ITAAC Closure Verification Process Office Instruction NRO-REG-103, Revision 1 Lauren Kent April 12, 2018 1

Major changes

  • Implementation experience and tabletop exercises used to update the OI
  • Eliminated 50% threshold non-targeted ITAAC
  • Eliminated potential problem category
  • Implemented public calls to resolve issues of insufficient information or ITAAC interpretations
  • Reduced use of insufficient information letters
  • Implemented submittal of multiple ICNs or UINs in a single package
  • Developed and implemented dashboards for ICN,IPCN,UIN metrics 2

ITAAC Closure Verification Process Submittal to

  • ICN NRC
  • UIN
  • IPCN Document
  • Accepts or rejects document Processing
  • Issues e-RIDS email NRO/DNRL
  • Checks for open licensing actions PM
  • Initiates VOICES Review
  • Requests technical review as needed Reviewer
  • Completes VEF or UINC Region II inspections Lead
  • Concurs on ITAAC Review complete Approver NRO/DNRL PM
  • Contact licensee as needed