Public Service Electric and Gas Company Stanley LaBruna Public Service Electric and Gas Company P.O. Box 236, Hancocks Bridge, NJ 08038 609-339-1200 Vice President - Nuclear Operations AUG 111992 NLR-N92108 U.S. Nuclear Regulatory Commission Attention:
Document Control Desk Washington, DC 20555 Gentlemen:
APPENDIX R CABLE WRAP STATUS UPDATE FACILITY OPERATING LICENSE NOS. DPR-70 AND DPR-75 SALEM GENERATING STATION UNIT NOS. 1 AND 2 DOCKET NOS. 50-272 AND 50-311 In our letter, NLR-N91056, dated April 4, 1991, Public Service Electric and Gas Company (PSE&G) committed to advise the NRC on the completion of engineering and installation milestones for the balance of our Appendix R Cable Wrap Project.
Please be advised that the milestones listed in Attachment 1, having been completed, mark the conclusion of the Cable Wrap Project for both Salem units.
This completed status was also verbally provided to NRC personnel-at a meeting in NRC Region I offices on July 9, 1992.
Should you have any questions, we will be pleased to discuss them with you.
Sincerely, Attachment C
Mr. T. T. Martin, Administrator USNRC Region I Mr. J. c. Stone USNRC Licensing Project Manager Mr. c. J. Anderson USNRC Region I Mr. T. P. Johnson USNRC Senior Resident Inspector Mr. K. Tosch, Chief Bureau of Nuclear Engineering New Jersey Department of Environmental Protection 92081801 91 920811
-- -- -'\\
.PDR ADOCK 05000272 i
P PDR I
i I
ATTACHMENT 1 MILESTONE COMPLETION Fire Area 1FA-EP-078C, Cable Reroute, DCP lEC-3118 Installation was completed on May 22, 1992,
- Service Water Valve Controls, DCP lEC-3098 Installation was completed on June 30, 1992, and Fire Area lFA-AB-lOOC, DCP lEC-3063 Installation was completed on July 8, 1992.
Installation completion dates are defined as the completion of the Design Change Package, Part "A" closeout checklists.