Suppl to Rev 3 to License Change Request 84-01 to Licenses DPR-70 & DPR-75,changing Action B to TS 3.3.3.8 & 3.3.3.9 Re Radioactive Liquid Effluent Monitoring Instrumentation & Gaseous Effluent Monitoring Instrumentation,Respectively
ML18096A653
Person / Time
Site: Salem  PSEG icon.png
Issue date: 04/20/1992
From: Labruna S
Public Service Enterprise Group
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML18096A654 List:
References
NLR-N92035, NUDOCS 9205010123
Download: ML18096A653 (3)


Text

Public Service Electric and Gas Company J

Stanley LaBruna Public Service Electric and Gas Company P.O. Box 236, Hancocks Bridge, NJ 08038 609-339-1200 Vice President - Nuclear Operations APR 2 O 1992 NLR-N92035 LCR 84-01, Rev. 3 Supplement United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

SUPPLEMENT TO REQUEST FOR AMENDMENT SALEM GENERATING STATION UNIT NOS. 1 AND 2 FACILITY OPERATING LICENSES DPR-70 AND DPR-75 DOCKET NOS. 50-272.AND 50-311 In accordance with the requirements of 10CFR5o'. 90, Public Service Electric and Gas Company (PSE&G) hereby transmits a request for

  • amendment of Facility Operating Licenses DPR-70 and DPR-75 for Salem Unit Nos. 1 and 2.

Pursuant.to the requirements of 10CFR50.91(b) (1), a copy of this request for amendment has been sent to the State of New Jersey.

This submittal supplements the changes proposed in PSE&G letter NLR-N90113, dated May 31, 1990.-

Action b. of Salem Unit 1 and 2 Technical Specifications 3.3.3.8 and 3.3.3.9, is being revised to change "operable" to "OPERABLE."

This proposed change would clarify that the term "OPERABLE, 11.as defined in Section 1 of the Technical Specifications, applies to the affected Action statements.

This proposed change does not involve any new interpretation of the Technical Specification operability requirements.

This_submittal also proposes a change to Salem Unit 2 Technical Specification Table 6.2~1, Minimum Shift Crew Composition.

The table includes footnotes to identify shift crew positions which may be satisfied by one individual for both'Salem units.

The footnotes as submitted in our May 31, 1990 letter state that certain individuals (filling Unit 2 shift positions) may also fulfill the requirements for Unit 2.

The proposed change would revise the footnotes to change "Unit 2 11 to "Unit 1, 11 which is consistent with the original intent of the footnotes and Unit 2 Amendment 33 as issued by the NRC. contains the revised Technical Specification pages.

For convenience, the changes to the affected pages, proposed in our letter dated May 31, 1990, have been included in the attachment.

/

9205010123 920420 ~

PDR ADOCK 05000272 P

PDR

~\\

Document Control Desk NLR-N92035 APR 2 0 1992 The changes proposed herein do not involve any changes to the intent of any Technical Specification requirements.

Therefore, the Determination of No Significant Hazards Consideration, provided in PSE&G's letter dated May 31, 1990, remains valid.

Attachment Affidavit c

Mr. J. c. Stone Licensing Project Manager Mr. T. Johnson Senior Resident Inspector Sincerely, Mr. T. Martin, Administrator Region I Mr. K. Tosch, Chief Bureau of Nuclear Engineering Department of Environmental Protection CN 415 Trenton, New Jersey 08625

I

. c*.* r1 REF:

NLR-N92035 STATE OF NEW JERSEY SS.

COUNTY OF SALEM Stanley LaBruna, being duly sworn according to law deposes and says:

I am Vice President - Nuclear Operations of Public Service Electric and Gas Company, and as such, I find the matters set forth in our letter dated APR 2 O 1992

, concerning the Salem Generating Station, Unit Nos. 1 and 2, are true to the best of my knowledge, information and belief.

  • My Commission expires on SHERRY l. CAGLE NOTARY PUBLIC OF NEW JERSEV My Commission Expires March 5, 1997