Advises That Engineering & Installation for Balance of App R Cable Wrap Project Listed in Attachment 1 Have Been Completed
ML18096A402
Person / Time
Site: Salem  PSEG icon.png
Issue date: 12/19/1991
From: Labruna S
Public Service Enterprise Group
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NLR-N91197, NUDOCS 9112310233
Download: ML18096A402 (2)


Text

Public Service Electric and Gas Company Stanley LaBruna Public Service Electric and Gas Company P.O. Box 236, Hancocks Bridge, NJ 08038 609-339-1200 Vice President - Nuclear Operations DEC 1 9 1991 NLR-N91197 U.S. Nuclear Regulatory Commission Attention:

Document Control Desk Washington, DC 20555 Gentlemen:

APPENDIX R CABLE WRAP STATUS UPDATE FACILITY OPERATING LICENSE NOS. DPR-70 AND DPR-75 SALEM GENERATING STATION UNIT NOS. 1 AND 2 DOCKET NOS. 50-272 AND 50-311 In our letter, NLR-N91056, dated April 4, 1991, Public Service Electric and Gas Company (PSE&G) committed to advise the NRC on the completion of engineering and installation milestones for the balance of our Appendix R Cable Wrap Project.

In continuation of our compliance with that commitment, please be advised that the milestones listed in Attachment 1 have been completed.

Should you have any questions, we will be pleased to discuss them with you.

Sincerely, Attachment C

Mr. T. T. Martin, Administrator USNRC Region I f""*'i

  • r-4 C)

(.)

(. *.. /.

Mr. J. c. Stone USNRC Licensing Project Manager Mr. C. J. Anderson USNRC Region I Mr. T. P. Johnson USNRC Senior Resident Inspector Mr. K. Tosch, Chief Bureau of Nuclear Engineering New Jersey Department of Environmental Protection o::J -t 1 *-::* *-=* 1 ()"::* *-=* *":* -c, t 1 *-::* 1 *";;,*

~bR-~~65~( 6~)60i72 P

PDR

.~

ATTACHMENT 1 MILESTONE COMPLETION Fire Area 2FA-AB-064A, DCP 2EC-3050 - Installation was completed on October 17, 1991, Fire Area 1FA-MP-078I, DCP lEC-3075 - Installation was completed on October 25, 1991, and Fire Area 2FA-MP-078I, DCP 2EC-3067 - Installation was completed on October 25, 1991.

Installation completion dates are defined as the completion of the Design Change Package, Part "A", closeout checklists.