Advises That Engineering & Installation of Milestones for Balance of App R Cable Wrap Project,Listed on Encl, Completed
ML18096A539
Person / Time
Site: Salem  PSEG icon.png
Issue date: 02/21/1992
From: Labruna S
Public Service Enterprise Group
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NLR-N92018, NUDOCS 9202280121
Download: ML18096A539 (2)


Text

r--

Public Service Electric and Gas Company Stanley LaBruna Public Service Electric and Gas Company P.O. Box 236, Hancocks Bridge, NJ 08038 609-339-1200 Vice President - Nuclear Operations FE.B 2 1 *1992 NLR-N92018 U.S. Nuclear Regulatory Commission Attention:

Document Control Desk Washington, DC 20555 Gentlemen:

APPENDIX R CABLE WRAP STATUS UPDATE FACILITY OPERATING LICENSE NOS. DPR-70 AND DPR-75 SALEM GENERATING STATION UNIT NOS. 1 AND 2 DOCKET NOS. 50-272 AND 50-311 In our letter, NLR-N91056, dated April 4, 1991, Public Service Electric and Gas Company (PSE&G) committed to advise the NRC on the completion of engineering and installation milestones for the balance of our Appendix R Cable Wrap Project.

In continuation of our compliance with that commitment, please be advised that the milestones listed in Attachment 1 have been completed.

Should you have any questions, we will be pleased to discuss them with you.

Sincerely, Attachment c

Mr. T. T. Martin, Administrator USNRC Region I Mr. J. C. Stone USNRC Licensing Project Manager Mr. c. J. Anderson USNRC Region I Mr. T. P. Johnson USNRC Senior Resident Inspector Mr. K. Tosch, Chief Bureau of Nuclear Engineering New Jersey Department of Environmental Protection 9202280121 920221 PDR ADOCK 05000272 F

PDR

~ ---,

ATTACHMENT 1 MILESTONE COMPLETION

  • Fire Area 1FA-EP-078C, DCP lEC-3073 - Installation was completed on November 25, 1991,
  • Fire Area 2FA-EP-078C, DCP lEC-3065 - Installation was completed on January 17, 1992, and
  • Fire Area lFA-AB-lOOC, DCP lEC-3051 - Installation was completed on February 4, 1992.

Installation completion dates are defined as the completion of the Design Change Package, Part "A" closeout checklists.