear |
| References | |
| IR 2018503 | |
| Download: ML18100A365 (7) | |
See also: IR 05000456/2018503
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION III
2443 WARRENVILLE RD. SUITE 210
LISLE, ILLINOIS 60532-4352
April 10, 2018
Mr. Bryan C. Hanson
Senior VP, Exelon Generation Company, LLC
President and CNO, Exelon Nuclear
4300 Winfield Road
Warrenville, IL 60555
SUBJECT: BRAIDWOOD STATION, UNITS 1 AND 2NRC INTEGRATED INSPECTION
REPORT 05000456/2018503; 05000457/2018503
Dear Mr. Hanson:
On March 8, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an Emergency
Preparedness Inspection at your Braidwood Station, Units 1 and 2. On March 8, 2018, the
NRC inspectors discussed the results of this inspection with the Site Vice President,
Ms. M. Marchionda, and other members of your staff. The results of this inspection are
documented in the enclosed report.
The NRC inspectors did not identify any finding or violation of more-than-minor significance.
This letter, its enclosure, and your response (if any) will be made available for public inspection
and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document
Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for
Withholding.
Should you have any questions concerning this inspection, we will be pleased to discuss them
with you.
Sincerely,
/RA/
Steven K. Orth, Chief
Plant Support Branch
Division of Reactor Safety
Docket Nos. 50-456; 50-457
Enclosure:
IR 05000456/2018503; 05000457/2018503
cc: Distribution via LISTSERV
B. Hanson
-2-
Letter to Brian C. Hanson from Steven K. Orth dated April 10, 2018
SUBJECT: BRAIDWOOD STATION, UNITS 1 AND 2NRC INTEGRATED INSPECTION
REPORT 05000456/2018503; 05000457/2018503
DISTRIBUTION:
RidsNrrDorlLpl3
RidsNrrPMBraidwood Resource
RidsNrrDirsIrib Resource
DRPIII
DRSIII
ROPreports.Resource@nrc.gov
ADAMS Accession Number ML: 18100A365
OFFICE
RIII
RIII
RIII
RIII
NAME
GHansen:cl
SOrth
DATE
04/09/18
04/10/18
OFFICIAL RECORD COPY
Enclosure
U.S. NUCLEAR REGULATORY COMMISSION
REGION III
Docket Numbers:
50-456; 50-457;72-073
License Numbers:
Report Numbers:
05000456/2018503; 05000457/2018503
Enterprise Identifier: I-2018-503-0000
Licensee:
Exelon Generation Company, LLC
Facility:
Braidwood Station, Units 1 and 2
Location:
Braceville, IL
Dates:
March 5, 2018, through May 8, 2018
Inspectors:
G. Hansen, Senior Emergency Preparedness Inspector
M. Garza, Emergency Preparedness Inspector
J. McGhee, Senior Resident Inspector
D. Sargis, Reactor Engineer
Approved by:
S. Orth, Chief
Plant Support Branch
Division of Reactor Safety
2
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring licensees performance
by conducting an Emergency Preparedness Inspection at Braidwood Station, Units 1 and 2, in
accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs
program for overseeing the safe operation of commercial nuclear power reactors. Refer to
https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations were identified.
Additional Tracking Items
None
3
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures in effect
at the beginning of the inspection unless otherwise noted. Currently approved Inspection
Procedures with their attached revision histories are located on the public website at
http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.
Samples were declared complete when the IP requirements most appropriate to the inspection
activity were met consistent with Inspection Manual Chapter 2515, Light-Water Reactor
Inspection Program - Operations Phase. The inspectors reviewed selected procedures and
records, observed activities, and interviewed personnel to assess licensee performance and
compliance with Commission rules and regulations, license conditions, site procedures, and
standards.
REACTOR SAFETY
71114.01Exercise Evaluation (1 Sample)
On March 7, 2018, the inspectors evaluated the Biennial Emergency Plan Exercise. The
exercise scenario simulated an event at Braidwood Station that initiated with the declaration
and notification of an Alert in response to a hazardous plant condition. The scenario
conditions simulated the escalation of the significance of the event, requiring the declaration
and notification of a Site Area Emergency and a General Emergency, as well as the
development of Protective Action Recommendations that were communicated to the
required state and local government agencies.
71114.08Exercise EvaluationScenario Review (1 Sample)
The inspectors reviewed and evaluated the proposed scenario for the March 7, 2018,
Biennial Emergency Plan Exercise.
