Public Service Electric and Gas Company Stanley LaBruna_.
Public Service Electric and Gas Company P.O. Box 236, Hancocks Bridge, NJ 08038 609-339-1200 Vice President - Nuclear Operations
. JUL 14 1992 NLR-N92090 U.S. Nuclear Regulatory Commission Attention:
Document Control Desk Washington, DC 20555 Gentlemen:
APPENDIX R CABLE WRAP STATUS UPDATE FACILITY OPERATING LICENSE NOS. DPR-70 AND DPR-75 SALEM GENERATING STATION UNIT NOS. 1 AND 2 DOCKET NOS. 50-272 AND 50-311 In our letter, NLR-N91056, dated April 4, 1991, Public Service Electric and Gas Company (PSE&G) committed to advise the NRC on the completion of engineering and installation milestones for the balance of our Appendix R Cable Wrap Project.
In continuation of our compliance with that commitment, please be advised that the milestones listed in Attachment 1 have been completed.
Should you.have any questions, we will be pleased to discuss them with you.
Sincerely, Attachment c,_
Mr. T. T. Martin, Administrator
. USNRC Region I Mr. J. c. Stone USNRC Licensing Project Manager Mr. c. J. Anderson USNRC Region I Mr. T. P. Johnson USNRC Senior Resident Inspector Mr. K. Tosch, Chief Bureau of Nuclear Engineering New. Jersey Department of Environmental Protection
,., ::; u ;1,1.,. ~~~72~g5~~ ~~Aa7;----
p PDR
JUL 14 1992 ATTACHMENT 1 MILESTONE COMPLETION Fire Area 1FA-AB-064B, DCP lEC-3071 - Installation was completed on April 13, 1992.
Fire Area 1FA-AB-084A, DCP lEC-3074 - Installation was completed on April 27, 1992.
- Fire Area 2FA-EP-078C Cable Reroute, DCP 2EC-3091 Installation was completed on March 13, 1992 (**),
- Service Water Valve Controls, DCP 2EC-3076 Installation was completed on March 25, 1992 (**),
Installation completion dates are defined as the completion of the Design Change Package, Part "A" closeout checklists.
Of special note, the two packages marked (**) above represent the completion of the Salem Unit No. 2 Cable Wrap Project.