Enclosure - DOE Approval of GE-Hitachi Global Laser Enrichment LLC Classified Cyber Network
ML18095A830
Person / Time
Site: 07007016
Issue date: 04/09/2018
From: Mccune M
US Dept of Energy, Oak Ridge Operations Office
To: Jacob Zimmerman
Division of Fuel Cycle Safety, Safeguards, and Environmental Review
Bartlett M
Shared Package
ML18095A789 List:
References
Download: ML18095A830 (2)


Text

Department of Energy Nuclear Energy Oak Ridge Site Office P.O. Box 2001 Oak Ridge, Tennessee 37831 April 4, 2018 Mr. Jacob Zimmerman, Chief Enrichment and Conversion Branch Office of Nuclear Material Safety and Safeguards MS: 3WFN-13C64 U. S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Mr. Zimmerman:

APPROVAL OF GE HITACHI GLOBAL LASER ENRICHMENT, LLC CLASSIFIED CYBER NETWORK In the enclosed letter, Global Laser Enrichment, LLC (GLE) requested Department of Energy (DOE) continued Authorization To Operate (ATO) for the classified network identified in Program Cyber Security Plan - Engineering and Industrial Control System Environments for the GE Hitachi Global Laser Enrichment LLC Wilmington, NC Facilities (PCSP), GLEP-00015-R, Revision 5.1, approval for this PCSP, and approval for the Classified Distributive Information Network (CDIN), GLEP-00023-R, Revision 8.2.

The DOE Nuclear Energy Oak Ridge Site Office (NE-ORSO), acting as the Authorizing Official (AO) for the GLE classified cyber networks, approves PSCP, GLEP-00015-R, Revision 5.1, and CDIN, GLEP-00023-R, Revision 8.2. Based upon these approvals, DOE NE-ORSO approves GLEs request for continued ATO for the network identified in PSCP, GLEP-00015-R, Revision 5.1 for the processing up to, and including, Secret Restricted Data, with no change in the current ATO expiration date.

In order to re-authorize this classified network before the current November 2018 expiration date, GLE is requested to submit the 2018 Continuous Monitoring (CM) or CM Report to the Nuclear Regulatory Commission and DOE NE-ORSO prior to this November 2018 date. Once this Report is determined to be acceptable, DOE NE-ORSO, as AO, will be able to renew the ATO for the classified cyber network identified in PCSP, GLEP-00015-R, Revision 5.1, for an additional three (3) years.

If you have any questions, please contact me at (865) 576-2535 or Randall M. DeVault at (865) 241-8277.

Sincerely, Mary C. McCune, Acting Manager Nuclear Energy Oak Ridge Site Office Enclosure and ccs on Page 2

Mr. Jacob Zimmerman APPROVAL OF GE HITACHI GLOBAL LASER ENRICHMENT, LLC CLASSIFIED CYBER NETWORK

Enclosure:

- Letter from Pat Jenny, GLE Security/Licensing Manager, to Director, Division of Security Operations, U.S. Nuclear Regulatory Commission, (U) Request for Authorization to Operate, and Plan Approvals, dated February 22, 2018 (GLE-2018-0019) cc w/o enclosure:

R. DeVault, NE-OR3, NE-ORSO Q. Nguyen, SC-45.2, SC-OR S. Rice, NE-OR3, NE-ORSO M. Bartlett, NRC K. Everly, NRC