OTHER ACTIVITIESBASELINE
71151Performance Indicator Verification
The inspectors verified licensee performance indicators submittals listed below. (3 Samples)
(1) EP01: Drill/Exercise Performance-1 Sample (July 1, 2017, through December 31, 2017)
(2) EP02: Emergency Response Organization Drill Participation-1 Sample (July 1, 2017,
through December 31, 2017)
(3) EP03: Alert And Notification System Reliability-1 Sample (July 1, 2017, through
December 31, 2017)
INSPECTION RESULTS
No findings or violations were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors confirmed that proprietary information was controlled to protect from public
disclosure. No proprietary information was documented in this report.
4
On March 8, 2018, the inspectors presented the Emergency Preparedness Inspection
results to the Site Vice President, Ms. M. Marchionda, and other members of the licensee
staff.
DOCUMENTS REVIEWED
71114.01Exercise Evaluation (71114.01)
- EP-AA-1000; Exelon Nuclear Standardized Radiological Emergency Plan; Revisions 29
- EP-AA-1001; Exelon Nuclear Radiological Emergency Plan Annex for Braidwood Station;
Revision 34
- EP-AA-1001, Addendum 3; Emergency Action Levels for Braidwood Station; Revision 3
- EP-AA-111; Emergency Classification and Protective Action Recommendations; Revision 21
- EP-AA-111-F-02; Braidwood PAR Flowchart; Revision H
- EP-AA-112; Emergency Response Organization (ERO)/Emergency Response Facility (ERF)
Activation and Operation; Revision 18
- EP-AA-112-400; Emergency Operations Facility Activation and Operation; Revision 13
- EP-AA-113; Personnel Protective Action; Revision 13
- EP-AA-114; Notifications; Revision 14
- EP-AA-122; Drills and Exercise Program; Revision 19
- EP-AA-125-1001; EP Performance Indicator Guidance; Revision 9
- Two Years of Drill and Exercise Timelines; 03/2016-03/2018
- Braidwood 2016 NRC Exercise Evaluation Report; 04/27/2016
- Braidwood September 20, 2016 Focused Area Drill 2014 Evaluation Report; 09/23/2016
- Braidwood December 20, 2016 Emergency Exposure Drill Evaluation Report; 12/22/2016
- Braidwood 4th Quarter 2016 Performance Indicator Drills Report; 01/04/2017
- Braidwood 2017 2nd Half Health Physics Drill Findings and Observations Report; 11/23/2017
- Braidwood 2017 Core Damage Assessment Drill Report; 12/05/2017
- Braidwood 4th Quarter 2017 Performance Indicator Drills Report; 12/11/2017
- Two Year List of Drill and Exercise Corrective Action Program Issues; 03/2016-03/2018
- AR 02622561; EP DEP PI Drill Used Duplicate Players; 02/05/2016
- AR 02638642; Comments and Improvement Items from Jan-Feb EP Drills; 03/10/2016
- AR 02667962; Adverse Trend in DEP Failures/Needs Improvement in LORT; 05/11/2016
- AR 02679189; EPMedical Drill Issue; 06/08/2016
- AR 02718795; EPERO Focus Area Drill (FAD) Lessons Learned; 09/22/2016
- AR 03957101; EP12/20/2016 DEP Drill Lessons Learned; 12/28/2016
- AR 03970916; EPNear Miss on OYE Drill Scenario Confidentiality; 02/06/2017
- AR 04084139; Braidwood EP 12-13-2017 4th Quarter Call In Drill; 12/14/2017
- AR 04103315; Braidwood EP Pre-Exercise Failed Overall Objective J.1; 02/12/2018
- AR 04103318; Braidwood EP Pre-Exercise Failed Facility Objective B.6; 02/12/2018
71114.08Exercise EvaluationScenario Review
- Braidwood Station 2018 NRC Graded Exercise 60 Day Submittal; 12/20/2018
71151Performance Indicator Verification (71151)
- NRC Performance Indicator Data; Emergency PreparednessAlert and Notification System
Reliability; 3rd Quarter 2017-4th Quarter 2017
- NRC Performance Indicator Data; Emergency PreparednessNRC ERO Drill Participation;
3rd Quarter 2017-4th Quarter 2017
5
- NRC Performance Indicator Data; Emergency PreparednessDrill/Exercise Performance;
3rd Quarter 20174th Quarter 2017
- NEI 99-02; Regulatory Assessment Performance Indicator Guideline; Revision 7