Public Service Electric and Gas Company ENCLOSURE 3 Steven E. Miltenberger Public Service Electric and Gas Company P.O. Box 236, Hancocks Bridge. NJ 08038 609-339-1100 v;ce Pres1aer.t a~o Chief Nuc!ear Otticer NOV O 5 1990 NLR-N90206 U.S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555 Gentlemen:
SYSTEMATIC ASSESSMENT OF LICENSEE PERFORMANCE (SALP) SALEM AND HOPE CREEK GENERATING STATIONS DOCKET NOS. 50-272, 50-311 AND 50-354 This is in response to your letter dated October 9, 1990, that transmitted the SALP Report and requested Public Service Electric and Gas Company (PSE&G) to provide written comments.
PSE&G is in agreement with the technical content of the Report, with the exception of one minor editorial change.
The Reactor Scrams and Unplanned Shutdowns section of the Hope Creek SALP incorrectly stated, under item number 2, that a similar failure and scram occurred in 1986.
The correct date is August 26, 1988.
Regarding the Board Recommendations and areas of weakness contained in the Salem SALP, PSE&G is currently involved in implementing both short and long-term actions to improve overall performance.
We believe that the short term actions already implemented, or in the process of implementation, will yield positive results during the upcoming year.
Our longer term efforts are focused on addressing large scope projects such as:
Plant Materiel Condition, Procedure Upgrade and Spare Parts/Procurement.
We have also enhanced our management strategy.
The responsibility for these large scope/long-term projects has been removed from line managers involved in the day-to-day station activities.
PSE&G has initiated programs and committed the necessary resources to improve the Salem Station.
We are monitoring our progress closely and expect to see positive results.
Document Control Desk NLR-N90206 2
NOV o 5 1990 Please contact us if you have any questions regarding this transmittal.
Sincerely, c
Mr. J. c. Stone Licensing Project Manager - Salem Mr. s. Dembek Licensing Project Manager - Hope Creek Mr. T. Johnson Senior Resident Inspector Mr. T. Martin, Administrator Region I Mr. Kent Tosch, Chief New Jersey Department of Environmental Protection Division of Environmental Quality Bureau of Nuclear Engineering CN 415 Trenton, N.J.
08625
t# **
PAGE Salem 26 ENCLOSURE4 ERRATA SHEET SALP BOARD REPORT ERRATA SHEET LINE
- NOW READS SHOULD READ 16 Scram in 1986
- Scram in 1988 Basis: This change reflects correction of an* administrative error.