t.
I
~*
Public Service Electric and Gas Company
~ *.
Stanley LaBruna Public Service Electric and G~s Company P.O. Box 236, Hancocks Bridge, NJ 08038 609-339-1200 Vice President - Nuclear Operations IAY o 6 199Z NLR-N91105 LCR 91-08 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:
REQUEST FOR AMENDMENT REACTOR TRIP SYSTEM INSTRUMENTATION SALEM GENERATING STATION UNIT NOS. 1 AND 2 FACILITY OPERATING LICENSE NOS. DPR-70 AND DPR-75 DOCKET NOS. 50-272 AND 50-311 In accordance with the requirements of 10CFR50.90, Public Service Electric and Gas Company (PSE&G) hereby transmits.a request for amendment of Facility Operating Licenses DPR-70 and' DPR-75 for Salem Generating Station, Unit Nos. 1 and 2, respectively.
In accordance with 10CFR50.91 (b) (1) requirements, a copy of this request has been sent to the state of New Jersey.
The proposed amendment modifies Technical Specification 3/4.3.1 Reactor Trip System Instrumentation, Limiting Conditions for Operation, Action Requirements, and Surveillance Requirements, including associated tables.
The proposed changes contain administrative changes, provide consistency between Salem Units 1 and 2 and ensure technical accuracy. includes a description, reason, justification and significant hazards analysis for the proposed change. contains the Technical Specification pages revised with pen and ink changes..
_,,---92_0_5-18_0_1_8_3-----c9-:-::2=--:0:-::5::-0::-:6:--------:--\\
PDR ADOCK 05000272 p
PDR I I
Document Control Desk NLR-N91105
- lllAY O 6 1992 PSE&G has scheduled two refueling outages (Salem 1 and 2) during the first six months of 1992.
A significant number of our personnel resources are used to support these outages.
Therefore, we request that this amendment not be approved prior to June 30, 1992.
Also, due to the extensive procedure changes required, PSE&G is requesting a 120 day implementation period after amendment approval.
Should you have any questions regarding this transmittal, please contact us.
Sincerely, Attachments (2) c Mr. J. c. Stone Licensing Project Manager Mr. T. Johnson Senior Resident Inspector Mr. T. Martin, Administrator Region I Mr. Kent Tosch, Chief New Jersey Department of Environmental Protection Division of Environmental Quality Bureau of Nuclear Engineering CN 415 Trenton, NJ 08625