Requests Schedular Relief from Installing Permanent Mod to RHR Sys Prior to End of 10th Refueling Outage to Address Provisions of NRC Bulletin 88-004 Re RHR Pump Interaction. New Design Will Be Installed During 11th Refueling Outage
ML18096A778
Person / Time
Site: Salem PSEG icon.png
Issue date: 05/29/1992
From: Labruna S
Public Service Enterprise Group
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
IEB-88-004, IEB-88-4, NLR-N92047, NUDOCS 9206170189
Download: ML18096A778 (2)


Text


------------

Public Service Electric and Gas Company Stanley LaBruna Public Service Electric and Gas Company P.O. Box 236, Hancocks Bridge, NJ 08038 609-339-1200 Vice President - Nuclear Operations

  • MAY 2 9 1992.

NLR-N92047 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

NRC BULLETIN 88-04 SCHEDULAR RELIEF SALEM GENERATING STATION UNIT NO. 1

. DOCKET NO. 50-272 By letter* (ref: NLR-N90172) dated August 31, 1990, Public Service Electric & Gas Company (PSE&;G) committed to installing a permanent modification to the Residual Heat Removal (RHR) System prior to the end of.the tenth refueling outage.

The purpose* of the modification was to address the Bulletin 88-04 concerns on RHR Pump interaction.

To address these concerns, the RHR trains will be isolated during minimum flow conditions identified.in the Bulletin.

Currently, this isolation is accomplished administratively. If the technical specification surveillance indicates a potential for shut off head conditions, one pump is tagged out of service and previously approved Emergency Operating Procedure changes are incorporated.

A permanent design change based on an interlock between the RHR.

Pump minimum flow valves and the RHR cross-connect valves is being developed.

During the development of the design change, an unreviewed safety question (USQ) for the new design was identified.

PSE&G attempted to resolve the USQ and complete the design change in time to allow installation during the tenth refueling outage.

When it became evident that the USQ could not be resolved and the final design completed for installation during the tenth refueling outage, PSE&G notified the NRR Project Manager by telephone that.they would be requesting a schedule change.

PSE&G plans to install the new design during the eleventh refueling outage, currently scheduled for November, 1993.

  • r t".1.'~ f"1,....)

~; \\.,! *~-* J 9206170189 920529

~DR ADOCK 05000272 PDR

Document Control Desk NLR-N92047 2

MAY 2 9. 1992 PSE&G will extend the administrative compensatory measures identified in the August 31, 1990 letter and currently in place, until the modification is completed during the eleventh refueling outage.

Should there be any questions with regard to this submittal, please do not.hesitate to contact us.

Sincerely, C

Mr. J. c. Stone.

Licensing Project Manager Mr. T. Johnson Senior Resident Inspector Mr. T. Martin, Administrator Region I Mr. Kent Tosch, Chief New Jersey Department of Environmental Protection Division of Environmental Quality Bureau of Nuclear Engineering CN 415 Trenton, NJ 08625